MICE WBS rebuild/extract: Top level: –http://mice.iit.edu/tb/MICE-Schedule/http://mice.iit.edu/tb/MICE-Schedule/ –PM: (Long acting) Level 2: –MICE Muon.

Similar presentations


Presentation on theme: "MICE WBS rebuild/extract: Top level: –http://mice.iit.edu/tb/MICE-Schedule/http://mice.iit.edu/tb/MICE-Schedule/ –PM: (Long acting) Level 2: –MICE Muon."— Presentation transcript:

1 MICE WBS rebuild/extract: Top level: –http://mice.iit.edu/tb/MICE-Schedule/http://mice.iit.edu/tb/MICE-Schedule/ –PM: (Long acting) Level 2: –MICE Muon Beam, MICE Hall and infrastructure MMB, MH&I: Nichols S/w, cntrls, instrumentation: Apsimon –MICE Instrumentation: Bross –MICE Cooling Channel Zisman To be expanded to next levels asap.

2 2.0 MICE Muon Beam, MICE Hall, infrastructure MICE Muon Beam, MICE Hall, infrastructure: –Nichols Software, controls, instrumentation: –Apsimon 2.0 MMB, MH&I 2.0.1 MICE Muon Beam:Long 2.0.2 MICE Hall and infrastructure:Nelson 2.0.3 Christmas 2007 shutdown:Hayler

3 2.0.1 MICE Muon Beam Long

4 2.0.1.1 Target Booth Removal of old target: Discussion with RPA: Require revised method statement quantifying doses, isotopes etc. Suggestion using MMPX to evaluate activation Revision goal: 13Sep07 18: Jacking motor controls: Working with G.Charnley, to be updated, goal 13Sep07. 23: Cable installation: working with A.Nobbs, to be updated, goal 13Sep07 33: Development of bearings: working S.Payne Require to prepare document for CM19. Document to: Propose operation scheme to be presented to ISIS (Findlay) for running from January ’08; Propose development plan for final target bearing scheme 37: Installation of the PSU: Location defined, working with A.Nobbs 40: Installation of target controls: Location defined, working DL on controls, S.Britnell on cabling in Hall and MLCR Revision of schedule promised for 13Sep07

5 2.0.1.2 Q35 refurbishment Long Refurbishment scheme needs to be reviewed in light of experience Review to be carried out as soon as E.Cappozi and C.Locket are both avaulable. Testing scheme to be developed in consultation with M.Hughes and K.Tilley

6 2.0.1.3 Linde refridgerator Courthold Noted pressure on schedule: First priority: must not be allowed to slip: Implies potential call on additional resources Require to ensure adequate number of people trained for working at height: MC has organisation of training course in hand ~8 places available. Agreed: first call on places for: Spensley (if not already trained), Jamdagni (+second Hall Foreman), Capozzi, Lockett, Courthold, Nelson, Jones

7 2.0.1.4 PSI solenoid Courthold To be reviewed for next week (13Sep07) Noted from discussion: Require to add electrical testing schedule Swagelock adaptor, which is on order, is required before vac test can begin. Question added ‘in proof’: Does this need to be chased with Swagelock?

8 2.0.1.5 Q4—9 installation Nelson To be reviewed for next week (13Sep07) Noted from discussion: Presently only delivery schedule Installation schedule needs to be developed

9 2.0.2 MICE Hall Nelson Tasks identified (with person responsible) below. [Caution, may not be complete list:] Magnetic shield wallsNelson MICE Hall Floor:Nelson Plinth (concrete infill in ‘pit’) False floor (levelling sloping floor) Rolling platformsNelson WaterGovens Air conditioningGovens PowerGriffiths Liquid-hydrogen systemIvanyushenkov MLCRKyberd NetworkingBrandwood Cabling:Griffiths Linde Test positionsCourthold Final positionsCourthold Cable trays/cable layout etc.

10 2.0.2.1 MICE Local Control Room Kyberd P.Kyberd not at meeting so noted: Revision requested for 13Sep07 Personnel responsible for sub-systems: Civil work:Houseman in absence of Pyke PPSAlexander NetworkingBrandwood Racks‘DL’ Rack installation PK CablingBritnell

11 2.0.3 XMas2007-shutdown Hayler Discussion of resources (availability, etc.) starts 06Sep07 Priority 1: Implies planning of tasks Sep—Dec done to preserve/advance Christmas schedule


Download ppt "MICE WBS rebuild/extract: Top level: –http://mice.iit.edu/tb/MICE-Schedule/http://mice.iit.edu/tb/MICE-Schedule/ –PM: (Long acting) Level 2: –MICE Muon."