G LEN R IDGE P UBLIC S CHOOLS CONSTRUCTION PROJECT UPDATE FOREST AND LINDEN AVENUE SCHOOLS JULY 23, 2012.

Similar presentations


Presentation on theme: "G LEN R IDGE P UBLIC S CHOOLS CONSTRUCTION PROJECT UPDATE FOREST AND LINDEN AVENUE SCHOOLS JULY 23, 2012."— Presentation transcript:

1 G LEN R IDGE P UBLIC S CHOOLS CONSTRUCTION PROJECT UPDATE FOREST AND LINDEN AVENUE SCHOOLS JULY 23, 2012

2 INTRODUCTION After nearly a year of study and discussion, the Board of Education has decided to launch major capital improvement projects at Forest Avenue School and Linden Avenue School. These projects are designed to provide our educators with the additional space and flexibility necessary to meet the evolving educational needs of our youngest students. Through prudent management of the districts resources, we have a one-time opportunity to make these improvements without incurring debt. We could not undertake this initiative without the help and support of the community. We look forward to working and communicating with staff, parents and neighbors as we move forward.

3 STATEMENT OF NEED - CAPACITY FOREST AVENUE SCHOOL Functional201 students Current259 students Overage58 students LINDEN AVENUE SCHOOL Functional210 students Current278 students Overage68 students

4 STATEMENT OF NEED - ENERGY CONSERVATION E NERGY A UDIT R ESULTS W INGS MOST ENERGY INEFFICIENT SPACES IN THE D ISTRICT HVAC W INGS

5 STATEMENT OF NEED - USE OF SPACE FOREST AVENUE SCHOOL All Classrooms Used All Day Self-contained Special Education Classroom Resource Room Special Education Program Shared-Use Room: Resource Center/Reading Instruction Shared-Use Room: Morning Pre-K/Afternoon Art LINDEN AVENUE SCHOOL All Classrooms Used All Day Self-contained Special Education Classroom Resource Room Special Education Program Shared-Use Room: Morning Art/Afternoon Counseling, Meetings, OT/PT

6 ADDRESSING THE NEEDS FOREST AVENUE SCHOOL Classroom Small Group Instructional Room HVAC Wing Playground Basketball Court Eliminated LINDEN AVENUE SCHOOL Classroom Small Group Instructional Room HVAC Wing Playground

7 COST Forest$729,000 Linden$789,000 TOTAL$1,379,000

8 TASKS COMPLETED Educational Specifications Architectural Drawings Soil Testing Arborist Evaluation State Application

9 TASKS IMMINENT Confer with Mayor and Borough Manager Borough Committees Approvals (Planning Board, Historic Preservation Commission) State Approval Bids Neighbor Meetings Ongoing Communication

10 CONSTRUCTION TIMETABLE Schematic Design Process: 3 Months - April 7, 2012 Initiate Contract w/ Architect (DRG to draft and forward). Secure quote for Survey of properties. Secure quote for Site / Civil Engineering Services. Secure quote for Soils Engineering and Analysis

11 CONSTRUCTION TIMETABLE ( contd) NJDOE: District to provide an Educational Specification to support additions. Include mission statement, purpose, proposed occupancy, room amenities, etc. District to review proposed plan layouts provided by architect. Provide written comment for architect to make revisions. Architect to develop final floor plans and elevations for state and local review. Amend the currently approved LRFP via Board of Education Resolution. Adopt the final Educational Specifications and Drawings via Board of Education Resolution. Approve DRG to expedite application and all supporting materials to the NJDOE for Schematic Approval.

12 CONSTRUCTION TIMETABLE ( contd) Local Planning Requirements: Appear before Glen Ridge Planning Board for courtesy review as required by the NJDOE. Appear before Glen Ridge Historic Preservation Commission. Construction Documents Process: 2 Months - July 25, 2012 (REVISED) Collect site survey / soils information. Develop drawings and specifications. Consult with attorney on front end requirements. Send completed documents to DCA Trenton for review. Tony Brun has approved for final educational adequacy and forward to NJDCA to initiate Local Review. Local reviewer has agreed to meet next week to finalize the plans.

13 CONSTRUCTION TIMETABLE ( contd) DCA Trenton Review: 3 Months (varies) - Oct 1, 2012 DCA issues code review. Architect responds Preparing for bid Advertise - Bid Period 1 ½ Months - November 15, 2012 Construction 5-6 Months (varies) - May 15, 2013 Long lead items Windows - 16 weeks from order Unit Ventilators - 10 weeks from order


Download ppt "G LEN R IDGE P UBLIC S CHOOLS CONSTRUCTION PROJECT UPDATE FOREST AND LINDEN AVENUE SCHOOLS JULY 23, 2012."