One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Southern WV 340 Environmental Infrastructure Program Sherry.

Similar presentations


Presentation on theme: "One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Southern WV 340 Environmental Infrastructure Program Sherry."— Presentation transcript:

1 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Southern WV 340 Environmental Infrastructure Program Sherry Adams 340 Program Manager

2 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Raleigh Mercer Greenbrier Pocohontas Wayne McDowell Cabell Summers Monroe Wyoming Logan Fayette Boone Lincoln Webster Krouts Creek Gilbert Pageton Mercer Co. and Oakvale Road Fayette County Mingo Kilsyth Boone County Cool Ridge / Flattop and Piney Creek Nicholas Southern WV Environmental Infrastructure Section 340 Marsh Fork

3 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Southern WV Environmental Infrastructure – Section 340 Authorized by WRDA 92 (Sec. 340) Amended by WRDA 96 (Sec. 359) Amended by WRDA 99 (Sec. 368) Increased authority to $40M Amended by WRDA 2000 (Sec. 550) 75 / 25% cost share Inventory of needs – $1.1B Scope Water and wastewater Surface water resource protection and development Environmental restoration $20.2M Appropriated thru FY 05 $750K Appropriated in FY 06 (Corps) $2M ARC

4 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Kilsyth / Mt. Hope Environmental Infrastructure Water quality improvement project Part of a comprehensive watershed restoration plan for Dunloup Creek Phase I – Design of Kilsyth Collection System and upgrade of Mt. Hope wastewater treatment plan (WWTP) Phase II – Construct WWTP upgrade at Mt. Hope Phase III – Construct Kilsyth collection system Total Corps Project Cost – $2.5M Design cost – $340K Construction cost – $2.1M Local Sponsor – City of Mt. Hope (25%) Source of Non-Federal funds – SCBG, DEP Stream Restoration Funds, SRF Loan Current Status Initiate Phase II – Mt. Hope WWTP construction

5 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Cool Ridge / Flat Top Environmental Infrastructure Construction of new WWTP, pump station, force main and collection system Total Corps Project Cost – $3.6M Local Sponsor – Shady Spring PSD (25%) Source of Non-Federal funds – SRF Loan, IJDC Loan, Flat Top Lake Grant Current Status Initiated construction Dec 05

6 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Boone County PSD Environmental Infrastructure New WWTP and collection system to improve local environment Total Corps Project Cost Design Cost - $450K Construction Cost - $2M Local Sponsor – Boone County PSD (25%) Source of Non-Federal funds – SCBG, ARC grant, IJDC loan, IJDC grant Current Status Execute construction agreement and initiate construction of WWTP

7 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Krouts Creek Environmental Infrastructure Stormwater diversion 5 x 9 underground box culvert 1,250 feet long Total Project Cost – $3.3M Local Sponsor – City of Huntington (25%) Source of Non-Federal funds – WVCA, City of Huntington Current Status Complete construction Mar 06

8 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Piney Creek Interceptor Environmental Infrastructure Replacement of gravity sewer line In close proximity to Whitestick Creek and runs through the incorporated Town of Mabscott Total Corps Project Cost – $1.3M Local Sponsor – Beckley Sanitary Board (25%) Source of Non-Federal funds – Beckley Sanitary Board Current Status Execute design / construction agreement Feb 06 Initiate construction Mar 06

9 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Oakvale Road PSD Environmental Infrastructure Water system extension/upgrade to Southern Hollow Road Serves 30 new customers Additional phases allow potential of providing water service and fire protection to another 1,100 customers Total Project Cost – $830K Local Sponsor – Oakvale Road PSD (25%) Source of Non-Federal funds – State Digest, WVAWC, Mercer Co. Commission, IJDC Grant Current Status Initiate construction Mar 06 Complete construction Aug 06

10 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Completed 340 Environmental Infrastructure Projects 340 ProjectsTotal Project Cost (000s) Date PCA Executed Date Complete Gilbert Sewer (Design)$209Jun 95Dec 97 Gilbert Sewer (Construction)$3,107Mar 98Dec 99 Mercer Water (Design)$209Aug 95Jun 98 Mercer Water (Construction)$2,333Sep 98Mar 01 Krouts Creek (Design)$344Dec 98Sep 00 Pageton (Design)$156Oct 99Jun 01 Pageton (Construction)$2,367Sep 01Sep 02 Fayette Co. Wastewater (Design) $2,367Sep 99Aug 01

11 One Team – Relevant, Ready, Responsive, Reliable US Army Corps of Engineers Huntington District Questions