Presentation is loading. Please wait.

Presentation is loading. Please wait.

Joint Outreach Team Implementation Plan July 12, 2013 10:30-11:30 a.m.

Similar presentations


Presentation on theme: "Joint Outreach Team Implementation Plan July 12, 2013 10:30-11:30 a.m."— Presentation transcript:

1 Joint Outreach Team Implementation Plan July 12, 2013 10:30-11:30 a.m.

2 Overview WelcomeMark Gabriel – Plan Purpose – General Execution Issues Implementation Plan Tony Montoya – Tier 1 – Tier 2 Questions Open 2

3 Welcome 3 Mark Gabriel Administrator

4 Plan Purpose Prioritize tasks and establish schedule Identify needs for customer and stakeholder collaboration Comply with request to submit implementation plan Meld recommendations into Western business, existing initiatives 4

5 General Execution Issues Incorporate into normal course of doing business Budget, costs and funding Collaboration and outreach Benefits Timing 5

6 Implementation Plan 6 Tony Montoya Chief Operating Officer

7 Tier 1: Immediate Implementation or Consideration 1A: Required Regulation Reserve Capacity 1B: OASIS Consolidation 1C: LGIP Revisions 1D: Rate-Setting Methodologies 1E: Combined Transmission System Opportunities 1F: Intra-hour Scheduling 1G: Efforts to Integrate VERs 7

8 1A: Required Regulation Reserve Capacity Description: Conduct analysis and develop consistent methodology for determining and reviewing regulation reserve capacity needed by each BA and sub-BA to meet requirements Actions: In progress Evaluating BPA’s method Received two BA results with others expected in October Will evaluate results and schedule periodic updates Expected completion: October 2013 8

9 1B: Common OASIS Description: Consolidate the four Western Interconnection OASIS sites into one Actions: In progress since 2011 Review business plan Create a charter and milestones Expected completion: June 2015 9

10 1C: LGIP Revisions Description: Revise and conform Western’s LGIP to implement recommendations from WestConnect’s Work Group Actions: Initiated May 2013 Includes specific recommendations by JOT Possible additional reforms Public process and FERC approval Expected completion: December 2014 10

11 1D: Rate-Setting Methodologies Description: Evaluate potential to standardize transmission and ancillary service rate methodologies Actions: Initiated May 2013 Phase 1: Survey existing methodologies Phase 2: Evaluate potential for standardization with customers Expected completion: December 2014 11

12 1E: Combined Transmission System Opportunities Description: Identify opportunities and interest for increased transmission integration within DSW, RM and CRSP Actions: Discuss opportunities with power and tariff customers, neighbors and partners Pursue only if there is sufficient interest in area Expected completion: 1-3 years 12

13 1F: Intra-hour Scheduling Description: Comply with FERC Order 764 Actions: In progress Coordination with other scheduling utilities Expected completion: November 2013 13

14 1G: Integrate VERs Description: Participate in efforts to identify and find solutions to support reliable, cost effective and efficient use of variable energy resources Actions: In progress Continue participation in field trials for new technologies (i.e. WECC initiatives) Participate in regional or sub-regional efforts (i.e. NWPP) Examine benefits of WAUE BA joining RTO Expected completion: Up to 2 years 14

15 Tier 2: Further Evaluation and Consideration 2A: New Transmission Products 2B: Transition from Contract Path to Flow Based 2C: Integrated Resource Planning Program 15

16 2A: New Transmission Products Description: Explore developing new, intra-regional, inter-regional, Western-wide transmission products Actions: In progress Update business case of redirecting service between Federal hydroelectric project transmission systems 16

17 2B: Transition to Flow Based Approach Description: Study achievability, cost and benefits of moving move from contract-path to flow-based approach Actions: Identify appropriate forum to discuss Include broad segment of transmission community within WECC 17

18 2C: Integrated Resource Planning Program Description: Evaluate compliance, quality and execution of EPAMP and IRP programs Actions: In progress with two parts Part 1: Implement automated tool for annual and five-year submissions—partially complete Part 2: Evaluate contractor’s findings and establish action plan 18

19 Questions? 19


Download ppt "Joint Outreach Team Implementation Plan July 12, 2013 10:30-11:30 a.m."

Similar presentations


Ads by Google