Presentation is loading. Please wait.

Presentation is loading. Please wait.

RARF Frequently Asked Questions from Resource Entities Ed Geer RARF Workshop III 8/29/2013.

Similar presentations


Presentation on theme: "RARF Frequently Asked Questions from Resource Entities Ed Geer RARF Workshop III 8/29/2013."— Presentation transcript:

1 RARF Frequently Asked Questions from Resource Entities Ed Geer RARF Workshop III 8/29/2013

2 2 Q: What is our Point of Interconnection – Substation Code? A: Generally, the substation where Resource Entity equipment connects to TSP equipment. Q: What are the acceptable ranges for Governor Droop Setting and Dead-band? A: Governor Droop Setting >= 0.02 and <= 0.05 Governor Dead-band <= 0.036 Q: What do we enter for Governor Droop Setting and Dead-band if our resource is exempted from providing governor response, or is a WGR currently in PRR833 ADR? A: Enter Governor Droop Setting of 5% (entered as 0.05) and Governor Dead-Band of 1 Hz. Questions about Data Items – UNIT Info tab

3 RARF Workshop III 8/29/2013 3 Q: What needs to be entered on the Reactive Capability tab? A: The actual gross leading and lagging reactive capability of the resource, specified at four MW output levels covering the full range of operation. Q: Should substation capacitors, reactors or other reactive devices be reflected in the Reactive Capability tab? A: No; substation capacitors, reactors or other reactive devices are modeled separately and are NOT included in the Reactive Capability tab. Enter the substation capacitors, reactors on the Capacitor and Reactor Data tab and dynamic reactive devices on the Static_Var_Compensator Data tab. Q: Where can we find more information about Resource Reactive Capability and Reactive Testing? A: Refer to the presentation posted with the June 14, 2013 Reactive Testing Workshop. Questions about Data Items – Reactive Capability tab

4 RARF Workshop III 8/29/2013 4 Q: What is needed for Positive Sequence Reactance? A: Synchronous Reactance – Xdi (unsaturated) and Xdv (saturated) Q: What sites need Collector System one-lines and collector system data? A: Currently only the Wind RARF has tabs for submitting Collector System one-lines and Collector system data. Future RARF form updates will add forms and tabs for Solar and Battery/Storage resources. Q: What is meant by “Zero Sequence Grounding Resistance For An Impedance Grounded Generator In P.u. (100 MVA Base)” A: The grounding of the generator through a resistor or reactance Questions about Data Items – Planning tab

5 RARF Workshop III 8/29/2013 5 Q: Do we need to change the RARF to reflect that we have a 3 -winding transformer? A: Case 1: No, if you have a buried tertiary or no connections to the tertiary winding, only enter Zero Sequence Data - Winding Connection Code =5. (Transformer Test Report must be submitted with RARF) Case 2: Yes, if you have a modeled generator, device or load connected to the tertiary or additional secondary winding (Transformer Test Report submitted with RARF) Q: Do we need to complete the Transformer Tap Settings tab for each transformer A: Yes, we need the high side and low side taps, if they exist. You would have one row on the spreadsheet for high side and one row for low side taps. For more information about transformer taps as modeled by ERCOT, please refer to the Key Documents posted for the August 9, 2011 Transmission Model Workshop. Q: What is meant by “Zero Sequence Grounding Resistance For An Impedance Grounded Transformer In P.u. (100 MVA Base)” A: The grounding of the transformer – if solidly grounded wye, then enter 0.0 for Grounding Resistance and Reactance. If ungrounded wye, enter 99999.0 for Grounding Resistance and Reactance. If wye grounded through a resistance or reactance, enter those values in per unit on 100 MVA base. Questions about Data Items – Transformer Data tab

6 RARF Workshop III 8/29/2013 6 Q: Can we use the positive sequence reactance for the transformer for the zero sequence reactance? A: Generally, the zero sequence reactance will be less than the positive sequence reactance, for example for core form transformers (Transformer Test Report submitted with RARF). Questions about Data Items – Transformer Data tab

7 RARF Workshop III 8/29/2013 7 Q: What are valid codes for the Zero Sequence Data - Winding Connection Code? A: Taken from Jay Teixeira’s October 29, 2012 RARF Workshop II presentation Item #6. Questions about Data Items – Transformer Data tab

8 RARF Workshop III 8/29/2013 8 Q: What is Planning Rate C for a line? A: The conductor 2 hour rating. Per Protocols: Conductor/Transformer 2-Hour Rating The two-hour MVA rating of the conductor or transformer only, excluding substation terminal equipment in series with a conductor or transformer, at the applicable ambient temperature. The conductor or transformer can operate at this rating for two hours without violation of National Electrical Safety Code (NESC) clearances or equipment failure. Questions about Data Items – Line Data tab

9 RARF Workshop III 8/29/2013 9 Q: Why do we need to submit all the embedded files (Dynamic Data, site one-lines, collector system one-lines) and attached files (Transformer Reports) every time we submit a RARF update? A: The files must be embedded or attached with each submittal because we don’t have an incremental update system – ALL RARF data is submitted on each RARF update. Each RARF submittal must be a complete stand-alone package (zip file with all forms and associated files). Questions about RARF Submission

10 10 Additional Questions?


Download ppt "RARF Frequently Asked Questions from Resource Entities Ed Geer RARF Workshop III 8/29/2013."

Similar presentations


Ads by Google