Presentation is loading. Please wait.

Presentation is loading. Please wait.

DOM 301 : Operations Management Practice

Similar presentations


Presentation on theme: "DOM 301 : Operations Management Practice"— Presentation transcript:

1 DOM 301 : Operations Management Practice
Master Production Schedule Materials Requirement Planning Manufacturing Resource Planning By; Munyao Mulwa Dept Management Science

2 Master Production schedule
MPS is the plan that a company develops for production, inventory, staffing, etc.   Sets the quantity of each end item to be completed in each week over short-range planning horizon.

3 Master Production schedule
A statement of production, not a statement of market demand MPS takes into account capacity limitations, as well as desires to utilize capacity fully Stated in product specifications – in part numbers for which bill of material exist Since it is a build schedule, it must be stated in terms used to determine component part needs and other requirements; not in monetary or other global unit of measure

4 Master Production schedule
An effective MPS provides Basis for making customer delivery promises Utilizing plant capacity effectively Attaining the firm’s strategic objectives as reflected in the production plan and Resolving trade-off between manufacturing and marketing

5 Master Production schedule
MPS INPUTS: Forecast Demand Production Costs Inventory Costs Customer Orders Inventory Levels Supply Lot Size Production Lead Time capacity

6 Master Production schedule
MPS OUTPUT (production plan): Amounts to be Produced Staffing Levels Quantity Available to Promise Projected Available Balance

7 What to produce When to produce How much to produce
Firm orders from known customers Forecasts of demand from random Aggregate production plan What to produce When to produce How much to produce Inventory record file Engineering design changes Bill of material file Master production schedule (MPS) Material planning (MRP) Reports 12 12 12

8 Structured Approach to Master Scheduling
• Select the items and /or levels in the product structure to be included in the master schedule • Determine the time horizon and time fences for the master schedule • Obtain demand information for each item in the schedule over the time horizon • Prepare tentative master schedule • Perform rough-cut capacity planning on the tentative master schedule • Revise the tentative master schedule so it is capacity feasible

9 Time Fences Frozen Moderately Firm Flexible
No schedule changes allowed within this window Moderately Firm Specific changes allowed within product groups as long as parts are available Flexible Significant variation allowed as long as overall capacity requirements remain at the same levels 9 9 9

10 Forecast and available
Time Fences 8 15 26 Weeks Frozen Moderately Firm Flexible Firm Customer Orders Forecast and available capacity Capacity 10 10 10

11 Master Schedule stability
Freezing and time fencing concepts are used for stability No changes (or changes only after tougher negotiations) incorporated in certain number of recent periods of the schedule in the case of freezing Frozen period provides a stable target for manufacturing to hit Time fences specify periods in which various types of changes can be handled Two common fences are demand fence and planning fence, demand fence is the shorter of the two 9 9 9

12 Examples of MPS MPS using Level Strategy Week 1 2 3 4 5 6 7 8 9 10 11
Week 1 2 3 4 5 6 7 8 9 10 11 12 Forecast 15 Available 25 30 35 40 45 50 20 MPS On hand 9 9 9

13 Examples of MPS MPS using Chase Strategy Week 1 2 3 4 5 6 7 8 9 10 11
Week 1 2 3 4 5 6 7 8 9 10 11 12 Forecast 15 Available 20 MPS On hand 9 9 9

14 Material Requirements Planning (MRP)
Material Requirements Planning (MRP) is a computer-based production planning and inventory control system. It is a material control system that attempts to keep adequate inventory levels to assure that required materials are available when needed MRP is applicable in situations of multiple items with complex bills of materials (dependent) demand items 9 9 9

15 Objectives of an MRP system
Ensure the availability of materials, components, and products for planned production and for customer delivery, Maintain the lowest possible level of inventory Plan manufacturing activities, delivery schedules, and purchasing activities. 9 9 9

16 Product Tree Structure (BOM)
Product Structure Tree for Assembly of Meter A LT Inventory A 2week C 1 week D 1 week Safety stock for A, C & D = 20, 30 & 120 respectively D(1) C(1) D(2) A Level 0 Level 1 Level 2 Demand for meter type A Week 42 = 200 Meters Required; Create a schedule to satisfy demand, stating any assumptions made 4 4 4

17 Manufacturing Resource Planning (MRP II)
Goal 1: Plan and monitor all resources of a manufacturing firm – manufacturing, marketing, finance, engineering etc firm in a closed loop system generating financial figures Goal 2: Simulate the manufacturing system. Generate what if scenarios 23 23 23

18 Manufacturing Resource Planning (MRP II)
The fundamental manufacturing equation is; What are we going to make? What does it take to make it? What do we have? What do we have to get? Using the example of Meter Type A, answer the above questions 23 23 23


Download ppt "DOM 301 : Operations Management Practice"

Similar presentations


Ads by Google