1 Post Installation Pipe Inspection Prepared for KYTC Section Engineers Meeting March 5, 2013 By Kean H. Ashurst Jr., P.E. Kentucky Transportation Center

2 Overview More structured and standardized reporting format Different technologies for laser deflection testing What to look out for Certification Program

3 Video Inspection Summary Report

4 Video Inspection Report - Individual Pipe

5 Deflection Inspection Summary Report

6 Deflection Inspection Report - Individual Pipe

7 Different Technologies Video inspection Laser inspection – 2 different technologies in use in KY – Rausch (spinning laser head) – Cues (laser ring) Both use laser light to measure off a picture Not time of flight laser measuring

8 What to look out for All deflection measurements should be based off of AASHTO nominal diameter The last 5 to 12 feet of all laser inspections are always missing Rausch unit is consistent Cues unit will vary Maximum scanning speed should not exceed 30 ft/min

9 What to look out for Rausch (spinning laser head) – As pull back speed increases the gap between identical points increases Rausch - Single point scans – Whole run scan vs. single point scan – Single point scan is more accurate Rausch - Unit has to be centered in pipe

10 What to look out for Calibration is critical for the Cues system Pipe is “racked” – Can control rather than horizontal/vertical – Cues has an ovality report – Rausch has a wireframe diagram If you can see deflections then most likely the pipe is over deflected

11 Cues H/V Profile

12 Rausch Single Point Scan Footage Horizontal Deviation Vertical Deviation Width Reference Ring Scanned Profile Average diameter for this “slice” Nominal Diameter

13 Rausch Wireframe Diagram Diameter, deformation & deflection % Distance in pipe Color Deflection Limits Red/Black > 5.7% Yellow/Brown >2.1%

14 Max Deflection Not in H/V

15 Rausch Vertical Profile

16

17

18 Cues Profile

19 Certification Program Post installation pipe certification program Test track – 3 materials (RCP, CMP, HDPE) – Distressed pipe – Show they can complete form – Adequately identify distresses and deflections – Operator certified for their equipment

20 Thank You Kean H. Ashurst Jr., P.E. Kentucky Transportation Center University of Kentucky 176 Raymond Building Lexington, KY 40506 (859) 257-7319 kean.ashurst@uky.edu