Download presentation
Presentation is loading. Please wait.
1
Introduction to Wastewater Treatment
Mark O. Liner, P.E. Naturally Wallace Consulting
2
Wastewater Engineering
If I gave you a jar of this and said ….get it clean. What would you do?
3
How to go from A to B to C? Treatment of Natural Gas Condensate
4
Reverse Engineering Glass of water and add:
Sand Sugar Salt Oil How do you make this water clean?
5
Design Steps Decision: Wastewater Treatment is Needed Basis of Design
Process Selection Preliminary Design Final Design
6
First Step: Basis of Design
Most important step of the project !!! Foundation for all decisions Dictates project $$$s Changing the Basis of Design halfway thru the project is like changing ….
7
Basis of Design Data Flow Influent Characterization
Effluent Requirements Miscellaneous Considerations
8
Flow – Measurement Weirs Flumes Meters Beware of chunks
9
Flow - Domestic Usually predictable
10
Flow - Industrial Usually unpredictable Engineers want predictable
11
Flow - Equalization Hold and discharge Treat as it comes Treatment
Equalization best money spent Gets you to steady state Treatment Equalization Treat as it comes Equalization Treatment
12
Flow – Design Numbers Minimum and maximum hourly flow
For pipe/channel sizing Average daily flow For mass balance, chemical usage, and sludge production
13
Characterization - Analytes
Nitrogen Phosphorus pH Alkalinity Metals Bacteria/Algae Solids Total (TS) Dissolved (TDS) Suspended (TSS) Organics Biodegradable (BOD) Chemically Oxidized (COD) Volatile (VOC) Oils (O&G, TPH)
14
Characterization - Table
Average plus one standard deviattion
15
Effluent Requirements
Typically set by government Depends on disposal method River Groundwater Land Moving target ??? It pays to discuss and negotiate
16
Miscellaneous Site Constraints Climate Money Time Land Availability
Capital Costs Operating Costs Time Start date Project Life
17
Design Steps Decision: Wastewater Treatment is Needed Basis of Design
Process Selection Preliminary Design Final Design
18
Second Step: Process Selection
Given a Basis of Design, what is the best way to go from A to B to C??? Experience is crucial in this step Engineer/Vendor dance
19
Process Selection
20
Process Selection Proof of Concept
Coffin Butte Landfill, Oregon Pumped flow from leachate barrel, Masterflex peristaltic Standpipe, unglued grease slip fit to elbow Collection header same as underdrain Distribution header same as underdrain Inexpensive poly tank 44-gal, AES BT44 Recirc Inexpensive poly tank 44-gal, AES BT44 bh Masterflex peristaltic Tank 1 bh Tank 2 tu tu Tank 3 To drain tu bh Tank 4 bh tu tu tu tu tu bh bh tu tu bh Blocks tu tu tu tu BOD Removal - passive Nitrification / Anammox – FBA (aerated) Nitrification / Anammox - FBA (aerated) Graduated poly tank 55-gal with lid, AES T55 Denitrification / metals removal
21
Process Selection – Pilot Plant
22
Process Selection – Primary Treatment
The lowly septic tank – the “greenest” wastewater treatment technology No electricity…
23
System Selection – Primary Treatment
Solids removal Screening Grit Removal Sedimentation Floatation Dissolved Air Floatation Oil/Water Separator Removing sand
24
System Selection – Biological Treatment
Soluble wastewater can not be removed as a solid So, we have bacteria eat it and remove them The trick is to create an environment for them to live and STAY
25
System Selection – Secondary Treatment
26
System Selection – Biological Treatment
Design Considerations Aerobic and anaerobic bacteria Periodic sludge removal Solids separation to keep bacteria from flowing downstream Nutrient requirements (industrial Limits 30 mg/L Biochemical Oxygen Demand 30 mg/L Total Suspended Solids
27
System Selection – Tertiary Treatment
Filtration Membrane Sand Carbon Chemical Addition pH Adjustment Disinfection Ultraviolet Chemical
28
Design Steps Decision: Wastewater Treatment is Needed Basis of Design
Process Selection Preliminary Design Final Design
29
Preliminary Design Drawing set to build consensus Process Schematic
Site Plan Hydraulics
30
Process Schematic
31
Site Plan
32
Hydraulic Profile
33
Design Steps Decision: Wastewater Treatment is Needed Basis of Design
Process Selection Preliminary Design Final Design
34
Final Design Selection and sizing of minor equipment Pumps and piping
Tanks Instrumentation Aeration Equipment Concrete Electrical
35
Coordination of All Disciplines
36
Final Design Communicate what is to be built to contractor
Basis of cost estimate for Owner and cost quote from contractor Represents details from all disciplines
37
Thank You
38
Mark O. Liner, P.E. Naturally Wallace Consulting
Lagoon Technology Mark O. Liner, P.E. Naturally Wallace Consulting
39
Lagoon ??? More lagoon systems in the USA than any other system
Easy to build and maintain Very little is written about them Not much to say!!!
40
Types of Lagoons Anaerobic Facultative Polishing Partial Mix
Complete Mix High Performance Batch Reactor Equalization/Storage Evaporation/Cooling
41
Lagoon Applications Covered Agricultural Contaminated Stormwater
Lagoons are everywhere. Small towns, pig farms, paper mills, airports. Seems like everyone has one. Call it a pit, a pond, Contaminated Stormwater Mine Water Treatment Advanced Domestic Wastewater
42
What is it??? Constructed basin Lined Water level control
Sludge Lagoon in Slovenia
43
What are they good for? What are lagoons good for? Solids Management
Removal and Storage Oxidation of Organics (BOD) Naturally Mechanically Hydraulic Equalization Smooth out the peaks
44
How do you design??? Function related to design Water depth
Surface area Detention time Anaerobic Lagoon (6.0 meter deep) Facultative Lagoon (1.5 meter deep)
45
Solids Removal What are solids? Sedimentation rate Organics (bacteria)
Inorganics (silt and sand) Algae Sedimentation rate Wind/Turbulence Type of solids Concentration of solids
46
Settling Time
47
Sludge Accumulation Settled solids undergo digestion and compaction over time Rule of Thumb: 0.5 m3/m3/d sludge accumulation for domestic wastewater
48
Sludge Accumulation Plot
51
Algae Employed in facultative lagoons
Diurnal cycle cause fluctuations in Dissolved oxygen pH Solids Measured by Chlorophyll Alpha test
52
Organics Removal Simplified model assumes steady state complete-mix reactor Equation:
53
Government Design
56
Advanced Design Linvil Rich Current Advanced Design Methods L. Rich
Grady and Daigger Metcalf & Eddy Performance Modeling by Biomass Growth not BOD removal Same Modeling Techniques That Are Used For Designing Conventional Sewage Plants Linvil Rich
57
Theoretical Relationship
58
Anaerobic Lagoons Deep > 3 meter deep Covered Loading
Grease cap Floating cover Loading 0.04 – 0.30 kg-BOD/m3/d Detention Time 1-50 Days
59
Aerobic Lagoons Taking oxygen in gas phase to water in liquid phase
Passive = ambient transfer Active = mechanical Floating Aerators Blower and Diffusers
60
Aeration by Diffusers
61
How much oxygen? Calculate mass of oxygen required for bacterial degradation AND digestion Correct for field conditions
62
Mixing Lagoons have low solids Low energy/volume Large volumes!!!
1-2 W/m3 = rule of thumb
63
Short Circuiting
64
Short Circuiting
65
Civil Design Site Soils and Water Seal
66
Soils Testing for Lagoons
Minimum Requirements Four borings per 0.5 acres Depth to 10’ below design floor One boring to 25’ Borings located at deepest excavation Borings at borrow pits for nature and consistency Vertical Separation 4’ between pond seal and maximum groundwater level 2’ separation permitted for synthetic liners
67
Lagoon Seals Percolation less than 1/16” per day at 6’ water depth
Soil seals shall be clay or include bentonite Minimum thickness of 4” Synthetic Seals Greater than 30 mil thickness Anchored at berm and vented Empirical testing required to document compliance
68
Liner Systems Clay and Bentonite Soil Synthetic Clay Geomembrane
Asphalt/Concrete
69
Installation of Synthetic Liner
70
Boot Installation
71
Seam Testing
72
Water Balance Testing Seepage rate must be less than 500 gallons per acre per day
73
Lagoon Equipment Aeration Covers Baffles Proprietary
74
Aeration Equipment Floating Mechanical Submerged Diffusers
75
Covers Covers Conserve heat Control odors Prevent algae
76
Baffles
77
Proprietary Systems Parkson – BioLac EDI – ATLAS Lemna – BTP
Nelson Environmental EDI’s ATLAS Internal Clarifier
78
Berm Failure
79
Berm Failure
80
Berm Inspection
81
Floating Liner
82
Liner vent
83
Whale of a Liner
84
Thank You
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.