COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.

Similar presentations


Presentation on theme: "COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT."— Presentation transcript:

1 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT

2 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 2 Main events from the last CW (Granada) u INSTRUMENT é The Baffle The problem (eigen frequencies) is understood, thanks to a very strong involvement of ESA, CNES and CSL technical teams. New design of the feet Qualification is successful Flight Model is already manufactured & under integration é Integration & Test of the Instrument Flight Model has started in CNES- Toulouse Optical verification under progress First « Image » made with the telescope u SATELLITE é Mechanical & Thermal analyses have some delay because of late inputs from the launcher é Critical Design Review under progress é Conflict of resources with the CALIPSO mission

3 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 3 Main events from the last CW (Granada) u GROUND SEGMENT é Control Segment  nominal Command & Control : under Integration test Flight Dynamics : under interface tests é Mission Segment  some issues Very tight schedule Insufficient resources u SYSTEM & OPERATIONS é RIS (System Interfaces Review) Successful Main outcomes are  Conflicts of resources with the Calipso mission have to be closely managed  Exploitation Phase to be quickly assessed (tasks, responsibilities & resources é LAUNCHER contract has started with Arianespace & Starsem

4 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 4 Main events from the last CW (Granada) u SYSTEM & OPERATIONS é Reinforcement of the Network of Ground Stations é Delay of the Brasilian Ground Station Location Change from Natal to Alcantara No progress of interface definition for the last 6 months Discussions are slowly restarting é Search for alternatives Use of the MOST ground stations is under discussion Vienna ground station is the likely candidate

5 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 5 Planning

6 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 6 Milestones System PDR Oct 2003 Satellite PDR Jan 2004 Instrument CDR May 2004 System Interfaces Review March 2005 Satellite CDR April 2005 RPQT Satellite Qualification Review Flight Readiness Review LAUNCH Satellite I&T Readiness

7 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 7 Next 6 months roadmap u Delivery of the Flight Instrument u Delivery of the Flight Platform u Preparation & Start of the satellite assembly u Integration and test of the Ground Segment u Preparation of the System Tests u Preparation of operations u Prepration of the launch campaign é Ship & Shoot approach (~30 days) u Ground Stations é Secure the schedule the Alcantara ground station é Perform the compatibility tests with the (MOST) ground station in Vienna

8 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 8 Start the thinking of Post-Launch Activities u Flight Acceptance é At least 2 months é Development Expertise is required Technical assessment Trouble shooting u Exploitation é A minimal Development Expertise is to be maintained é Tasks and associated responsibilities are to be defined é Resources needed (incl.preparation of exploitation Manpower Money é Exploitation Cost sharing A dedicated Steering Committee has to be organized

9 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 9 Budget (qualitative) Status u Instrument expenses are under control (development is over) u Satellite é Overcosts are expected because of possible delays u System & Ground Segment é Launcher: nominal expenses é Control Centre : nominal expenses é Mission Centre : serious funding issues u The budget for Exploitation is not defined yet

10 COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 10 Synthesis & Conclusion u Technical issues é Normal work u Planning é The launch of Calipso mission is on the (Corot) critical path u Budget é To think of provision for shifts of planning é Mission Center (CMC) funding to be increased u Exploitation to be prepared é Organization é Funding and budget u Conclusion é Huge progress of the project, the dream is now reality é The COROT team is at full-speed é The count-down is still running é The COROT satellite is still planned to be launched by the 2006 summertime (NEXT YEAR)


Download ppt "COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT."