Yakima Air Terminal.  Project Overview  Project Schedule  Impacts  Project Status  Questions.

Similar presentations


Presentation on theme: "Yakima Air Terminal.  Project Overview  Project Schedule  Impacts  Project Status  Questions."— Presentation transcript:

1 Yakima Air Terminal

2  Project Overview  Project Schedule  Impacts  Project Status  Questions

3  The Yakima Air Terminal has received an $11,000,000 grant. The grant is to:  Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways;  Resurface airfield pavement between the north taxiway edge line to the non-movement line;  Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator;  Replace all existing directional and hold short signs; and  Correct several markings not meeting FAA standards.

4

5

6  Expected construction START DATE June 22, 2015:  Phase 1: June 22, 2015 – July 17, 2015  Phase 2: July 20, 2015 – July 31, 2015  Phase 3: August 1, 2015 – August 14, 2015  Phase 4: August 15, 2015 – September 4, 2015  Phase 5: September 8, 2015 – September 29, 2015  Phase 6/7: September 30, 2015 – October 30, 2015

7

8  Phase 1: June 22, 2015 – July 17, 2015  Ramp Closures.  McCormick West, and Plath Hangar.  Partial Ramp Closures.  Fuel Tank/House and McCormick Air Center.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

9

10  Phase 2: July 20, 2015 – July 31, 2015  Ramp Closures.  Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building.  Partial Ramp Closures.  McCormick Air Center and Private Hangars (formerly Noland-Decoto).  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

11

12  Phase 3: August 1, 2015 – August 14, 2015  Ramp Closures.  GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp.  Partial Ramp Closures.  Private Hangars (formerly Noland-Decoto).  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

13

14  Phase 4: August 15, 2015 – September 4, 2015  Ramp Closures.  East Terminal Apron Ramp.  Partial Ramp Closures.  East Itinerant Ramp.  Runway 4/22 and Bravo Taxiway Closed.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

15

16  Phase 5: September 8, 2015 – September 29, 2015  Ramp Closures.  No Ramps Closed.  Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

17

18  Phase 6: September 30, 2015 – October 30, 2015  Partial Ramp closures denoted by barricades.  Runway 4/22 closed intermittently.  On-going construction activity and vehicle traffic on service roads and taxiways.

19

20  Phase 7: September 30, 2015 – October 30, 2015  Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas.  On-going construction activities and vehicle traffic on service roads and ramps.

21  If at all possible, avoid construction areas.  Please plan all operations around construction to the maximum extent possible.  If there are known operations that will be impacted by the proposed schedule, please let us know.  The Airport Management will provide NOTAMs.  Do not travel (plane or car) across barricades delineating closed pavement.  Do not provide direction to the contractor unless there is an emergency.

22  Robert Peterson Rob.Peterson@yakimaairterminal.com Office: (509) 575-6149 (#7) Cell: (509) 833-0898  Kris Yalovich Kris.Yalovich@yakimaairterminal.com Office: (509) 575-6149 (#7)  Stephanie Ray, PE sray@hlacivil.com (509) 966-7000  Michael Battle, PE mbattle@hlacivil.com (509) 966-7000