Asphalt Roadway Daily Report of Quality Control (Form No. 675-030-20) A step by step guide.

Similar presentations


Presentation on theme: "Asphalt Roadway Daily Report of Quality Control (Form No. 675-030-20) A step by step guide."— Presentation transcript:

1 Asphalt Roadway Daily Report of Quality Control (Form No. 675-030-20) A step by step guide

2

3

4

5

6

7

8

9

10

11

12

13

14 This is calculated from the Gmm on the Mix Design. It is Gmm times 43.3 times thickness of the lift.

15

16

17

18 Automatic Calculation

19

20 Automatic Calculation

21 Automatic Calc. If within tolerance, # is Blue, if not # is Red

22 New sublot MUST be started on separate line

23

24

25

26 Automatic Calculation

27

28 If spread is within the allowable tolerance, # is Blue, if not # is Red. If out tell Foreman and document it in the Remarks at the bottom of the page.

29

30 Proper number and correct spacing is VERY important!

31 Enter previous tons, Sq. Yards & Tons in This Lot

32 These daily totals go here Automatic calculation

33 Input the waste from the days production Automatic calculation

34 These Tonnages Are Totals for This Pay Item

35 Density Required Previous Tonnage: Today’s Tonnage: Total Density Required:

36 No Density Required Previous Tonnage: Today’s Tonnage: No Density Required Total Tonnage:

37 These 2 numbers must equal this one: These 3 numbers must equal this one:

38 Compaction Temperature from Mix Design

39 Avg. of all temperatures, Max. temp of the day, Min. temp. of the day & Avg. temp of the 1 st 5 loads.

40 Enter pay item for tack. If tack is included in the price of the asphalt, enter the pay item for the type of asphalt being placed. Prime calculations can be entered here if prime is being used

41 Enter the type of tack being used.

42

43 Enter the distributor number (FDOT calibration number) that is being used to place the tack. (From previous slide)

44 Look up beginning depth reading and the corresponding gallon reading

45 Enter the beginning measurement and the corresponding gallons from the tack chart. REMEMBER: NO CHART~NO START

46 Look up ending depth reading and the corresponding gallon reading

47 Enter the ending measurement and the corresponding gallons from the tack chart after tack is shot. This is an automatic calculation. (Beginning gallons minus ending gallons.)

48 Enter the time you finished shooting the tack and the temperature of the tack from the distributor.

49 Look up temp. on chart and select corresponding Correction Factor.

50 Enter the correction factor for the temperature of the tack.

51 Enter the previous gallons of tack. Automatic calculations. Net gallons * Corr. Factor. & sum of previous gallons plus today's gallons.

52 Enter the Square Yards covered with tack. Automatically calculates tack spread rate.

53 Enter your T.I.N. #

54 Enter any addition remarks about the days production

55 Areas that Vary in Width How to calculate them How to show them on the report

56 See remarks below for explanation of difference in shoulder width

57

58

59 Base How to calculate them How to show them on the report

60

61 Take total S.Y. and divide it by the number of lifts that the base will be placed in That is the prorated S.Y. for lift 1 of 3. Show calculations in remarks. No density required on 1 st lift of base

62

63 Low Pay Factor Material How it is calculated How to show it on the report

64

65

66

67 Asphalt Guidelines Roadway VT responsibilities Roadway QC responsibilities

68

69

70

71

72

73

74

75

76

77 Asphalt Roadway Verification Report (Form No. 675-030-21) A step by step guide

78 Fill in all the above correct information: 1. Page No: 2. Fin Project ID: 3. Material No: 4. Type of Mix: 5. Mix Design: 6. Intended Use: 7. Plant No: 8. Lot No: 9. Intended Lot Size:

79 Enter in Your Target Spread Rate

80 Fill in all the above correct information: 10. Date 11. Sublot 12. Lane/ Lift # of # 13. Station to Station 14. Loads # 15 (LOADS) This is an automatic calculation. Verification of Spread Rate

81 Fill in all the above correct information: 16. Width 18. Tons # 15 (LINEAR FEET), 17 (S.Y.) & 19 (SPREAD RATE) Are all automatic calculations. If measurement “Meets” tolerance y for yes and N for no (see spec 330- 2.2 & 300-8.4

82 Record of Bituminous Material Box Record the date and sublot from the above information Record the 21. Pay Item 22. Grade of Asphalt 23. FDOT Calibration chart Verify Tack Spread Rate Once Per Day (CPAM 5.10)

83 Record the 24. Beginning Measurement 25. Gallons 26. End Measurement 27. Gallons

84 Record the 28. Time of Day After Unloading 29. Temperature of Tack 31. Correction Factor 33. Square Yard Automatic Calculations 30. NET Hot Gallons 32. Gallons/ Liters @ 60*F

85 Verification Results “Y” for yes/ “N” for no Refer to Spec 300-8.4 If there is NO verification, you need to communicate with the QC Tech, and come up with a resolution.

86 Verify Tack Spread Rate Once Per Day (CPAM 5.10) Temperature Verification 36. Load number (from the truck the Temperature was taken) 37. Temperature (CPAM 5.10-11.3) Temperatures

87 Qualified Technician ID# First nine characteristics of FLA ID# Input Any Remarks for the Day’s production

88

89

90

91

92

93

94

95

96

97

98

99

100

101

102

103

104

105


Download ppt "Asphalt Roadway Daily Report of Quality Control (Form No. 675-030-20) A step by step guide."

Similar presentations


Ads by Google