Presentation is loading. Please wait.

Presentation is loading. Please wait.

Material Requirements Planning ISQA 459 Class 4 Mellie Pullman.

Similar presentations


Presentation on theme: "Material Requirements Planning ISQA 459 Class 4 Mellie Pullman."— Presentation transcript:

1 Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

2 Materials Requirements Planning Material Requirements Planning (MRP) MRP Logic and Product Structure Trees MRP Example Lot Sizing in MRP Programs

3 Material Requirements Planning Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials needed to produce a product. MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced. Dependent demand drives MRP. MRP is a software system.

4 Example of MRP Logic and Product Structure Tree B(4) E(1)D(2) C(2) F(2)D(3) A Product Structure Tree for Assembly A Lead Times A1 day B 2 days C1 day D 3 days E4 days F1 day Demand Day A Day 8 20 B (Spares) Day 6 15 D (Spares) Given the product structure tree for A and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed.

5 LT = 1 day First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A in the 9 th week to receive them in the 10 th week.

6 Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time. Spares LT = 2 B(4) E(1)D(2) C(2) F(2)D(3) A 4x50=200

7 B(4) E(1)D(2) C(2) F(2)D(3) A spares Part D: Day 6 Finally, repeating the process for all components, we have the final materials requirements plan: 7

8 Material Requirements Planning System Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items. Determines exact unit numbers needed. Determines the dates when orders for those materials should be released, based on lead times.

9 Firm orders from known customers Forecasts of demand from estimates Aggregate product plan Master production schedule (MPS) Material planning (MRP) Engineering design changes Bill of material file Inventory transactions Inventory record file Reports 9

10 Bill of Materials (BOM) File A Complete Product Description Materials Parts Components Production sequence Modular BOM Component or Subassemblies BOM Planning BOM or kits create an artificial parent to the BOM used for inexpensive items like washers or pins to group. Explosion: revealing the requirements for each component.

11 Coding If identical items exist at various levels in the BOM: Item is coded at lowest level at which it occurs D (Level 2 or Level 3) This number identifies the part at the lowest level of usage. A B DE C EF GD

12 Inventory Records File Buckets= time units in MRP system Week bucket vs. day bucket Each inventory item carried as a separate file Status according to time buckets. Pegging Identify each parent item that created demand. Parent vs. child Parent= Items above the current level Child = Items below the current level

13 Primary MRP Reports Planned orders to be released at a future time. Order release notices to execute the planned orders. Changes in due dates of open orders due to rescheduling. Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule. Inventory status data.

14 Secondary MRP Reports Planning reports, for example, forecasting inventory requirements over a period of time. Performance reports used to determine agreement between actual and programmed usage and costs. Exception reports used to point out serious discrepancies, such as late or overdue orders.

15 Additional MRP Scheduling Terminology Gross Requirements: needed during each period. Scheduled Receipts: Existing orders that arrive at beginning of period. On-hand or available balance: (depending on software convention, could be at the beginning of each period or end): Book: Inventory balance at end of each period. Net requirements: What is need to meet requirements and safety stock. Planned order receipt: arrives at beginning of period. Planned order release: Addresses lead time.

16 MRP Examples

17 Closed Loop MRP Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning Realistic? No Feedback Execute: Capacity Plans Material Plans Yes Feedback

18 Lot Sizing in MRP Programs Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC) Part Period Balancing-changing lot sizes to reflect requirements in the future (how many periods should be combined to reduce cost)

19 MRP Game Different types of lot sizes

20 Tinker Toy Lawn Mower


Download ppt "Material Requirements Planning ISQA 459 Class 4 Mellie Pullman."

Similar presentations


Ads by Google