Development Plan for Reliable Card-size IOC N. Kamikubota and S.Yamada, J-PARC/KEK May 2015 in MSU, kami, KEK/J-PARC.

Similar presentations


Presentation on theme: "Development Plan for Reliable Card-size IOC N. Kamikubota and S.Yamada, J-PARC/KEK May 2015 in MSU, kami, KEK/J-PARC."— Presentation transcript:

1 Development Plan for Reliable Card-size IOC N. Kamikubota and S.Yamada, J-PARC/KEK May 2015 in MSU, kami, KEK/J-PARC

2 May 2015 in MSU, kami, J-PARC/KEK In KEK, Blueberry-Raspberry-BeagleBone Blueberry By T.Kato-san (retired), in his farm (in Mt. Tsukuba) By N.Yamamoto and others, in J-PARC CCR (KEK-Tokai) Homemade Jam Hobby, training ・ 4 BBB controllers, each has 4 RS232C ports ・ 16 radiation-monitoring devices ・ trial to use low-cost card-size PC as an EPICS IOC By T.Obina, in 2014 in cERL (KEK-Tsukuba) Raspberry pi BeagleBone Black cERL, radiation monitoring Fig.s by T.Obina

3 May 2015 in MSU, kami, J-PARC/KEK Reliabiliy ? ・ BBB controllers in cERL, KEK-Tsukuba, have been working without any problem since early 2014 ・ But.. potential risks to introduce many BBB pieces - hardware weakness, long-term reliability and availability, etc. Develop a Customized Card-size IOC ・ J-PARC/KEK started design study with a company in Japan ・ aims “reliable BBB” ; with simple I/O, not much CPU power ・ Attentions toward higher reliability - selected parts (long-life CPU, careful choice of C,R, etc.) - against EM noises (ferrite in DC line, bi/bo photo isolation, etc.)

4 Design study for customized IOC Fig. by M.Nishizawa, Beat System Service, Japan 1 LAN for EPICS CA, 1 LAN for a device Heat contact (no fan, 7W) 12V DC in w. ferrite bead Display+2 USB For maintenance 2 serial ports for devices (RS232C and RS485 as default) Intel E3815 (1.46GHz 1 core, 1 thread) 2-GB DDR3L-SDRAM memory 1 disk-slot (SSD mSATA) 4 bi and bo ports w. photo isolations A plan view, not the final design

5 May 2015 in MSU, kami, J-PARC/KEK Two Chassis Plans Schedule and Cost ・ FY2015: Design study -> produce a few pieces of prototype - arrange them as EPICS IOCs, field tests in J-PARC Initial Cost: \?,000k # (not decided yet) ・ FY2016: mass production (here “mass”= 40-50 pieces) - replace 30-40 VME-bus IOC for networked PLC etc. - ~10 pieces for newly introduced devices after 2016 expected cost: ~\120k(USD1k) per piece + chassis (\30k or \120k) Fig. by M.Nishizawa, Beat System Service, Japan Single Multi (Rack-mount)

6 May 2015 in MSU, kami, J-PARC/KEK To friends in EPICS Community ・ give us a good name for this customized IOC ex) Blueberry ? ・ ask volunteers to join “mass production” in 2016: producing more pieces turns to cheaper cost per piece Thank you for your attention

7 Appendix: Customized PC Spec (by Beat System Service)

8 Sept. 2012, kami, KEK/J-PARC by M.Nishizawa, Beat System Service, Japan

9 Appendix: Card-size PCs (comparison by T.Obina)

10 From the presentation by T.Obina [1] T.Obina, "Development of Compact Device Server with EPICS", PASJ2014-MOOL08, 11th Annual Meeting of Particle Accelerator Society of Japan, 2014 May 2015 in MSU, kami, J-PARC/KEK

11 From the presentation by T.Obina [1] T.Obina, "Development of Compact Device Server with EPICS", PASJ2014-MOOL08, 11th Annual Meeting of Particle Accelerator Society of Japan, 2014 Note: now (May 2015), Raspberry Pi2 with improved CPU (900MHz Q-core ARM Cortex-A7) is available

12 Appendix : J-PARC Facility

13 J-PARC Japan Proton Accelerator Research Complex A joint project between JAEA and KEK JAEA – Japan Atomic Energy Agency (Nuclear Facility) KEK – High Energy Accelerator Research Organization (Academic Institute like Universities) 400MeV Linac, 3GeV RCS, 50GeV MR –and 3 Experimental Facilities (MLF, HD, NU) –Exp. user-run started Dec.2008-Apr.2009 Site is in JAEA in Tokai, Ibaraki, Japan by JAEA by KEK

14 J-PARC Facility J-PARC = Japan Proton Accelerator Research Complex 3 GeV RCS (25 Hz, 1MW) Hadron Beam Facility (HD) Materials and Life Science Experimental Facility (MLF) Neutrino to Kamioka (NU) 30 GeV MR (0.75 MW) Linac (330m) High- Inten. Proton

15 J-PARC Facility (KEK/JAEA ) Bird’s eye photo in January of 2008 South to North Neutrino Beams (to Kamioka) JFY2009 Beams 30 GeV Main Ring Hadron Exp. Facility Materials and Life Experimental Facility JFY2008 Beams 3 GeV RCS CY2007 Beams Linac CCR (Central Control Room)

16 J-PARC and KEK Sites Tsukuba KEK- Tsukuba Tokyo Tokai Tokyo-Narita Int’l Airport JAEA-Tokai 50km KEK- Tokai J-PARC is a Joint project: -> JAEA - Linac and RCS -> KEK - MR Shuttle Bus (90min.)

17 Recent Trials toward High-Power High-Power Trials –RCS: Dec.2014, success in transporting 1-MW equivalent beam to the MLF Target LI/RCS/MLF’s design goal is 1MW –MR: Mar.2015, one-shot trial reached at 390kW MR design goal is 750kW User Operations –MLF: 400kW user-run since Mar.2015 (before 300kW) 500kW user-run since Apr.2015 –MR: over 300kW for NU since Mar.2015 (before ~250kW) 300-350kW for NU in May 2015 * we will continue efforts to reach to the design goals May 2015 in MSU, kami, J-PARC/KEK