Aquatic Facility Evaluation Date: 5/7/15 Kyle McCawley, P.E. City of Merriam.

Similar presentations


Presentation on theme: "Aquatic Facility Evaluation Date: 5/7/15 Kyle McCawley, P.E. City of Merriam."— Presentation transcript:

1 Aquatic Facility Evaluation Date: 5/7/15 Kyle McCawley, P.E. City of Merriam

2 Project Scope Pool basin/shell condition Perimeter deck and fence Play amenities Building structures Mechanical space Recirculation system Disinfection system ADA accessibility Safety concerns Aquatic Facility Evaluation

3 Bathhouse ItemConcernResolution ADA Access (Bathhouse) Current configuration does not meet standards - Water closets - Lavatories - Shower compartments Renovated the bathhouse Bathhouse skylightsCrackedReplace

4 Main Pool ItemConcernResolution ADA Access (Main Pool)Hose in accessible routeRelocate the hose connection, or install a pool lift with a battery ADA Access (Main Pool)Change in level for the stair accessInstall without a change in level Concrete deteriorationDeteriorating deep-end transitionReplace Gutter/deck joint (Main pool)Deterioration of concreteDevelop a long repair with a structural engineer Basin lifeDeterioration of concrete Replace within 6-10 years

5 Slide Pool ItemConcernResolution Slide tower deckingExcessive corrosionReplace Slide tower structural steelSurficial corrosionClean and recoat Slide tube seamsSeparationReseal Concrete deteriorationDeteriorating slide pool stepsReplace Basin lifeDeterioration of concrete Replace within 8-12 years

6 Wading Pool ItemConcernResolution ADA Access (Wading Pool) Current configuration does not meet standardsInstall a pool lift Wading pool slide pumpOverheatingInstall ventilation system Drain pipingCorroded at the slide pool and the wading poolReplace Deck railingCorroded at the wading poolReplace

7 Mechanical Room ItemConcernResolution Filtration systemDeteriorating due to - Age of system - Excessive corrosion Replace Electrical panelsSurficial corrosionClean

8 Implementation Plan Year 0 to 2 Item TasksEstimated Cost Slide tower deckingReplace$25,000 to $50,000 Slide tower structural steel -Clean and recoat -Replace compromised components $5,000 to $20,000 Filtration systemReplace$75,000 to $125,000 ADA Access (Wading Pool) Install a pool lift$5,000 to $10,000 ADA Access (Main Pool) Install a pool lift with a battery$5,000 to $10,000 ADA Access (Main Pool) Install without a change in level$2,500 to $5,000 Wading pool slide pumpInstall ventilation system$2,500 to $5,000 In-pool lightingReplace$5,000 to $10,000

9 Implementation Plan Year 3 to 4 Item TasksEstimated Cost Concrete deterioration -Repair main pool deep end transition -Repair slide pool steps $2,500 to $5,000 Basin CoatingRecoat$25,000 to $50,000 Gutter/deck joint (Main pool) Develop a long repair with a structural engineer $25,000 to $50,000 Cracked skylightsReplace$5,000 to $10,000 Slide tube seamsReseal$1,000 to $2,000 Electrical panelsClean$500 to $1,000

10 Implementation Plan Year 5 to 6 Item TasksEstimated Cost ADA Access (Bathhouse) Renovation$400,000 to $500,000 Drain pipingReplace$10,000 to $20,000 Deck railingReplace$2,500 to $5,000 Deteriorating basinsReplace$1,500,000 to $2,500,000

11 Questions?


Download ppt "Aquatic Facility Evaluation Date: 5/7/15 Kyle McCawley, P.E. City of Merriam."