Presentation is loading. Please wait.

Presentation is loading. Please wait.

WCCUSD Bond Program Project Status Report Citizen Bond Oversight Committee Measure M, D, J, D-2010 & E-2012.

Similar presentations


Presentation on theme: "WCCUSD Bond Program Project Status Report Citizen Bond Oversight Committee Measure M, D, J, D-2010 & E-2012."— Presentation transcript:

1 WCCUSD Bond Program Project Status Report Citizen Bond Oversight Committee Measure M, D, J, D-2010 & E-2012

2 Coronado Elementary School: Replacement Campus

3 Coronado Elementary School: Replacement Campus Construction Contract Value: $26,974,910 Percent Complete: 15% Change Orders: $0 (0%) Notice to Proceed: 1/6/14 Completion Date: 5/31/15

4 El Cerrito High School: Stadium

5 El Cerrito High School: Stadium Construction Contract Value: $13,438,000 Percent Complete: 14% Change Orders: $0 (0%) Notice to Proceed: 1/27/14 Completion Date: 9/27/15

6 Gompers / LPS: Replacement Campus

7 Construction Contract Value: $53,887,350 Percent Complete: 55% Change Orders: $673,297 1.23% Notice to Proceed: 8/20/12 Completion Date: 8/15/15

8 Helms Middle School: Sports Field

9 Construction Contract Value: $5,951,048 Percent Complete: 99% Change Orders: $212,694 (3.45%) Notice to Proceed: 1/7/13 Completion Date: 4/21/14

10 Kennedy High School: Science Wing Renovation

11 Construction Contract Value: $4,136,303 Percent Complete: 83% Change Orders: $81,893 (1.94%) Notice to Proceed: 9/16/13 Completion Date: 9/16/14

12 Kennedy High School: Richmond Swim Center

13 Construction Contract Value: 7,642,921 Percent Complete: 5% Change Orders: $0 (0%) Notice to Proceed: 4/28/14 Completion Date: 4/28/15

14 Montalvin Elementary School: New Classroom Building

15 Construction Contract Value: $2,843,000 Percent Complete: 15% Change Orders: $0 (0%) Notice to Proceed: 2/3/14 Completion Date: 10/31/14

16 Ohlone Elementary School: West Campus Replacement

17 Construction Contract Value: $16,961,000 Percent Complete: 90% Change Orders: $1,645,876 (8.85%) Notice to Proceed: 8/1/11 Completion Date: 9/25/14

18 Pinole Valley High School: Detention Basin, Utilities, & Paving

19 Construction Contract Value: $2,126,744 Percent Complete: 90% Change Orders: $0 (0%) Notice to Proceed: 11/12/13 Completion Date: 3/22/14

20 Pinole Valley High School: Interim Housing Campus

21 Pinole Valley High School: Interim Housing Construction Contract Value: $5,530,000 Percent Complete: 10% Change Orders: $0 (0%) Notice to Proceed: 4/7/14 Completion Date: 8/15/14

22 Portola Middle School: Campus Replacement

23 Construction Contract Value: $42,762,406 Percent Complete: 34% Change Orders: $88,792 (.20%) Notice to Proceed: 5/13/13 Completion Date: 12/29/15


Download ppt "WCCUSD Bond Program Project Status Report Citizen Bond Oversight Committee Measure M, D, J, D-2010 & E-2012."

Similar presentations


Ads by Google