1 1 1/15 Status of the Nuclotron-NICA G.Trubnikov MAC, June 7, 2011

2 2 KVINTA : 70 hours Gamma-3: 24 hours (Belarus, Poland, Czech, Greece, Germany, Bolgaria) MPD-STRELA (MRPCfor MPD): 72 hours (Russia, China, Germany) Delta-LNS: 67 hours (Russia) FAZA: 52 hours (JINR, ITEP) NIS-GIBS: 10 hours (JINR) KVINTA : 70 hours Gamma-3: 24 hours (Belarus, Poland, Czech, Greece, Germany, Bolgaria) MPD-STRELA (MRPCfor MPD): 72 hours (Russia, China, Germany) Delta-LNS: 67 hours (Russia) FAZA: 52 hours (JINR, ITEP) NIS-GIBS: 10 hours (JINR) MPD-STRELA 2/15 Nuclotron Run 43 21 February - 22 March 2011

3 Estimation of the average vaccum in the Nuclotron ring measuring circulating deutron beam lifetime at Е=5 MeV/u corresponds to the vacuum pressure not worse than 4*10 -10 Тоrr. Estimation of the average vaccum in the Nuclotron ring measuring circulating deutron beam lifetime at Е=5 MeV/u corresponds to the vacuum pressure not worse than 4*10 -10 Тоrr. Magnetic field, T Beam intensity, particles 2/15 Nuclotron-M Results

4 4 New digital system for on-line beam orbit measurment Nuclotron Run 43 21 February - 22 March 2011 Beam signal amplitude evolution from pick-ups (Acceleration. Field rising from 300 to 1000 Gs) 3/15

5 4.5÷ 5·10 10 (d) at 300 MeV/u For the first time at Nuclotron had been performed beam slow extraction 3,1 GeV/u 4/15 Nuclotron-M Results

6 6/15 Automatic beam orbit correction system (kit of 28 correctors) Nuclotron Run 43 21 February - 22 March 2011 MCP detector for residual gas ions registration Beam profile evolution at acceleration (transverse and longitudinal)

7 7/15 7 First 6 turns (about 50  s), deutron beam after orbit correction. Blue - injected beam, Red - signal from pick-up. Circulating beam signals during 1150 ms. Small increasing of the signal amplitude is connected to beam de-bunching Nuclotron-M Results

8 Full-scale reconstruction of the power supply system for whole complex ! 8/15 Nuclotron-M Results

9 9/15 Nuclotron-M Results

10 10/15 Nuclotron-NICA foreinjector Cascade transformer up to 0,7 MeV p,d laser ESIS dd

11 11/15 Heavy Ion Source KRION-6T Nuclotron-NICA Assembling of electron/ion optics system: view from the “ion extraction” side. Superconducting test coil (L=19 cm, 32 layers of SC wire) : preparation for testing in a liquid helium. Magnetic field (T) versus current (A) for SC solenoids; experimental and expected data. 1) 26 layers (green line, 21 Jan.’11) – 7.41T at I_crit.=131 A (experimental data); 2) 32 layers (top green line, 25 Apr.’11) – 7.81T at I_crit=114 A (experimental data); 3) red line: critical current for SC wire according it’s manufacturer data; 4) blue line: expected for Krion-6T ESIS – 22 layers, L=120 cm, B=6 T at I_working=118 A. Should be ready in September 2011.

12 12/15 Source of polarized particles (p, d, H) JINR+INR RAS Nuclotron-NICA We plan to assemble and TEST SPP at Nuclotron with  d in the end of 2012

13 13/15 Nuclotron-NICA RF ON (h=1), Buncher ON RF ON (h=10), Buncher ON RF OFF, Buncher OFF Stochastic cooling system prototype at Nuclotron Vacuum chamber for kicker Vacuum chamber for pick-up Slot-coupler structures, manufactured at IKP FZJ We plan to assemble and TEST stochastic cooling system prototype at Nuclotron in the end of 2011 (everything will depend on electronics delivery)

14 14/15 Moreover: - dedicated test bench for injection system (inflector plates) into Booster is in operation; - dedicated prototype of HV platform (PS 225kV/3A) is under assembly; - new system of the whole complex synchronization is under design and construction; - new thermometry and quench detection system for Nuclotron is in progress; - … PLANS: Next run at Nuclotron with prolonged period (1,5-2 months) is planned for November-December 2011 and beam will be delivered mainly for physicists. Nuclotron-NICA

15 15/15 Thank you for your attention