Presentation is loading. Please wait.

Presentation is loading. Please wait.

ACEC WI Department of Transportation Liaison Committee Quarterly Meeting February 3, 2015.

Similar presentations


Presentation on theme: "ACEC WI Department of Transportation Liaison Committee Quarterly Meeting February 3, 2015."— Presentation transcript:

1 ACEC WI Department of Transportation Liaison Committee Quarterly Meeting February 3, 2015

2 Wisconsin Asphalt Pavement Association A nonprofit organization that represents Wisconsin’s asphalt industry We are a resource for our members (80+ contractors and manufacturers), their customers and the public at large. We are a third party…product driven Contact us at: www.wispave.orgwww.wispave.org Brandon Strand – Executive Director Deb Schwerman – Director of Engineering 4600 American Parkway Suite #201 Madison, WI 53718 608-255-3114

3 Estimating HMA projects What’s in hot mix asphalt Air Aggregates PG binder Air For now it’s free… Aggregates Engineered product from mining, drilling, blasting, crushing, screening, washing, processing, stockpiling, loading, hauling, etc… Consensus property requirements ESAL fractured face specification (E-0.3 vs. E-30)

4 PG Binder Performance Grade Binder Temp ranges in °C Resist rutting Resist cracking Petroleum by-product Modified to take on different properties Acid or polymer modifiers Additives Warm Mix Anti-Strip Rejuvenators Extenders

5 What affects PG Binder cost? Market is fluid…dependent on demand Follow FDM 14-10-5.10 for appropriate PG binder grade uses Additives are very expensive Limit PG binder grades to three per project (2 if possible) Utilize a full tanker truck load of liquid binder (FDM 14-10- 35.3.2) Approx. 22 tons of liquid = 420 tons of HMA

6 What affects mixture cost? The asphalt plant Portable vs. Permanent Haul distance from project Project type Availability of recycled materials-base course or RAP Possible asphalt savings by utilizing salvaged pavement/millings Testing requirements Proper certifications HMA volumetric testing, PG binder, tack coat, etc… Nuclear density testing (test strip, cores, etc…) IRI testing Documentation and overhead

7 What affects mixture cost? Anticipated disincentive potentials Material specific Time specific (working day contracts vs. completion dates) Constructability concerns Longitudinal joint construction (joint heaters) Obstacles (RR crossings, bridges, bus pads, manholes, inlets, water boxes, etc…) Number of side roads, intersections, turn lanes, etc… Cold weather production Increased drying time Superheating of materials Plant and personnel operate slower

8 What affects mixture cost? Traffic Closed/open traffic Tandem paving Staging Restrictions (working hours, days of the week, holidays, etc…) Multiple mobilizations Night versus daytime working hours Project Let dates Understand project schedule Resources versus work Overtime workload Proper construction management

9 Requirements that increase costs Material transfer devices Longitudinal joint heaters Cold Weather Paving specification per ASP 6 WMA additives are required-biddable item Additional rolling equipment is required More contractor risk

10 Tips for accurate estimates Know your project Get out in the field Visualize construction-understand the staging of the project Understand time restrictions (lane closures) Use proper traffic mitigation for project (detours, flaggers, reduce speed limit, etc…) Don’t rush, take your time…if you have a question, ask Try not to overcomplicate the project Provide accurate and “defined quantities” Review the project through the eyes of industry for bidding and the project staff for building Be careful when using prior designs as a reference

11 Tips for accurate estimates Average unit prices are not necessarily representative Get rid of the “bid it as you see it” mentality Allow enough time to properly build the project Use your asphaltic surface SS465 bid items… Distinguish mainline paving from all other paving with the appropriate item Identify areas of non mainline paving and ensure that contract time allows for all of that “other” work For smaller tonnage projects determine if the item is adequate

12 Tips for smooth construction Proper management Partnering Don’t be afraid to be the engineer Make engineering judgments Don’t let change orders negatively affect project You are not the designer…we are not a method spec. state…building per plan might not be right for every application

13 Items to remember Time is money If you can’t quantify or define it…it’s risk Risk is expensive Complication = Risk When in doubt…ASK!!!

14 Things to come… Combined bid item for E-mix and PG binder Re-writing of QMP to include PWL specification for larger projects Ride specification requirement for bridges and approaches Specification Updates Tack increase from 0.025 gal/sy to 0.05-0.07 gal/sy Increase VMA requirement for E-0.3 and E-3 surface mixes Cold Weather paving specification (SS 450) Elimination of PG 64-22…now PG 64-28 CMM re-write for nuclear density (8-15) CMM re-write for design life, mix design, dispute resolution, etc…(8-65/66)

15 Things to come… PG binder MSCR testing (Phase I implementation) HMA Paving inspector requirement for all projects with over 5000 tons of HMA Training is held in each Region state-wide Pilot project solicitation High RAP/RAS Thin Lift Overlay Cold in Place Recycling Full depth reclamation HMA Inspection Training 2015

16 WAPA Thank you for having me Annual Conference Black Bag training sessions Work hand in hand with DOT/FHWA/Locals etc… Green Team Tech Team Sub-committee work WHRP Don’t hesitate to reach out…that’s what we’re here for

17 Questions


Download ppt "ACEC WI Department of Transportation Liaison Committee Quarterly Meeting February 3, 2015."

Similar presentations


Ads by Google