1 Ground Safety Review – Phase II September 8-10, 2008 Phil Mott
AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE Ground Safety Review – Phase II September 8-10, 2008 Phil Mott Phil Mott AMS-02 GSR Phase II

2 Documents Governing GHE Design
KHB C Space Shuttle Payload Ground Safety Handbook SW-E-0002E Ground Support Equipment General Design Requirements NASA-STD formerly NSS/GO B Standard for Lifting Devices and Equipment Phil Mott AMS-02 GSR Phase II

3 Primary Support Stand (PSS)
Used for payload integration and shipping Two configurations: Low & High Constructed with Aluminum 6061 Covers are Alumalite (painted aluminum face sheet with plastic corrugate) Factors of Safety 2 on yield 3 on ultimate Phil Mott AMS-02 GSR Phase II

4 Primary Support Stand (PSS) – Low Configuration
Shipping Configuration 195” x 125” x 117” high Top Cover is removed as one piece Phil Mott AMS-02 GSR Phase II

5 Primary Support Stand (PSS) – High Configuration
Assembly/Integration Configuration 195” x 125” x 166” high Phil Mott AMS-02 GSR Phase II

6 Primary Lifting Fixture (PLF)
Used to lift the PSS and AMS-02 Welded steel A36 structure WLL: 26,800 lbs Factors of Safety 3 on yield 5 on ultimate Initial proof load to 2X WLL Annual load test to 1X WLL Phil Mott AMS-02 GSR Phase II

7 Multi Purpose Lifting Fixture (MPLF)
Used to lift the Lower USS (LUSS) into place on the Upper USS and to lift the PAS into place for attachment Welded steel A36 structure WLL: lbs Factors of Safety: 3 on yield 5 on ultimate Initial proof load to 2X WLL Annual load test to 1X WLL Phil Mott AMS-02 GSR Phase II

8 Lower USS (LUSS) Shipping Fixture
Used to ship/move/install the Lower USS Can be moved with forklift or crane/MPLF Welded steel A36 structure Phil Mott AMS-02 GSR Phase II

9 Can be moved with forklift, crane, air pallet, hand carts, or by hand
Other Hardware Can be moved with forklift, crane, air pallet, hand carts, or by hand All lifting hardware will meet NASA-STD Master Dewar Transfer Dewar Valve Box L Valve Box S Control System (5 racks) Pumps (2) Heat Exchanger Hoses, Stands, Fittings, Etc Power Supply (2) Chiller PVVV Vacuum Pump UPS’s Numerous computers Toolboxes (2) Fans TRD GSE Air Supply/Compressor K Bottles Phil Mott AMS-02 GSR Phase II

10 Assembly Operations Phil Mott AMS-02 GSR Phase II

11 Arrival at KSC – Unload/Prep in the SSPF Airlock
Crane PSS/Upper USS-02. Fork/Crane Lower USS-02 Fork/Crane all other Hardware including CGSE Phil Mott AMS-02 GSR Phase II

12 Arrival at KSC – Unload/Prep in the SSPF Airlock (cont)
Phil Mott AMS-02 GSR Phase II

13 Move Into SSPF – Footprint 7
Crane or air pallet PSS/USS-02 Crane, fork, or air pallet all other hardware Phil Mott AMS-02 GSR Phase II

14 Unpacking Remove the upper cover from the PSS using the MPLF or slings
Remove the side panels from the PSS Remove the cover from the LUSS Shipping Fixture Set up Cryosystem GSE (CGSE) Phil Mott AMS-02 GSR Phase II

15 PSS Preparation for AMS-02 Assembly/Integration
Install Upper Columns and Beams on the PSS Phil Mott AMS-02 GSR Phase II

16 PSS Preparation for AMS-02 Assembly/Integration
Raise the PSS/Upper USS-02 to the high position Install supports Phil Mott AMS-02 GSR Phase II

17 Installation of the Lower USS onto the Upper USS
Fork the Lower USS under the Upper USS in the PSS Phil Mott AMS-02 GSR Phase II

18 Installation of the Lower USS onto the Upper USS (cont)
Lift the Lower USS into position using the MPLF Position hydraulic jacks under the Lower USS for support and final positioning Attach Lower USS to Upper USS with pins and bolts Phil Mott AMS-02 GSR Phase II

19 Installation of the PAS
Weight of PAS = 220 lbs PAS will be installed using the LUSS, overhead crane, and bottle jacks PAS EBCS Phil Mott AMS-02 GSR Phase II

20 Installation of the PAS (cont)
Procedure similar to Lower USS installation – Details in work Place PAS on top of LUSS Shipping Fixture Place under payload using forklift Raise and rotate using bottle jacks Phil Mott AMS-02 GSR Phase II

21 Installation of the Keel
Weight of Keel = 67 lbs Keel will be a 2 person manual lift and bolts installed by a 3rd person Phil Mott AMS-02 GSR Phase II