Progress and plans for HO Installation S. Dugad, K. Sudhakar Tata Institute of Fundamental Research India-CMS Meeting at BARC, 20-21 July 2005
2
Progress During March-2005 CMS week HO group was told about making cable layout plan Fabio (Muon Group) presented tentative layout plans in March-2005 CMS week. In April, HO team visited CERN for equipment training. During this visit, we presented new scheme for the same which was accepted and were asked to workout more details Since then, P. Verma, mechanical engineer from TIFR, started implementing this scheme. Mock-up of HO panel was made at TIFR to see the feasibility of the layout scheme.
3
Progress contd... After rigorous interaction with the Integration group in last 3 months, layout scheme is more or less accepted for Ring-2 in full detail. In view of the long delivery period of signal cables, it was important to finalize these lengths. After laying actual signal cables (by HO group during 12-15 July) on Ring-2 (Sector-6 & 8) as per the proposed layout design, actual lengths were compared with estimated lengths from ACAD design. After reasonable agreement between actual and estimated design length; the signal cable were finalized and order to be placed soon. HV and Signal Cables have different path HV Cable on Sector-2 laid up to HV patch panel. Actual length agrees with ACAD estimations.
4
R-Φ view of Ring-2
5
Signal Cable Laid
6
Some more ….
7
Readout Box (RBX) Calibration Length of calibration cables were re-evaluated by making a mock-up at TIFR. They were installed in RBX at CERN and certified to be OK Calibration cables made for RING+2 To be made for Ring +1, 0, -1, -2 Cables to be sent to CERN and start testing RBX boxes ~ Sep.-2005
8
Status of Ring-1 layout scheme Cables to be routed from readout side of Muon Detectors More complications! MAB problem for Ring ± 2 resolved completely, but it is more serious for Ring ±1 and not yet resolved Proposed layout scheme is a combination of Fabio/HO proposal Details being finalized
9
MAB Locations on YB1
10
3-D Model of the Overlap Region
11
Details of Overlap Region in Plan View
12
Installation of HO panels 4 (out of 12) HO panels in Ring+2 installed From 19 th July another 6 will be mounted on Ring+2 and 10 on Ring+1 Vertical sectors (1 & 7) will be mounted in UX5.
13
Proposed Action Plans Ring-0 layout scheme at preliminary stage Ring 1 layout and installation plans to be finalized at TIFR/CERN Source Run scheme to be finalized by Sep.2005 at TIFR For new layout scheme of cables we need to make 1000 clamps at TIFR (CERN?)
14
Proposed Action Plans Testing of RBX from Sep.2005 New DAQ to arrive in mid-august at CERN Making HV and LT Box for Ring ±2 at CERN Disconnect points for Ring ±1 at FNAL RBX/Tray Cable installation Oct.2005 for Ring+2 at CERN Light Leak/Calibration runs after installation in Oct.2005 at CERN Source Runs Nov.-2005