1 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) HVDC SPARE PARTS OPTIMIZATION PRESENTED BY Mr.Montri Srisom-on (EGAT) Mr.Rozimi Remeli (TNB)

2 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) Meeting in Hat Yai th Aug 04

3 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) Meeting At Gurun 7 th Oct 04

4 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) MAIN OBJECTIVE CONCEPT OF SHARING DATABASES SHARING (TNB INSERT) OVERVIEW OF PRESENTATION:

5 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) Main Objective Minimize outage time Minimize costing on keeping HVDC spare parts Increase HVDC spare parts utilization and optimisation

6 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) CONCEPT OF SHARING Exchange all of spare databases. Only similar and critical spare items are considered to be shared by setting the method of sharing, consider the suitable number of max-min and responsible person to purchase.

7 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) Optimum number is as recommended by Siemens Minimum number is half of the optimum number Both parties shall maintain minimum number CONCEPT OF SHARING (continue)

8 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) Databases sharing will be done on neutral web page and can access by using password for security. Both parties have their own authority to update databases separately. Besides of databases on web site both parties shall update the hard copy for backup and exchange in every 6 months. DATABASES SHARING

9 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) (TNB INSERT)

10 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) FOR DISCUSSION

11 THAILAND – MALAYSIA 300/600 MW HVDC INTERCONNECTION EGAT-TNB JOINT MAINTENANCE CO-OPERATION COMMITTEE (JMCC) THE END THANK YOU