Download presentation
Presentation is loading. Please wait.
1
Assessing the Effectiveness of K.P.M.s
Alex Finn – WBoPDC Transportation Manager David McDougall – Inroads Asset Manager
2
Where and What Population 42,000 212,000 hectares 1030 km roads
3x national growth rate 10th fastest growing (96-01) 14th fastest growing (01-06) 212,000 hectares 1030 km roads 790/240 (sealed/unsealed) 177 Bridges and Structures Encompass Tauranga City 110,000 pop Largest port in NZ
3
Background The problem faced in 1999 The Solution Growth at 4%
Declining Levels of Service Escalating costs Council not wanting rate rises The Solution Lump sum, performance based, long term maintenance contract ….PBC-01
4
Joint Principals – NZTA & WBOPDC 2-Tier Governance structure
PBC-01 - Introduction 10 Years – Joint Principals – NZTA & WBOPDC 2-Tier Governance structure Joint Client Panel WBoPDC NZTA (Transit)
5
PBC-01 Features Outcome based (measured by KPM) Lump sum Transfer of Operational Control & therefore some risk transfer Single provider
6
Investment $3million investment including subsidy Gathering data Setting up KPMs Developing contract document Tendering process Compensating tenderers
7
Savings for Council Estimate for 10 years $135m Tender $105m Saving $30m Tender/Estimate $78%
8
In Summary Investment $3 million Savings over 10 years $30 million Includes savings in NZTA subsidy
9
Setting up Performance Measures
Affordable Level of Service Necessary for community and the asset Must drive the contractor to provide the correct response
10
Basis of PBC Savings Economy of scale Contract period – 10 years Risk allocation Definition of Level of Service
11
Economy of Scale Efficiency Multi-skilled workforce
12
Contract Period Better resources Opportunity to invest in asset High value staff
13
Risk Allocation To party suffering consequences of failure to manage To party best able to lower risk
14
What has Worked Average road roughness has improved Smooth travel exposure has improved Surface condition (SDI) has improved Condition of structures has improved Provision of streetlighting has improved Roads are safer than peer local authorities Customer service has improved
18
What has not worked Dust KPM Difficult to measure Subject to environmental conditions
19
What has not Worked (2) Sealed Width KPM Good idea in principle Formula weighting focused on long straight underwidth roads Mountainous, winding roads were avoided New roads agreed by negotiation
20
What has not Worked (3) Streetlighting Intended to provide consistent level of illumination Difficult to measure consistently Difficult to address if lights are too far apart
21
Asset Manager - Inroads
David McDougall Asset Manager - Inroads
22
Asset Consumption Whole of Life Value for money Big Ticket Items
Consuming inherent value/life of an asset by deferring maintenance and thereby incurring more expense later Assessing the long term impacts that negate initial gains Applies to assets where life cycle>> contract period Big Ticket Items Resurfacing ($350k per annum) Pavement Reconstruction ($1M p.a.)
23
Why Resurface in a Performance Based Contract?
Resealing Why Resurface in a Performance Based Contract? Minimise maintenance costs (internal) Texture KPM (%<0.5mm thresholds) Surface Defects Index KPM f(RAMM Rating, High Speed Data) Residual Seal Life KPM
24
Residual Seal Life – Issues
RAMM Default life - based on average performance over similar geographical areas in NZ Start = End Compares existing age to RAMM default age f(traffic, seal type) ∑network Set at Year 0 KPM requires same Y0 Yr 8, 9 & 10 Flawed…? Why?
25
Residual Seal Life – Flawed? Why?
Large variation in actual performance Not necessarily start of Yr 0 Previous MIS, philosophy Conservative seal selection criteria Snapshot To 10 to match Yr 0? Counter productive Could extract more value with careful MIS
26
Residual Seal Life – Why is it Important?
Measurement of value left in a network Difficult to measure Now favour comparison to previous top surface Tracking texture change over time
27
Existing Top Surface vs Previous Top Surface
30
Seal Residual Life - Summary
Extending the life of an asset through a careful and proactive MIS thereby adding value Residual Life KPM should encourage the extraction of its maximum potential life through an effective MIS tracking age profiles not through Y0 profiles flexible risk transfer needs to have understanding/management
31
Pavement Residual Life
“Consuming inherent value/life of an asset by deferring maintenance and thereby incurring more expense later” What pavement KPMs drive Reconstruction? Roughness – STE Maintenance Costs Residual Life
32
Pavement Residual Life
Intent in 2002: Design Checks pre construction Performance Measurement Post Construction Use FWD deflection to measure Residual Life Transfer maintenance consequences Reality in 2010 Design Checks Verify Design Assumptions Post Construction Maintenance is only short term ( life)
33
Measure subgrade deflections
Design Theory Measure subgrade deflections Calculate thickness of aggregate to protect subgrade based on stiffness (Es)of aggregate Empirical Based on what has worked in past If we do this in these situations then % failures should be less than 5% No guarantees
34
Pavement Residual Life
We don’t know how to measure residual life of pavements Deflection (e.g. FWD) does not measure life We know when they have failed/about to fail Measurement/prediction of actual life is difficult
35
Pavement Residual Life
What have we learnt? Rely on good investigation, design Rely on Quality Assurance and Control during construction Monitor over time rutting and roughness Expected life projection based on actual annual trends in rutting and roughness
37
Transportation Manager - WBoPDC
Alex Finn Transportation Manager - WBoPDC
38
Team Culture Mindset “best for the network” Win-win approach Drive for innovation Danger of under-pricing Contractor must make a profit Reported through Balanced Scorecard
40
Customer Care Contractor and client support each other Sharing information Act jointly to resolve issues Managing community expectations Customer processes measured and reported Customer satisfaction surveys reported
42
Conclusion More for less Partnering relationship based on mutual respect Data specific Clearly articulated outcomes Councils seeks to extend Subject to NZTA endorsement
43
Questions
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.