Presentation is loading. Please wait.

Presentation is loading. Please wait.

Martin Luther King, Jr. Blvd. Viaduct, Portland Project Background and Today’s Design Status.

Similar presentations


Presentation on theme: "Martin Luther King, Jr. Blvd. Viaduct, Portland Project Background and Today’s Design Status."— Presentation transcript:

1 Martin Luther King, Jr. Blvd. Viaduct, Portland Project Background and Today’s Design Status

2 Location – Looking Southeast

3 Closer View - Looking Southeast

4 Historic Background - MLK MLK (Union Ave.) built 1938 –H-15 Design Live Load

5 Historic Background – Grand Grand Ave. built 1964 –HS-20 Design Live Load

6 Viaduct – looking SE (late 1930’s)

7 Viaduct – Below (late 1930’s)

8 Grand Ave. w/ MLK Looking SW

9 Grand Ave. Looking N. at Caruthers

10 Stairway, N. Side of Caruthers

11 Early Problems Crosses Filled-In Slough –Wood Waste Timber Piles Not Driven Deep Enough Partial Structure Settlement ACWS Added to Raise Grade Jacking Attempt after cutting columns. Instead of raising the structure, it lowered the footings.

12 Sunken Area – Looking NW

13 Today’s Conditions Structure Settlement, Translation & Deterioration Sufficiency Ratings –MLK 19, Grand Ave. 60 (out of 100) SB Weight Restrictions (50,000 lb) Ongoing Maintenance

14 MLK Sunken Span & Concrete

15 Bent 26 – Before Repair Apr. ‘02

16 Beam Support Repairs

17 Column Repairs 2001-2002

18 Column Repairs 2001-2002 cont.

19 Stakeholder & Architectural Goals 1 Environmental Assessment & 4(f) Evaluation Process 2001-2002 Design Review Advisory Committee (DRAC) Improved Vehicular Access Improved Ped. & Bike Access Traffic Calming Landscaping, Planters on Structure

20 Stakeholder & Architectural Goals 2 Access to Springwater Trail Gateway to SE Portland Appearance Reminiscent of Existing Structure –Shorter, Haunched Spans 24 m (80 ft) –Deck Overhangs –Historic Lighting Fixtures Historic Interpretive Signs (in pylons) Improved Ped. & Bike Access

21 Stakeholder & Architectural Goals 3 Architectural Rails –Open for Outward Visibility –“Not like the Ross Island Bridge” –Must meet LRFD Strength & Performance –Similar to FHWA Crash-Tested Rail –FHWA Concurrence Keep Adjacent Businesses Open Cross Existing UPRR Future Light Rail Transit Beneath

22 Near Ivon St. Looking North (1930’s)

23 Gateway Rendering 2001

24 Rail Mockup w/ Light Pole

25 Bridge Replacement Concept Studies (1999-2001) Replace MLK Structure on Existing Alignment Highway Standards –45 mph, 3.6 m Lanes, Std. Metal Rails Prestressed Concrete Girders –Approx. 36 m (120 ft.) Spans

26 New Alignment Alternatives Boulevard (35 mph) Standards –Grade Separated Alternative (Chosen) –Signalized Alternative (Not Chosen) –3.3 m Lanes, 1.2 m & 1.8 m Shoulders –Tight Curves: Shorter Bridge, Less Skew –Substandard Horizontal Alignment Accepted By City of Portland via IGA Ownership Transfers to Portland Upon Completion

27 At-Grade Signalized Alternative

28 MLK/Grand Selected Alternative

29 Engineering Solutions Replace MLK Struct., Rehab Grand TS&L (Sept. 2003): Replace Grand? –Approx. $3 million extra –Best time to replace during this project –Wouldn’t have to remove rails, etc. later –But, existing structure didn’t meet criteria to replace (SR > 50) –Not in original scope –Not in the budget

30 Stage Construction Challenges Narrow Lanes & Shld. on New Struct. Restricted Right-of-Way Traffic Volumes (60,000+ ADT) Maintain 4 Lanes During Construction Temporary Detour Structure (partial)

31 Stage Construction Sections

32 Superstructure Precast P/S Slab/Box Girders –Fits Desired Span Lengths (75’-80’) –Haunched for Architectural Appearance –Quicker to Build, No Falsework Req’d. –Good Structure Economy –Spread Boxes w/ Cast Deck –Has Been Done Before North 3 Spans CIP P/T Box Girder –Flared, Curved, Skewed

33 Haunched Beam – Half Elevation

34 Haunched Beam – Sections

35 Span Layout Issues Repetitive Spans Promote Economy Try To Avoid Existing Bents Many Utilities, Buried and Overhead Resulting Spans Weren’t Equal

36 Layout – w/ Grand Ave. Rehab.

37 Foundation Conditions Silt Overburden Layer Seismic Settlement & Amplification Use Steel H-Piles –Driven into Troutdale Gravel Layer –Approx. 15-20 m deep North & South –Approx. 25-30 m deep at wood waste MSE Wire Retaining Walls –CIP Architectural Facing, After Settlement

38 Logistical Challenges During Design Decentralization of ODOT in 2004 Designers/Drafters in: –Region 1, Portland –Region 2, East Salem –ODOT HQ, Salem Minimal Traffic Control Design Begun DEA, Inc. Recruited for Traffic Control Design, Drafting, Lead Structure Design

39 Evolving Bid Schedule November 2005: Change of Course –Cost of Grand rehab approached replacement cost –Decision to Replace Grand Ave. –Split Contracts March 9, 2006 bid for earthwork, drainage, utilities ($5 million) Nov. 2006 bid for structure and retaining walls

40 Layout – Grand Ave. Rehab.

41 Layout – Grand Ave. Replace

42 General Layout

43 Innovative Contracting Methods Complex Project with Significant Risk Elements –Want an experienced contractor with innovative abilities –Think it through ahead of time

44 Innovative Contracting, cont. 1 Best Value Bid Process (A+C+D) on Structure Work –“A” Component: Price (40%) –“C” Component: Qualifications (40%) –“D” Component: Tech. Approach (20%) –Not Used: “B” Component (Time)

45 Innovative Contracting, cont. 2 ODOT Experience with Best Value Contracting: –I-5 Interstate Bridge Lift Span Trunnion Replacement (1997) –St. Johns Bridge Rehabilitation (2003- 05) –Both Were A+C –Procedure now in place at Office of Procurement to streamline Best Value Contracting

46 Philosophical Considerations Budget Limitations –$32 million available from Bridge Program Scope creep –Project now approx. $50 million range Unfunded Stakeholder Demands Awareness of Project Scope –Grand Ave. not part of original scope

47 Philosophical Considerations cont. Context Sensitive Solutions –Was the original scope realistic considering the setting? –Old industrial area vs. redevelopment visions –Transportation impacts on communities –Cause urban blight vs. enhancement

48 Questions?


Download ppt "Martin Luther King, Jr. Blvd. Viaduct, Portland Project Background and Today’s Design Status."

Similar presentations


Ads by Google