Presentation of the Project „ Preparation of ceasing of dangerous junctions Zoltán Jákli KÖZOP Head of Completition Department Magyar Közút NZrt.

Similar presentations


Presentation on theme: "Presentation of the Project „ Preparation of ceasing of dangerous junctions Zoltán Jákli KÖZOP Head of Completition Department Magyar Közút NZrt."— Presentation transcript:

1 Presentation of the Project „ Preparation of ceasing of dangerous junctions Zoltán Jákli KÖZOP Head of Completition Department Magyar Közút NZrt.

2 TABLE OF CONTENT Network of Magyar Közút NZrt. I. Network of Magyar Közút NZrt. II. Ev ol ut i on of projects III. Traffic security projects of MK NZrt. IV. Presentation of the „ pr e paration ” proje c t Expected impacts V. Future plans, ou t loo k

3 Lorem Ipsum Length of the national public roads: 31 698,0 km 75 % of the entire public road traffic Goes here From the national public roads, the main network is 8339,8 km From the Main network 2253,6 km is "E" read, P a rt of the E ur o p e a n ne t work 27 % of the length of national public roads represent Crossing sections 7435 pc bridges and 8669 public road junctions may be found on national public roads I. Network of the „Magyar Közút Nzrt. ”

4 Traffic volume on the I. and II. class main roads and expressways ( 2011)

5 I. Network of the „Magyar Közút Nzrt. ” Traffic volume of tracks on the I. and II. class main roads and expressways (2011)

6 I. The network of Magyar Közút Nzrt. Accidents with personal injuries on the I. and II. class main roads (2007-2011) - 54 %

7 Accidents with personal injuries in junctions without traffic lights (I., II. class main roads; 2007-2011) I. The network of Magyar Közút Nzrt. - 48 %

8 I. The network of Magyar Közút Nzrt Counties concerned by the project

9 II. EVOLUTION OF THE PROJECT Subvention Idea Source Contract The project starts…

10 Major results  July 29, 2011. Minister of National Development – ordering letter Source: KÖZOP-3.5.0-09-11 „Improvement of access to areas”  May 15, 2012. Conclusion of Contracts of support for Project 2 KÖZOP-3.5.0-09-11-2011-0015 „Preparation of ceasing of dangerous junctions” KÖZOP-3.5.0-09-11-2011-0016 „Developments improving the security of traffic in the national network of public roads”  October 5, 2012. MK KözOP- approval of the rule for calculation of specific production cost Project management costs Installation of guardrails by our own implementation Provisory traffic techniques during the construction by our own implementation  November of 2012. The feasibility studies are ready  October 20, 2011. Reception of project proposal III. TRAFFIC SECURITY PROJECTS OF MK NZRT.  March 28,2012. Governemental decision – position of outstanding project

11 IV. Presentation of the preparatory project Why the roundabout? Better recognition Better recognition Favo u rable flow of traffic Less points of conflict s Favo u rable flow of traffic Less points of conflict s Lower speed Lower speed In total : HIGHER SEC U RITY In total : HIGHER SEC U RITY

12 Fejlesztésre javasolt helyszínek IV. Presentation of the preparatory project Plan making Plan making Authorization Authorization Execution plans Execution plans Acquisition of territory (if necessary) Acquisition of territory (if necessary) Archeology (if necessary) Archeology (if necessary)

13 Examined parameters Current geometric formation Situation of accidents (2007 – 2011), traffic conditions Expected decrease in the number of accidents Estimated investment & operating costs Foreign territory involvement Territory involvement of Natura 2000 Involvement due to archeological values Other external effects Economic efficiency indicators (Net current value, profit-cost rate, inner rate of return) IV. Presentation of the preparatory project

14 Junction of main road no.471. and road 4918. Especially dangerous site, i n total 21 traffic accidents with personal injuries occurred in the junction and surroundings in the examined period The relative accident indicator of the site c alculated onto the junction is 11,39 [b/10 7 jmkm/year]

15 Junction of main road no. 471. and road no. 4918. In case of rebuilding the junction, R b =10 m inner radius and R k =17 m outside radius of roundabout is recommended IV. Presentation of the preparatory project

16 Junction of Main road no. 62. – Road s. 70447. (M7 sub- junction) Examined site at half-trefoil junction of Motorway M7, and tree-branches „T” junction with traffic sign regulation of the second class road no. 62. The relative accident indicator of the place calculated onto the junction is [9,01 b/10 7 jmkm/year] IV. Presentation of the preparatory project

17 62. sz. főút – 70447. j. út (M7 alcsomópont) csomópontja In case of rebuilding the junction, it is recommended to build a roundabout of R b =15 m inner radius and R k =23,5 m of exterior radius IV. Presentation of the preparatory project

18 Traffic safety deficiencies It is hard to recognize and perceive the junction, the view of the straight passing is prevailing from the side-direction, too. The left turning lane is used for irregular overtaking IV. Presentation of the preparatory project

19 The geometric shaping of the junctions, the built-up of independent turning left lanes from all directions and the „guiding” effect of the electricity pylons help the progression at high speed The acute angle connecting of the main direction and of the sub-direction is especially unfavourable, both from the aspect of perception and from the aspect of providing an adequate associated line Traffic safety deficiencies IV. Presentation of the preparatory project

20 Table of timing

21 Country Average decrease (%) Total accidents personal injury accidents Australia41-6145-87 France 57-78 Germany36 Holland47 Great-Britain 25-39 United States3751 Hungary 47 (71) V.

22 Estimated decrease in annual victims and injured V. Expected impacts Accidents at the selected junctions between 2007 and 2011 Died Serious injured Slightly injured 0,050,94,7 Rural road1,93210,3525,668 Urban road

23 V. Expected impacts

24 Construction as soon as possible – New resource – New TSZ (Contract of Support) – NIF? MK? Continuous search of causes ad focus – New sites, new solutions Development of the water draining system Development of bridges, removal of bottle-necks V. Future plans, outlook

25 Thank you for your attention jakli.zoltan@kozut.hu