Presentation is loading. Please wait.

Presentation is loading. Please wait.

Lecture 5 Project Management Chapter 17.

Similar presentations


Presentation on theme: "Lecture 5 Project Management Chapter 17."— Presentation transcript:

1 Lecture 5 Project Management Chapter 17

2 Probabilistic/Uncertain Activity Times
In the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. An activity’s mean completion time is: t = (a + 4m + b)/6 a = the optimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate

3 Example Activity Immediate Predecessor Optimistic Time (a) Most Likely
Time (m) Pessimistic Time (b) A -- 4 6 8 B 1 4.5 5 C 3 D E 0.5 1.5 F B,C G H E,F 7 I 2 J D,H 2.5 2.75 K G,I

4 Management Scientist Solution

5 Lecture 5 Inventory Management Chapter 11

6 Types of Inventories Raw materials & purchased parts
Partially completed goods called work in progress Finished-goods inventories (manufacturing firms) or merchandise (retail stores) Replacement parts, tools, & supplies Goods-in-transit to warehouses or customers

7 Functions of Inventory
To meet anticipated demand To smooth production requirements To decouple operations To protect against stock-outs To take advantage of order cycles To help hedge against price increases To permit operations To take advantage of quantity discounts

8 Objective of Inventory Control
To achieve satisfactory levels of customer service while keeping inventory costs within reasonable bounds Level of customer service Costs of ordering and carrying inventory

9 Key Inventory Terms Lead time: time interval between ordering and receiving the order Holding (carrying) costs: cost to carry an item in inventory for a length of time, usually a year Ordering costs: costs of ordering and receiving inventory Shortage costs: costs when demand exceeds supply

10 Inventory Classification Systems ABC Analysis
Divides inventory into three classes based on annual dollar volume Class A - high annual dollar volume Class B - medium annual dollar volume Class C - low annual dollar volume Used to establish policies that focus on the few critical parts and not the many trivial ones No “hard-and-fast” rule to classify into different categories

11 ABC Analysis Example $232,057 Item Stock Number
Percent of Number of Items Stocked Annual Volume (units) x Unit Cost = Annual Dollar Volume Percent of Annual Dollar Volume Class #10286 20% 1,000 $ 90.00 $ 90,000 38.8% 72% A #11526 500 154.00 77,000 33.2% #12760 1,550 17.00 $ 26,350 11.3% B #10867 30% 350 42.86 15,001 6.4% 23% #10500 12.50 12,500 5.4% #12572 600 $ 14.17 $ 8,502 3.7% C #14075 2,000 .60 1,200 .5% #01036 50% 100 8.50 850 .4% 5% #01307 .42 504 .2% #10572 250 150 .1% $232,057

12 Economic Order Quantity Models
Economic order quantity (EOQ) model Economic production model (EPQ) Quantity discount model

13 Profile of Inventory Level Over Time
The Inventory Cycle Profile of Inventory Level Over Time Q Usage rate Quantity on hand Reorder point Time Receive order Place order Receive order Place order Receive order Lead time

14 Total Cost Annual carrying cost ordering Total cost = + Q 2 H D S TC =
Formula (11-1)

15 Cost Minimization Goal
The Total-Cost Curve is U-Shaped Annual Cost Ordering Costs Order Quantity (Q) QO (optimal order quantity)

16 Deriving the EOQ & Minimum Total Cost
The total cost curve reaches its minimum where the carrying and ordering costs are equal. Formula (11-2) Number of orders per year = D/Q0 Length of order cycle = Q0/D Formula (11-3)

17 Inventory Management – In-class Example
Number 2 pencils at the campus book-store are sold at a fairly steady rate of 60 per week. It cost the bookstore $12 to initiate an order to its supplier and holding costs are $0.005 per pencil per year. Determine (a) The optimal number of pencils for the bookstore to purchase to minimize total annual inventory cost, (b) Number of orders per year, (c) The length of each order cycle, (d) Annual holding cost, (e) Annual ordering cost, and (f) Total annual inventory cost. (g) If the order lead time is 4 months, determine the reorder point. Illustrate the inventory profile graphically. What additional cost would the book-store incur if it orders in batches of 1000?

18 Management Scientist Solutions
(d) (e) (f) (g) (b) (c)

19 Assumptions of EOQ Model
Only one product is involved Annual demand requirements known Demand is even throughout the year Lead time does not vary Each order is received in a single delivery There are no quantity discounts

20 Economic Production Quantity (EPQ)
Economic production quantity (EPQ) model: variant of basic EOQ model Production done in batches or lots Replenishment order not received in one lump sum unlike basic EOQ model Inventory is replenished gradually as the order is produced hence requires the production rate to be greater than the demand rate This model's variable costs are annual holding cost, and annual set-up cost (equivalent to ordering cost). For the optimal lot size, annual holding and set-up costs are equal.

21 EPQ = EOQ with Incremental Inventory Replenishment

22 EPQ Model Assumptions Demand occurs at a constant rate of D items per year. Production rate is p items per year (and p > u ). u = usage rate Set-up cost: $S per run. Holding cost: $H per item in inventory per year. Purchase cost per unit is constant (no quantity discount). Set-up time (lead time) is constant. Planned shortages are not permitted.

23 EPQ Model Formulae Optimal production lot-size (formula 11-5 of book)
Run time: Q */p Time between set-ups (cycle time): Q */u years

24 Example: Non-Slip Tile Co.
Non-Slip Tile Company (NST) has been using production runs of 100,000 tiles, 10 times per year to meet the demand of 1,000,000 tile annually. The set-up cost is $5,000 per run Holding cost is estimated at 10% of the manufacturing cost of $1 per tile. The production capacity of the machine is 500,000 tiles per month. The factor is open 365 days per year. Determine Optimal production lot size Annual holding and setup costs Number of setups per year Loss/profit that NST is incurring annually by using their present production schedule

25 Management Scientist Solutions
Optimal TC = $28,868 Current TC = (100,000) + 5,000,000,000/100,000 = $54,167 LOSS = 54, ,868 = $25,299

26 Economic Production Quantity Assumptions
Only one item is involved  Annual demand is known  Usage rate is constant  Usage occurs continually Production occurs periodically Production rate is constant Lead time does not vary  No quantity discounts 

27 EOQ with Quantity Discounts
The EOQ with quantity discounts model is applicable where a supplier offers a lower purchase cost when an item is ordered in larger quantities. This model's variable costs are Annual holding, Ordering cost, and Purchase costs For the optimal order quantity, the annual holding and ordering costs are not necessarily equal.

28 EOQ with Quantity Discounts
Formulae Optimal order quantity: the procedure for determining Q * will be demonstrated Number of orders per year: D/Q * Time between orders (cycle time): Q */D years Total annual cost: (formula 11.9 of book) (holding + ordering + purchase)

29 Example – EOQ with Quantity Discount
Walgreens carries Fuji 400X instant print film The film normally costs Walgreens $3.20 per roll Walgreens sells each roll for $5.25 Walgreens's average sales are 21 rolls per week Walgreens’s annual inventory holding cost rate is 25% It costs Walgreens $20 to place an order with Fujifilm, USA Fujifilm offers the following discount scheme to Walgreens 7% discount on orders of 400 rolls or more 10% discount for 900 rolls or more, and 15% discount for 2000 rolls or more Determine Walgreen’s optimal order quantity

30 Management Scientist Solutions

31 Operations Strategy Too much inventory Wise strategy
Tends to hide problems Easier to live with problems than to eliminate them Costly to maintain Wise strategy Reduce lot sizes Reduce safety stock

32 The Balance Sheet – Dell Computer Co.

33 Income Statement – Dell Computer Co.
(in millions, except per share amount) 28-Jan-00 29-Jan-99 Net revenue $25,265 $18,243 Cost of revenue 20,047 14,137 Gross margin 5,218 4,106 Operating expenses: Selling, general and administrative 2,387 1,788 Research, development, and engineering 568 272 Total operating expenses 2,955 2,060 Operating income 2,263 2,046 Other income 188 38 Income before income taxes 2,451 2,084 Provision for income taxes 785 624 Net income $1,666 $1,460 Earnings per common share: Basic $0.66 $0.58 Diluted $0.61 $0.53 Weighted average shares outstanding: 2,536 2,531 2,728 2,772 Retained Earnings: Balances at beginning of period 606 607 1,666 1,460 Repurchase of common stocks (1,012) (1,461) Balances at end of period $1,260 $606 Fiscal Year Ended

34 Debt Ratio What It Measures: The extent to which a form uses debt financing How You Compute: The ratio of total debt to total assets

35 Inventory Turnover Ratio
What It Measures: How effectively a firm is managing its inventories. How You Compute: This ratio is computed by dividing sales by inventories Inventory turnover ratio =


Download ppt "Lecture 5 Project Management Chapter 17."

Similar presentations


Ads by Google