Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chapter 16 Inventory Systems for Dependent Demand

Similar presentations


Presentation on theme: "Chapter 16 Inventory Systems for Dependent Demand"— Presentation transcript:

1 Chapter 16 Inventory Systems for Dependent Demand
Master production schedule Material Requirements Planning (MRP) System structure Example MRP II MRP/JIT 2 2 2

2 Material Requirements Planning
How much of an item is needed? When is an item needed to complete a specified number of units... in a specified period of time? Dependent demand drives MRP 3 3 3

3 Introductory Example - Dependent Demand
Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Product Structure Tree for Assembly A B(4) E(1) D(2) C(2) F(2) D(3) A Demand Day A Day B (Spares) Day D (Spares) Create a schedule to satisfy demand. 4 4 4

4 LT = 1 day Irwin/McGraw-Hill The McGraw-Hill Companies, Inc., 1998 5 5

5 LT = 2 Spares B(4) E(1) D(2) C(2) F(2) D(3) A Irwin/McGraw-Hill
6 Irwin/McGraw-Hill The McGraw-Hill Companies, Inc., 1998 6 6

6 B(4) E(1) D(2) C(2) F(2) D(3) A Part D: Day 6 40 + 15 spares
7 Irwin/McGraw-Hill The McGraw-Hill Companies, Inc., 1998 7 7

7 Master Production Schedule (MPS)
Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan (Product Groups) MPS (Specific End Items) 8 8 8

8 Time Fences Frozen Moderately Firm Flexible
No schedule changes allowed within this window Moderately Firm Specific changes allowed within product groups as long as parts are available Flexible Significant variation allowed as long as overall capacity requirements remain at the same levels 9 9 9

9 Forecast and available
Time Fences 8 15 26 Weeks Frozen Moderately Firm Flexible Firm Customer Orders Forecast and available capacity Capacity 10 10 10

10 Material Requirements Planning
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items Determines exact numbers needed Determines the dates when orders for those materials should be released, based on lead times 11 11 11

11 Firm orders from known customers Forecasts of demand from random
Aggregate product plan Engineering design changes Bill of material file Inventory transactions record file Master production schedule (MPS) Material planning (MRP) Reports Irwin/McGraw-Hill 12 The McGraw-Hill Companies, Inc., 1998 12 12

12 Bill of Materials (BOM) File A Complete Product Description
Parts Components Production sequence Modular BOM Subassemblies Planning BOM Fractional options 13 13 13

13 Inventory Records File
Each inventory item carried as a separate file See, for example, Exhibit 16.15 Status according to “time buckets” Pegging Identify each parent item that created demand 14 14 14

14 Primary MRP Reports Planned orders Order release notices
to be released at a future time Order release notices to execute the planned orders Changes in due dates of open orders due to rescheduling 15 15 15

15 Primary MRP Reports Cancellations or suspensions of open orders
due to cancellation or suspension of orders on the master production schedule. Inventory status data 16 16 16

16 Net Change System Activity driven Net change schedules
Potential for system nervousness 17 17 17

17 Another MRP Example A(2) B(1) D(5) C(2) X C(3)
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10 plus the following spares: 18 18 18

18 Adding some more terminology
Gross Requirements On-hand Net requirements Planned order receipt Planned order release 19 19 19

19 A(2) B(1) D(5) C(2) X C(3) 20 Irwin/McGraw-Hill 20 20

20 21 Irwin/McGraw-Hill 21 21

21 Manufacturing Resource Planning (MRP II)
Goal: Plan and monitor all resources of a manufacturing firm (closed loop): manufacturing marketing finance engineering Simulate the manufacturing system 23 23 23


Download ppt "Chapter 16 Inventory Systems for Dependent Demand"

Similar presentations


Ads by Google