Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.

Similar presentations


Presentation on theme: "Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime."— Presentation transcript:

1 Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime. Complied by AlNik Solutions for project managers using PMPlan products.

2 “Robert’s Rules of Order for Project Management” 1.Get a project charter 2.Create the project scope statement 3.Create the WBS with the project team 4.Create the activity list from the WBS 5.Sequence the activities in the order in which they must – or should – happen 6.Estimate the time of the activities based on which resources you have to complete the activities 7.Assign the needed resources to the activities 8.Get it done. From “Real Life Project Management: Managing the Project Scope” by Joseph Phillips Jan 28, 2005

3 Agenda of Presentation General Project Management Work Breakdown Structure Scheduling Earned Value Management

4 Common Project Processes Initiation –Defines the project objectives and grants authority to the project manager. Planning –Refines the project objectives and scope and plans the steps necessary to meet the project’s objectives. Executing –Puts the project plan into motion and performs the work of the project. Controlling –Measures the performance of the executing activities and compares the results with the project plan. Closing –Documents the formal acceptance of the project’s product and brings all aspects of the project to a close.

5 Elements of a Project’s Life Cycle Client Statement of Work Preliminary Project Plan Internal Review Proposal Project Plan Client Review/ Negotiations Baseline Project Plan Work Authorization Project Execution Client Requested Changes Project Monitoring Revised Project Plan Revised Project Plan PMPlan can be used effectively for most of the elements of a project’s life cycle.

6 Managing the Triple Constraint Project Scope –How much work is to be done? Increasing the scope causes more work to be done, and vice versa. Time –The schedule of the project. Modifying the schedule alters the start and end dates for tasks in the project and can alter the project’s overall end date. Cost –The cost required to accomplish the project’s objectives. Modifying the cost of the project generally has an impact on the scope, time, or quality of the project.

7 Project Manager Roles and Interactions

8 Elements of Developing a Project Plan Client SOW Work Breakdown Structure Activity Definition Resource Planning Resource Pool Activity Sequencing Activity Duration Estimating Cost Estimating Schedule Development Work Packages Project Plan Development PMPlan can address these elements when developing the project plan.

9 What is a Work Breakdown Structure “The Work Breakdown Structure (WBS) is the foundation for defining the project’s work as it relates to the objectives and establishes a structure for managing the work to its completion. The WBS defines: the project’s work in terms of activities that create deliverables. the project’s life-cycle process, in terms of process steps appropriate to that project and organization. And is the basis for establishing: All of the effort/cost to be expended to create the deliverables and supporting processes. The assigned responsibility for accomplishing and coordinating the work. ” (from the PMI Practice Standard for Work Breakdown Structures, Oct 2000)”

10 Good WBS Design Principles The 100% Rule –The WBS defines 100% of the work of the project –Anything that isn’t defined in the WBS is outside the scope of the project. –The work content on any item is the sum of what is included under that work item Upper Levels are Planned outcomes (deliverables), not planned actions Ends of WBS include the activities needed to create the project deliverables Mutually-exclusive elements –Work should only appear in one place in the WBS WBS must be consistent with the way the project will be performed and controlled Must be easy to update

11 WBS Role Partition the major project deliverables into smaller components to improve the accuracy of cost estimates Provide a mechanism for collecting actual costs Provide a mechanism for performance measurement and control

12 Sample WBS – Product Type Project

13 Sample WBS – Service Type Project

14 Sample WBS – Results Type Project

15 Why create a WBS? Cost Estimating Cost Budgeting Resource Planning Risk Management Planning Activity Definition

16 Scheduling Scheduling forces: –Quantification of discrete effort –Placement of tasks in proper relationship Two most common scheduling methodologies –Bar Charts (aka Gantt Charts) –Critical Path Method (CPM) using Precedence Diagramming Method (PDM)

17 Bar / Gantt Charts Defined: Analyze and specify the basic approach in execution Segment into reasonable number of activities Estimate the time required to perform each activity Manually places activities in time order –Sequential performance –Parallel performance Adjust to specified completion time

18 Bar / Gantt Charts Advantages: Plan, schedule and progress are all depicted graphically on a single chart Easily read Provides simple way to schedule small undertaking Provides summary display of more detailed plans and schedules Best used for management briefings

19 Bar / Gantt Charts Disadvantages: Planning and scheduling are considered simultaneously Simplicity precludes sufficient detail for timely detection of slippages Activity dependencies cannot adequately be shown Difficult to determine how activity progress delays affect project completion Difficult to establish and maintain for large projects.

20 Bar / Gantt Chart Sample Planned Progress Actual Progress Ahead of Schedule Behind Schedule Time Now Completed Task

21 Critical Path Method Advantages: Identifies activities that control the project length Determines shortest time for completion Identifies activities that are critical (i.e. cannot be delayed) Shows available float for non-critical activities Allows evaluation of “what-if” scenarios Allows monitoring & control of fast-track projects With software can be resource loaded and leveled

22 Critical Path Method Disadvantages Only as good as the effort put forth to properly model the plan Can be difficult to properly update Can be easily misused May lead to a false sense of security Actual conditions may necessitate significant modifications to model to accurately reflect reality

23 Precedence Diagramming Method (PDM) PDM network rules: –Activities are represented by boxes or nodes that are assigned properties of the activity they represent –Precedences are shown by arrows that have both direction and time properties –Precedences consist of two parts: A relationship and a lag value or constraint Finish – to – StartFS Finish – to – FinishFF Start – to – StartSS Start – to – FinishSF Lag = x Days ( a negative lag is called a lead)

24 PDM – Precedence Diagram PDM activities are comprised of: –Activity descriptions –Nodes representing the activity –Arrows representing relationship / dependency –Points indicating direction of relationship / dependency

25 PDM Logic Relationships Finish to Start (FS) – Activity A must Finish before Activity B may Start. The lag is usually zero. FS is the most common type. Start to Finish (SF) – Activity A must start before Activity B may Finish. The lag is usually greater than either activity duration. FS is the least common type. Activity AActivity BActivity AActivity B

26 PDM Logic Relationships Finish to Finish (FF) – Activity A must Finish before Activity B may Finish. The lag value is usually greater than zero. FF is a less common type. Start to Start (SS) – Activity A must Start before Activity B may Start. The lag value is usually greater than zero. SS is a less common type. Activity AActivity BActivity AActivity B

27 PDM Time Calculations Once the Network is constructed and duration of each activity is estimated, we can determined the following four time values: –Earliest Start (ES) – The earliest possible time an activity can begin –Earliest Finish (EF) – The earliest possible time an activity can finish –Latest Start (LS) – The latest possible time an activity can start without delaying project completion –Latest Finish (LF) – The latest possible time an activity can start without delaying project completion

28 PDM Time Calculations ES and EF are determined by making a Forward Pass (left-to-right) through the Network. ES of an activity is equal to the latest of early finish times of its predecessors. EF is the total of the activity ES plus its duration. LS and LF are determined by making a Backward Pass (right-to-left) through the Network. LF of an activity is equal to the smallest of the LS times of the activities exiting from the activity in question. LS of an activity is equal to its LF minus its duration.

29 PDM Activity Notation and Assumptions Each activity box consists of six cells For the following example assume all activities: –Begin on the morning of the scheduled start date –End the evening of the scheduled finish date –Using a 7-day workdays per week calendar 4E6 11213 ES EF Activity Duration LSLF 0 Lag

30 Forward Pass Example 6D9 4 8E8 1 4F10 7 12G18 7 2 0 0 (F to G) 10 + 0 + 1 = 11 (E to G) 8 + 0 + 1 = 9 (D to G) 9 + 2 + 1 = 12 Largest ES Early Start Calculations Early Finish Calculation 12 + 7 – 1 = 18

31 Backward Pass Example 18H24 25731 18I21 24427 18J 341 14K17 19422 2 0 0 (H to K) 25 - 2 - 1 = 22 (I to K) 24 - 0 - 1 = 23 (J to K) 34 - 0 - 1 = 33 Late Finish Calculations Late Start Calculation 22 - 4 + 1 = 19

32 CPM Example Exercise A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d FSFFSSSF

33 CPM Example Exercise Forward Pass Results A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d 1d6d7d17d18d37d63d82d 1d20d21d33d34d42d43d62d 34d39d40d52d

34 CPM Example Exercise Backward Pass Results A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d 1d6d7d17d18d37d63d82d 1d20d21d33d34d42d43d62d 34d39d40d52d 4d9d10d20d43d62d63d82d 1d20d21d33d34d42d43d62d 44d49d50d62d

35 CPM Example Exercise Backward Pass Results A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d 1d6d7d17d18d37d63d82d 1d20d21d33d34d42d43d62d 34d39d40d52d 4d9d10d20d43d62d63d82d 1d20d21d33d34d42d43d62d 44d49d50d62d

36 CPM – Float (or Slack) and Critical Path Additional Network calculations provides other important information allowing analysis and control: –Total Float (TF) – The amount of time an activity can be delayed without delaying the overall project completion, which is equal to Late Finish minus Early Finish. –Free Float (FF) – The amount of time an activity can be delayed without delaying the start of another activity. Can be determine by subtracting the smallest Total Float going into an activity from each predecessor into that activity. –Critical Path – The path through the Network that has the longest total duration, thus it defines the shortest period of time in which the project may be completed.

37 Float Calculation Example 21V30 351045 29W35 39745 36X40 46550 44Y50 44150 51Z60 511060 F T =15 F F =5 F T =10 F F =0 F T =10 F F =0 F T =0 F F =0 F T =0 F F =0

38 CPM Example Exercise Continue with Exercise A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d 1d6d7d17d18d37d63d82d 1d20d21d33d34d42d43d62d 34d39d40d52d 4d9d10d20d43d62d63d82d 1d20d21d33d34d42d43d62d 44d49d50d62d

39 CPM Example Exercise Float Results A 6d B 11d C 20d H J D 13d E 9d F 20d G 6d I 13d 1d6d7d17d18d37d63d82d 1d20d21d33d34d42d43d62d 34d39d40d52d 4d9d10d20d43d62d63d82d 1d20d21d33d34d42d43d62d 44d49d50d62d 3d 25d0d 10d

40 CPM Example Exercise Critical Path Traced A 1d6d 4d3d9d B 7d11d17d 10d3d20d C 18d20d37d 43d25d62d H 63d20d82d 63d0d82d J 1d20d 1d0d20d D 21d13d33d 21d0d33d E 34d9d42d 34d0d42d F 43d20d62d 43d0d62d G 34d6d39d 44d10d49d I 40d13d52d 50d10d62d FSFFSSSF

41 Scheduling Basics Review Two widely used scheduling techniques: –Bar / Gantt Charts Project, schedule & progress depicted on a single chart Easy to read Good for management review and oversight –Critical Path Method (CPM) Identifies activities that control the project length Identifies activities that are critical Shows available float for non-critical activities

42 Earned Value Tracking Earned Value (EV) based performance measurement systems “Link Expenditures to accomplishments”

43 This review of Earned Value Concept will: Describe a simple project and its progress Define Earned Value and related terms Show how Earned Value defines project performance

44 Earned Value System Can: –Provide early (Difficult to ignore) performance problem identification –Improve financial Reporting Does not: –Recognize Critical Paths Will not: –Take management action

45 Measurement Terminology Budget at Completion (BAC) –The sum of the total budget for a work package, major task, or project. Planned Value (PV) –The scheduled cost based on the allocation cost items such resources and material during the timeline of an activity –Also called Budgeted Cost for Work Scheduled (BCWS) Earned Value (EV) –The value of the work performed to-date using any reasonably accurate, mutually acceptable methodology for determining value (i.e.; 0/100%, 50/50%, 30/40/40, ratio of units completed versus total units, manager estimate, level of effort, being some examples). –Also called Budgeted Cost for Work Performed (BCWP) Actual Valve (AV) –Total incurred costs charged to a work package by the company’s accounting system, which can include labor costs, direct costs (overhead), and indirect costs (material, travel, and etc.) –Also called Actual Cost for Work Performed (ACWP) These values are used to calculate performance.

46 Performance Terminology Cost Variance (CV) –CV = EV – AV = BCWP – ACWP Cost Performance Index (CPI) –The cost efficiency ratio of earned value to actual costs (CPI = EV/AV) –In PMPlan, the CPI is used to calculate Estimate at Completion (EAC) (EAC = BAC/CPI) Schedule Variance (SV) –SV = EV – PV =BCWP – BCWS Schedule Performance Index (SPI) –The schedule efficiency ratio of earned value accomplished against planned value (SPI = EV/PV). The SPI describes what portion of the planned schedule was actually accomplished. Variance at Completion (VAC) –The predicted magnitude of possible underrun or overrun at completion of work package, major task, or project (VAC = BAC – EAC)

47 Review of Earned Value Concept Will –Describe a simple project and its progress –Define earned value and related terms –Show how earned value defines project performance Note: Sample tables and graphics shown in following slides are from PMPlan

48 Schedule This shows a sample project schedule

49 Planned Budget The sample project is loaded with resources which results in an allocated spend plan.

50 Time-Phased Spend Plan This shows the time-phased spend plan if the project proceeds as planned.

51 Typical Approach of Tracking of Actual versus Planned The chart tells us we have spent less than planned to date, but We cannot tell if we are behind schedule, nor if the cost for work completed matches the actual costs.

52 Using Earned Value Method For Earned Value Method to work well you need to breakdown the project into measurable activities (Note: in PMPlan,Cost Budgeting is done at the activity level not work package). It is recommended that your work packages (where you accumulate actual costs) be one or two levels above the activities. The following five slides show different performance results of our sample project.

53 Example PMPlan Earned Value Worksheet The project manager or task leader enters either a earned percentage or a $ value. Actual Cost is also entered. In this worksheet, actual cost can also include open commitments such as unpaid invoices for material and equipment. The ‘Threshold’ is a percent of the AV to the BAC, which determines when the application uses the CPI to calculate VAC. If AV is less than ‘Threshold’, the VAC equals CV. Based on the data entered, this project is both behind schedule and over budget. Even though the current CV = $4,000, the VAC indicates a potential overrun of $5,517. The next slide shows two other views of this data.

54 Project has Negative SV and CV In the lower half of the graph, the EV is below both the PV and AC indicating problems with cost and schedule. The upper half of the graph shows both CPI and SPI relative to a value of 1. It is showing that progress is being made to improve the schedule, but cost problem remains. The black EV bars in the Gantt schedule at the right shows that ‘Design’ and ‘Prototype’ activities are behind schedule.

55 Status when have - SV and zero (0) CV The EV and AC are equal, thus actual cost are inline with accomplishments. Even though the project is behind schedule, the schedule variance trend shows a strong improvement in schedule.

56 Status when have zero (0) SV, + CV This project is on schedule and should be completed under budget. With the project all of the earned bars line up with the green status line.

57 Why 50% Complete may not be half the schedule bar! In the above sample, all three activities have earned values of 50% of BAC, but the black earned bars are not the same length even though the planned bars are the same. Task A is behind schedule, because 75% of the budget was to be spent by end of December. Task B is ahead of schedule, because only 25% of the budget was to be spent by end of December.

58 In Summary – an Earned Value System Can: –Provide early (Difficult to ignore) performance problem identification –Improve financial Reporting Does not: –Recognize Critical Paths Will not: –Take management action

59 Project Management Methods Summary We have described three major processes used in project management –Work Breakdown Structure –Scheduling –Earned Value Management We are ready now to see how PMPlan can help you with these processes