1 Evaluating Business and Engineering Assets – Part II Part II Professor C. S. Park Copyright © 2005

2 Payback Period Lecture No.14 Professor C. S. Park Fundamentals of Engineering Economics Copyright © 2005

3 Chapter 5 Present-Worth Analysis Loan versus Project Cash Flows Initial Project Screening Methods Present-Worth Analysis Methods to Compare Mutually Exclusive Alternatives

4 Chapter Opening Story – Federal Express Nature of Project: Equip 40,000 couriers with PowerPads Save 10 seconds per pickup stop Investment cost: $150 million Expected savings: $20 million per year Federal Express

5 Ultimate Questions Is it worth investing $150 million to save $20 million per year, say over 10 years? How long does it take to recover the initial investment? What kind of interest rate should be used in evaluating business investment opportunities?

6 Mr. Bracewell’s Investment Problem Built a hydroelectric plant using his personal savings of $800,000 Power generating capacity of 6 million kwhs Estimated annual power sales after taxes - $120,000 Expected service life of 50 years  Was Bracewell's $800,000 investment a wise one?  How long does he have to wait to recover his initial investment, and will he ever make a profit?

7 Mr. Brcewell’s Hydro Project

8 Bank Loan vs. Investment Project Bank Customer Loan Repayment Company Project Investment Return  Bank Loan  Investment Project

9 Describing Project Cash Flows Year (n) Cash Inflows (Benefits) Cash Outflows (Costs) Net Cash Flows 00$650,000-$650,000 1215,50053,000162,500 2215,50053,000162,500 ………… 8215,50053,000162,500

10 Payback Period  Principle: How fast can I recover my initial investment?  Method: Based on cumulative cash flow (or accounting profit)  Screening Guideline: If the payback period is less than or equal to some specified payback period, the project would be considered for further analysis.  Weakness: Does not consider the time value of money

11 Example 5.1 Payback Period NCash FlowCum. Flow 01234560123456 -$105,000+$20,000 $35,000 $45,000 $50,000 $45,000 $35,000 -$85,000 -$50,000 -$5,000 $45,000 $95,000 $140,000 $175,000 Payback period should occurs somewhere between N = 2 and N = 3.

12 -100,000 -50,000 0 50,000 100,000 150,000 012 3 456 Years (n) 3.2 years Payback period $85,000 $15,000 $25,000 $35,000 $45,000 $35,000 0 123456 Years Annual cash flow Cumulative cash flow ($)

13 Practice Problem How long does it take to recover the initial investment for Federal Express? How long does it take to recover the investments made by Mr. Bracewell from his hydroelectric project?

14 Discounted Payback Period  Principle: How fast can I recover my initial investment plus interest?  Method: Based on cumulative discounted cash flow  Screening Guideline: If the discounted payback period (DPP) is less than or equal to some specified payback period, the project would be considered for further analysis.  Weakness: Cash flows occurring after DPP are ignored

15 Example 5.2 Discounted Payback Period Calculation PeriodCash FlowCost of Funds (15%)* Cumulative Cash Flow 0-$85,0000 115,000-$85,000(0.15) = -$12,750-82,750 225,000-$82,750(0.15) = -12,413-70,163 335,000-$70,163(0.15) = -10,524-45,687 445,000-$45,687(0.15) =-6,853-7,540 545,000-$7,540(0.15) = -1,13136,329 635,000$36,329(0.15) = 5,44976,778 * Cost of funds = (Unrecovered beginning balance) X (interest rate)

16 Summary Payback periods can be used as a screening tool for liquidity, but we need a measure of investment worth for profitability.