Presentation on Eco-Tourism Development Plan at Sagar Island a part of Integrated Coastal Zone Management Project, West Bengal 20 TH MAY,2016 THE WORLD.

Similar presentations


Presentation on theme: "Presentation on Eco-Tourism Development Plan at Sagar Island a part of Integrated Coastal Zone Management Project, West Bengal 20 TH MAY,2016 THE WORLD."— Presentation transcript:

1 Presentation on Eco-Tourism Development Plan at Sagar Island a part of Integrated Coastal Zone Management Project, West Bengal 20 TH MAY,2016 THE WORLD BANK

2 INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND

3 INTEGRATED COASTAL ZONE MANAGEMENT PROJECT AT SAGAR ISLAND Name of Project : Eco-Tourism Development Plan at Sagar Island, West Bengal, India Co-ordinator : State Project Monitoring Unit (SPMU), West Bengal PEA: : Sundarban Infrastructure Development Corporation ( a Govt. Enterprises of West Bengal) Consultant (ACF With PMC ) : HYDEA SpA, Italy and Ghosh, Bose & Associates (P) Ltd, India JV Project Cost : 36.84 Crore

4 BRIEF DESCRIPTION AND LOCATION OF THE PROJECT Sl. No. Name of WorkBrief Description and Location of Site Name of the Contractor Value of Work Awarded 1 Public Rain Shelter Cum Nat Mandir And Public Rain Shelter Cum Dala Arcade. Nat Mandir – An Open Pavilion with domed roof having an area of 450 Sq m Location –As on faces the temple, on the right side of the paved approach, right in front of the temple. Dala Arcade – A shopping arcade having 124 nos 10’ X 10’ shops to accumulate the dala vendors. Location – On the left side of the paved approach as face towards the temple M/s Viraj Project (P) Ltd Rs 13.20 Core 2 Eco- Camp Complex, Beach Shelter & Drainage. Eco-Camp – Consisting of Reception Centre, 20 nos small Eco-Huts, 10 nos Large tented Huts, Eating House & Toilet Blocks. Location – The Complex is located behind the temple complex between road no. 4 & 5. Beach Shelter – On the Beach overlook from the Temple. M/s Viraj Project (P) Ltd Rs 9.11 Core 3 Leach Pit Based Toilet and Permanent & Temporary Composite Solid Waste Management Facilities 20 Nos leach Pit Based Toilet Blocks comprising of 10 nos toilet in each block to be set up at 2 location, one near the exiting toilet right side of Road no. And another at the beach. 4 nos solid waste handling facilities shall be located at different locations covering the entire pilgrim area M/s N.K. Basu & Company Rs 2.12 Crore 4Bus Terminal.Bus Stand shall have Waiting Area, Food Court, Toilet Block and Tourist Information Centre & Transport Office Location – In the Road island at the confluence of Road No. 3,4&5 at the start of the Mela Ground M/s N.K. Basu & Company Rs 1.85 Crore

5 LOCATION OF ADOPTED ECOTOURISM FACILITIES ECO CAMP BUS STAND DALA ARCADE NAT MANDIR KAPIL MUNI ASHRAM BEACH SHELTERS COMPOSTING PLANT N LEACH PIT BASED TOILETS LEACH PIT BASED TOILET

6 Tendered Amount :- Rs 10,90,10,332.00 Name of Agency :- M/s Viraj Projects Pvt. Ltd. Date of Commencement as Per Work Order :- 27/01/2015 Expected Date of Completion :- 31/10/2016 Name of Job :- Public Rain Shelter Cum Dala Arcade

7 DALA ARCADE Area - 3095.75 sqm BIRDS’ EYE VIEW

8 NO. OF SHOPS – 124 AREA – 3095.75 SQM DALA ARCADE MAN EYE VIEW

9 Brief Description of the Project as on 30 th April 2016 Excavation :- 85% Completed. Filling Below Foundation (Yellow Sand) :- 80% Completed. Column Foundation (Base Raft) :- 19 Nos Out of 22 Nos Completed Column Casting 1 st Lift :- 22 Nos Out of 28 Nos Completed Column Casting 2 nd :- 18 Nos Out of 28 Nos Completed Column Casting 3 rd :- 18 Nos Out of 28 Nos Completed Toilet Block Slab at (+)3.45 m Level :- 01 Nos Out of 04 Nos Completed Lintel Casting :- 45 % Completed Damp Proof Course Work :- 50 % Completed Base Raft for Brick Work :- 75 % Completed Brick Work in Sub- Structure :- 70 % Completed Brick Work in Super Structure :- 60 % Completed Inside Shop Brick Work :- 30 % Completed Silver Sand Filling (Below Floor) :- 65 % Completed Grade Slab :- 40 % Completed Roof Slab Casting :- 30 % Completed

10 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to March In AprilCumulative Up to March In AprilCumulative 1Earth Work in Excavation Cum205047003527.434415.2353942.669 42.41%5.24%47.65% 2 Silver Sand Filling/ yellow sand filling Cum126756004004.956250.7224255.678 3 Plain Cement ConcreteCum900186.69940.235226.934 4 Reinforced Cement ConcreteCum1100659.28590.465749.750 5 Brick WorkCum1209.04665.37417.897683.271 6 ReinforcementMt15042.5384.90047.438 7 Back FillingCum750320.303 8 Anti Termite (Base & Wall)Sqm385056001557.470 9 Anti Termite (Below Floor)Sqm33001010.155 10 Damp Proof CourseSqm115.556.413 11 Earth DisposlCum53025002146.505 12 PlasterCum1265000 13 ShutteringSqm74502018.601410.1192428.722 14 Staging WorkCum5502000465.161145.255610.416 15 FlooringCum6420

11

12

13 Completion Status Major Mile Stone Basis Up to April 2016 Description of work Weight age % on the basis of Man Power Required Completion % as per weight age Excavation1512.75 Sand Filling in foundation21.6 Foundation Concrete54 Brick Work UPTO FFL107 Brick Wall from FFL to Bottom of Roof106 Floor Filling63.9 Floor Concreting104 Roof Concreting257.5 Partition Wall30.9 Inside Plaster20 Outside Plaster20 Finish Flooring20 Electrical20 Painting10 Sanitory10 Land Scaping20 Door Windows10 MISC WORK10 TOTAL10047.65

14

15 Roof Casting Work is on Progress

16 Public Rain Shelter Cum Dala Arcade ( Silver Sand Filling work is on Progress)

17 Sand Filling and Foundation work is on Progress

18 Brick Work is on Progress

19 BAR CHART PUBLIC RAIN SHALTER CUM DALA ARCADE Approved Drawing for Foundation received on 20-04-2015 so consider same date as start 3rd week WEEK 123456789101112131415161718192021 22232425262728293031 32323334353637 38383940 4141424344454647484950515253545556575859606162636465666768697071727374757677787980 Scope of work Site was demobilised and work was completely stopped due to Ganga sagar mel aa Mobilization Excavation, Filling & Ramming Work was stooped due to decission in of excavation quantity not finalised P.C.C Footing P.C.C For Masonary R.C.C Footing R.C.C Column Upto GR,Level Masonary Upto GR,Level R.C.C Column upto Bottom of Slab Masonary Upto Bottom of Slab Slab (R.C.C) Water Proofing Fixing of Door Windows Internal Plaster Electrical Inernal Flooring 5 Sanitary Internal Inside Painting Land Scaping Land Lighting Out Side Plastering Out Side Painting Cleaning & Misc. ORIGINAL REVISED BAR (incorporated the 52 days of work loss due to heavy rainfall ) This Programme is Archiveable when all condition of the contract will be Honoured by Employer

20 Tendered Amount :- Rs 23,828,531.00 Name of Agency :- M/s Viraj Projects Pvt. Ltd. Date of Commencement as Per Work Order :- 27/01/2015 Expected Date of Completion :- 31/10/2016 Name of Job :- Public Rain Shelter Cum Nat Mandir

21 VIEW OF NAT MANDIR Area – 606.434 sqmSitting Capacity - 725

22 Brief Description of Project as of 30 th April 2016 Foundation : - Completed. Filling below foundation (Yellow Sand) :- Completed. Back Filling by Excavated Earth :- Completed. Tie Beam :- Completed. Column up to Roof Beam Bottom :- Completed. Silver Sand Filling below Plinth :- Completed. Plain Cement Concrete below Floor :- Completed. Grade Slab :- Completed. Roof Beam & Dome Shuttering :- 50% Completed. (As per Previous Drawing) Reinforcement Work for Roof :- 40% Completed. (As per Previous Drawing) Roof & Dome Casting :- 1 st Dome 50% & 2 nd Dome 40% (As per previous Drawing. Dome Shuttering (As Per Revised Drg.) :- 2 Nos Dome Completed & Work is in Progress in another 2 Nos Dome. Reinforcement Work (As Per Revised Drg.) :- 2 Nos Dome Completed. Casting of Dome :- Work in progress in 2 Nos Dome Note: - The Work Stopped due to disagreement of Mohanto of Kapil Muni Ashram regarding the shape of dome from 20 th November 2015. Revised drawing had been issued and the work started from 17/3/2016.

23 Sno.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to March In AprilCumulative Up to March In AprilCumulative 1 Earth Work in Excavation Cum575900 893.5920.00893.592 59.08%4.72%63.80% 2 Silver Sand Filling/ yellow sand filling Cum460410 407.7830.00407.783 3 Plain Cement Concrete Cum 181 62.6160.0062.616 4 Reinforced Cement Concrete Cum255.3 171.53718.000189.537 5Brick WorkCum175 128.0940.00128.094 6ReinforcementMt33 11.0840.50011.584 7Back FillingCum280 780 775.1380.00775.138 8PlasterCum3365 9ShutteringSqm1110 1195.017558.001753.017 10FlooringCum1905

24

25

26 Completion Status Major Mile Stone Basis up to April 2016 Description of work Weight age % on the basis of Man Power Required Completion % as per weight age Excavation15 Sand filling44 Foundation15 Column + Masonary upto FFL55 Floor At GRL10 Column upto Bottom of Roof10 Roof Casting244.8 Tiling work60.0 Plaster20.0 Electrical20.0 Painting20.0 Landscaping50.0 TOTAL10063.8

27

28 Dome Shuttering & Concreting work is on progress

29 Date;- 30.09.15 BAR CHART PUBLIC RAIN SHALTER CUM NAT MANDIR Date of Proceed of Work- 27-01-2015: Foundation Drawings recived on 24:04:2015 MONTHS WEEK 12345678910112131415 1616 171718 1919 2020 21212 2323 2424 2525 2626 2727 2828 2929 3030 3131 32323 3434 3535 3636 3737 3838 3939 4040 4141 4242 43434 4545 4646 474748495051525354556 575758 595960616263646566 6767 6868 6969 7070 7171 7272 7373 Scope of work Mobilization Excavation,Filling & Ramming P.C.C Footing R.C.C Footing R.C.C Column & Tie Beam Upto PL,Level Outer Side Brick Stalt Ground Floor P.C.C & R.C.C Column's upto Floor Level Electrical Internal Work Stopped on 21:11:2015 client instruction due to change in Drawing.Changed roof Drawings released on 17:02:16 Top Slab Internal & External Plaster Flooring Water Proofing Painting (Internal & External) Land Scapping Landscap Lightining Cleaning & Misc. ORIGINAL REVISED BAR (incorporated the 52 days of work loss due to heavy rainfall )

30 ECO-CAMP SITE EATING HOUSE 8500 X 8500 SMALL HUT (20 NOS) 5000 X 4100 LARGE HUT (10 NOS) 6500 X 6500 RECEPTION 10500 X 8000 TOILET BLOCK

31 LARGE HUTSMALL HUT EATING HOUSETOILET BLOCK

32 Tender Amount :- Rs 51,294,983.95 Name of Agency :- M/s Viraj Projects Pvt. Ltd. Date of Commencement as Per Work Order :- 27/01/2015 Expected Date of Completion :- Name of Job :- Eco-Camp Complex

33 Large Hut (10 Nos) Excavation :- 8 Out of 10 Nos Hut Completed. Foundation :- 8 Out of 10 Nos Hut Completed. Column upto Plinth Level Slab :- 8 Out of 10 Nos Hut Complete. Casting of Plinth Slab :- 7 Out of 10 Nos Hut Completed. Column up to Eaves Beam Bottom :- 7 Out of 10 Nos Hut Completed. Casting of Eaves Beam :- 7 Out of 10 Nos Hut Completed. Brick work Above Plinth :- 6 Out of 10 Nos Hut Completed. Small Hut (20 Nos) Excavation :- 14 Out of 20 Nos Hut Completed. Foundation :- 11 Out of 20 Nos Hut Completed. Column upto Plinth Level Slab :- 11 Out of 20 Nos Hut Completed. Casting of Plinth Slab :- 9 Out of 20 Nos Hut Completed. Column up to Eaves Beam Bottom :- 9 Out of 20 Nos Hut Completed. Casting of Eaves Beam :- 5 Out of 20 Nos Hut Completed. Brick work Above Plinth :- 2 Out of 20 Nos Completed.

34 Eating House (1 No.) Excavation :- Completed. Foundation :- Completed. Column up to Plinth Level Slab :- Completed. Casting of Plinth Slab :- Completed. Column up to Eaves Beam Bottom :- Completed. Casting of Eaves Beam :- Completed. Brick Work Above Plinth :- Completed. Toilet Block (2 Nos) Excavation :- 2 Out of 2 Nos Block Completed. Foundation :- 2 Out of 2 Nos Block Completed. Column up to Plinth Level Beam :- 2 Out of 2 Nos Block Completed. Plinth Level Beam :- 2 Out of 2 Nos Block Completed. Plinth Level Slab :- 2 Out of 2 Nos Completed. Brick Work above Plinth :- 1 Out of 2 Nos Completed up to Lintel Level. Reception Block (1 No.) Excavation :- Completed. Foundation :- Complete. Pedestal upto Plinth Level Slab :- Complete. Plinth Level Slab :- Complete.

35 Sl.No. DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to March In AprilCumulative Up to March In AprilCumulative 1Earth Work in ExcavationCum60080005121.33468.045589.37 30.46% 3.69% 34.15% 2 Silver Sand Filling / Yellow Sand Filling Cum2632000905.4257.99963.41 3Plain Cement ConcreteCum11178.4654.9383.395 4Reinforced Cement ConcreteCum344700508.2366.04574.27 5Brick WorkCum480.5192.614.8197.41 6ReinforcementMt406046.036.1352.160 7ShutteringSqm267843003341.38533.643875.02 8Back FillingCum5137200 1925.79 8 251.052176.888 9FlooringCum10330.00

36

37

38 Completion Status Major Mile Stone Basis up to April 2016 Description of work Weightage % on the basis of Man Power Required Completion % as per weightage Excavation1511.25 Sand Filling in foundation21.4 Foundation107.0 Upto Floor Slab106.0 Upto Eaves Beam105.5 Masonary upto Eaves Beam103 Roof100 Plastering50 Door Windows20 Flooring30 Electrical50 Sanitory30 Painting20 Land Scaping30 MISC WORK100 TOTAL10034.15

39

40 ECO-CAMP – EATING HOUSE-BRICK WORK COMPLETED ECO-CAMP – TOILET BLOCK-I (UP TO LINTEL LEVEL) ECO- CAMP – LARGE HUT (BRICK WORK ABOVE PLINTH) ECO- CAMP – LARGE HUT– STRUCTURAL WORK IN PROGRESS

41 ECO-CAMP TOILET BLOCK II– (COLUMN COMPLETED UPTO LINTEL LEVEL) ECO-CAMP – RECEPTION CENTRE– PLINTH SLAB COMPLETE ECO-CAMP – SMALL HUT – EAVES BEAM WORK IS IN PROGRESS ECO-CAMP – SMALL HUT (BRICK WORK)

42 Tender Amount :- Rs 40,484,059.00 Name of Agency :- M/s Viraj Project Pvt. Ltd. Date of Commencement as Per Work Order :- 27/01/2015 Work Not Yet Started. Name of Job :- Drainage & Beach Shelter

43 BUS STAND No. of Buses- 38.

44 FOOD COURT (BUS STAND) TOURIST INFORMATION & TRANSPORT OPERATOR’S OFFICE FRONT ELEVATION

45 WAITING AREA (BUS STAND)

46 Tender Amount :- Rs 18,517,073.93 Name of Agency :- M/s N.K. Basu & Company Date of Commencement as Per Work Order :- 27/01/2015 Expected Date of Completion :- 30-11-2016 Name of Job :- Bus Terminal

47 Bus Terminal Present Position Waiting Area. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Eaves Beam :- Completed. Brick Work :- Stair Brick Work Completed. Back Filling :- Completed. Plastering work :- Completed. Grade Slab :- Completed. Food & Drink Facility. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Eaves Beam :- Completed. Back Filing :- Completed. Brick Work :- Completed. Plastering work :- Completed Grade Slab :- Completed. Toilet Block. Foundation :- Completed. Column :- Completed. Tie Beam :- Completed. Back Filing :- Completed. Lintel & Chajjah Casting :- Completed. Eaves Beam :- Completed. Brick Work :- Completed. Plastering :- Completed. Grade Slab :- Completed. Tourist & Information Office. Excavation :- Completed. Foundation :- Completed. Pedestal :- Completed. Back Filling :- Completed. Tie-Beam :- Completed. Column :- Completed up to Eaves Beam Bottom Brick Work (Above Plinth) :- Completed up to Eaves Beam Bottom Septic Tank & Soak Pit :- 2 nos Completed.

48 Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to March In AprilCumulative Up to March In AprilCumulative 1 Earth Work in Excavation Cum1802100 1847.67 5 0.001847.675 52.45%0.10%52.55% 2Yelow Sand FillingCum 405404.2180.00404.218 3Silver Sand FillingCum335 106.860.00106.86 4Plain Cement ConcreteCum110 97.7680.0097.768 5 Reinforced Cement Concrete Cum191350 264.9820.00264.982 6Brick WorkCum170.75 145.1833.184148.376 7ReinforcementMt29 13.6650.0013.665 8ShutteringSqm18152000 1293.29 1 0.001293.291 9Back FillingCum1251275 1263.09 6 0.001263.096 10Septic Tank & Soak PitNos 2 112 11PlasterCum9352000 924.7190.00924.719

49 Description of work Weightage % on the basis of Man Power Required Completion % as per weightage Excavation2520 Sand filling52.8 Foundation2316.58 Massonary Above Plinth32.47 Floor At GRL33 Column upto Bottom of Roof76 Roof Casting100.0 Tiling work30.0 Plaster31.5 Electrical10.0 Painting10.0 Brick Pavement100.0 Plumbing & Sanitary10.2 Landscaping20.0 Door & Window Fixing10.0 Misc Work20.0 TOTAL10052.55 Completion Status Major Mile Stone Basis up to April 2016

50

51

52 Description of work Weightage % on the basis of Man Power Required Completion % as per weightage Excavation2520 Sand filling52.8 Foundation2316.58 Massonary Above Plinth32.47 Floor At GRL33 Column upto Bottom of Roof76 Roof Casting10 Tiling work3 Plaster31.5 Electrical1 Painting1 Brick Pavement10 Plumbing & Sanitary10.2 Landscaping2 Door & Window Fixing1 Misc Work2 TOTAL10052.55

53

54 BUS TERMINAL – WAITING AREA – PLASTERING COMPLETE BUS TERMINAL – FOOD & DRINK FACILITY – PLASTERING COMPLETE BUS TERMINAL – TOURIST & INFORMATION CENTRE –BRICK WORK COMPLETE BUS TERMINAL – TOILET BLOCK – PLASTERING COMPLETE

55

56 Name of Job :- Leach Pit Based Toilet & Temporary and Permanent Composite Solid Waste Facility Tender Amount :-Rs. 21,224,549.75 Name of Contractor :- M/s N.K. Basu & Company Date of Commencement as Per Work Order :- 27/01/2015 Expected Date of Completion :- 30-11-2016

57 Brief Description of the Project as on 30 th April 2016 Out of 20 Nos Unit – Work is on Progress in 12 Nos Unit 5 Nos Block Completed up to Super Structure. 2 Nos Block Completed up to Sub Structure. 5 Nos Block Excavation & Leach Pit Brick Work Completed Sl.No.DescriptionUnit Tender Quantity Tentative Revised Qty Executed Qty.Physical Progress Up to March In April Cumulative Up to March In AprilCumulative 1. Construction of temporary toilet blocks with Leach Pit based onsite treatment system - 10 toilet per unit Nos20751240%5%45% Leach Pit Based Toilet

58

59 (under construction)

60

61 Name of Agency :- M/s N.K. Basu & Company Date of Commencement as Per Work Order :- 27/01/2015 Work Not Yet Started. Name of Job :- Temporary & Permanent Composite ` Soild Waste Facility

62 FINANCIAL PROGRESS AS OF 30 th APRIL, 2016 Sl. no.Name of ContractorName of JobContact Value Financial Progress Up to March In AprilCumulative 1M/s Viraj Project (P) Ltd. Construction of Rain Shelter cum Nat Mandir 23,828,531.0028.96%3.54%32.50% 2M/s Viraj Project (P) Ltd. Construction of Rain Shelter cum Dala Arcade 109,010,332.0027.96%2.81%30.774% 3M/s Viraj Project (P) Ltd. Construction of Eco- Camp Complex, 51,294,983.9540.24%4.42%44.66% 4M/s Viraj Project (P) Ltd. Construction of Beach Shelter & Drainage 40,484,059.000.00% 5M/s N.K. Basu & Company Construction of Bus Terminal 18,517,073.9344.82%0.92%45.74% 6M/s N.K. Basu & Company Construction of Leach Pit Based Toilet & Temporary and permanent composite solid waste facility 21,224,549.759.99%0.00%9.99%

63 Financial Progress

64 PAYMENT DETAILS Package -1: Construction of Public Rain Shelter cum Nat Mandir & Public Rain Shelter cum Dala Arcade Package -2: Construction of ECO - Camp Complex, Beach Shelter and Drainage Sl. No. RA Bill reference & DateDate of Certification Amount (Rs) Remarks 1. Mobilisation Advance 6.642 million 2.1 st RA Bill25/8/201591.94 Lac 3.2 nd RA Bill18/09/2015 22.63 Lac 4.3 rd RA Bill01/10/2015 44.93 Lac 5.4 th RA Bill18/12/2015 43.06 Lac 6.5 th RA Bill28/12/2015 33.09 Lac 7.6 th RA Bill13/01/2016 48.47 Lac 8.7 th RA Bill22/03/2016 25.12 Lac 98 th RA Bill27/04/2016 64.71 Lac Total = 440.37 lac Sl. No. RA Bill reference & DateDate of Certification Amount ( Rs) Remarks 1. Mobilisation Advance 4.589 million 2.1 st RA Bill25/8/201523.75 Lac 3.2 nd RA Bill18/09/2015 18.53 Lac 4.3 rd RA Bill01/10/2015 5.68 Lac 5.4 th RA Bill18/12/2015 25.32 Lac 6.5 th RA Bill28/12/2015 25.62 Lac 7.6 th RA Bill13/01/2016 26.34 Lac 8.7 th RA Bill01/02/2016 30.42 Lac 9.8 th RA Bill08/03/2016 22.19 Lac 109 th RA Bill27/04/2016 28.36 Lac Total = 252.10 Lac

65 Package -3: Construction of Leach Pit Based Toilet and Solid Waste Management Facility Package -4: Construction of Bus Terminus Sl. No. RA Bill reference & Date Date of Certification Amount (Rs.)Remarks 1. Mobilisation Advance1.061 million 2.1 st RA Bill23/01/201621.19 LacsTotal = 31.80 Lac Sl. No. RA Bill reference & Date Date of Certification Amount (Rs.) Remarks 1. Mobilisation Advance0.925 million 2.1 st RA Bill25/8/201523.90 Lac 3.2 nd RA Bill31/10/2015 15.77 Lac 4. 3 rd RA Bill7/12/2015 31.29 Lac 5. 4 th RA Bill22/03/2016 10.19 Lac Total = 90.40 Lac

66 BOTTLENECK OF THE PROJECT Change in Design & Bill of quantity as per Soil Investigation after award of contract. Inaccessibility of the site during rainy season Labour problem during election Period Frequent revision of Drawings of the structure and not timely submission also. Variation of quantities of BOQ with actual site condition and problems arise from that Inappropriate Monitoring of the progress of work by the Consultant in respect of the work Programme.

67 Measures Taken Drawing protocol has been finalised to avoid frequent revisions. Consultant has been requested for close monitoring for progress and appropriate action on agency thereon.

68 THANK YOU