SLRIDT Site Background SLRIDT Site Remediation Activities (2006-2009) 2010 Tallas Island Winter Dredging  Options  Pros/Cons  Winter Dredging Activities.

Similar presentations


Presentation on theme: "SLRIDT Site Background SLRIDT Site Remediation Activities (2006-2009) 2010 Tallas Island Winter Dredging  Options  Pros/Cons  Winter Dredging Activities."— Presentation transcript:

1

2 SLRIDT Site Background SLRIDT Site Remediation Activities (2006-2009) 2010 Tallas Island Winter Dredging  Options  Pros/Cons  Winter Dredging Activities  Challenges Experienced  Project Benefits Overview

3 SLRIDT Site Background

4

5 SLRIDT Site Remediation 2006

6 SLRIDT Site Remediation 2007

7 SLRIDT Site Remediation 2008

8 SLRIDT Site Remediation 2009

9 2010 Tallas Island Compensatory Mitigation Project

10 2010 Tallas Island Compensatory Mitigation Project

11 2010 Tallas Island Compensatory Mitigation Project

12 Options….. DDredge and Transport via Barge DDredge and Transport via Over-the-Road Trucks DDredge and Hydraulic Transport Tallas Island Winter Dredging

13 Pros  Expedite 2010 Construction Schedule  Minimizes Environmental Impacts  Minimizes Community Nuisances  Allows Shallow Draft Dredge Equipment Access  Cost savings Tallas Island Winter Dredging

14 Cons  Potential Hazards of On-Ice Dredge Work  Schedule Constraints  Temperature Dependent  Vegetation Segregation Tallas Island Winter Dredging

15

16

17

18

19

20

21

22

23

24

25

26

27

28 Challenges Experienced Tallas Island Winter Dredging

29 Unseasonably Mild Temperatures Tallas Island Winter Dredging

30 On-Ice Construction Safety Hazards Tallas Island Winter Dredging

31 Frost Road Construction Tallas Island Winter Dredging

32 Segregation of Vegetative Root Mass from Ice Tallas Island Winter Dredging

33 Thin Ice Experiences Tallas Island Winter Dredging

34 Extreme Working Conditions Tallas Island Winter Dredging

35

36 Project Benefits  Flexible 2010 Construction Schedule  Minimized Environmental/Community Impacts  Expedited Other SLRIDT Work Activities  Monetary Impact  Restoration of the Surrounding Environment Tallas Island Winter Dredging