Fehr & Peers | December 13 th, 2011 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction.

Similar presentations


Presentation on theme: "Fehr & Peers | December 13 th, 2011 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction."— Presentation transcript:

1 Fehr & Peers | December 13 th, 2011 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction

2 Presentation Overview 1.Scope of Work 2.Data Collection and Existing Conditions Analysis 3.Guiding Principles for the Future Access Plan 4.Alternatives Considered 5.Current Plan 6.Discussion / Questions

3 Scope of Work 1.Data Collection and Field Observations 2.Existing Conditions Traffic Model Development/Validation 3.Development of Access/Circulation Alternatives 4.Analysis of Alternatives 5.District and City Review 6.Selection of Preferred Alternative 7.Construction Period Traffic and Parking Management Plan

4 Data Collection and Field Observations February 9, 2011 Counted autos, pedestrians, bicyclists, buses 7:00 – 9:00 AM, 2:15 – 4:00 PM Observed directionality, parking behavior, traffic queuing, jaywalking, and unsafe maneuvers AM Peak Hour Observations Traffic queues extend back to shopping center Unsafe pedestrian movements Poorly regulated traffic flows PM Peak Hour Observations Traffic jams on-site Traffic queues from north end to Ramona Unsafe pedestrian movements Poorly regulated traffic flows

5 Existing Observations

6

7 Development of Access/Circulation Alternatives Reduce congestion during peak periods Accommodate drop-offs and pick-ups on-site Accommodate more parking on-site Separate ingress and egress traffic flows Separate traffic flows to/from parking lot and to/from drop-off aisle Provide for safe, controlled pedestrian crossings on Pinole Valley Road Goals:

8 Alternatives Analysis All alternatives have a new signal at the northern parking lot driveway Alternative 1 : Traffic signal at School Exit/Estrella only Alternative 2 : Traffic signal at Shea/Granada only Alternative 3 : Traffic signal at School Exit/Estrella and Shea/Granada Alternative 4 : No traffic signal at School Exit, Shea/Granada as existing

9 Alternatives Analysis

10 Evaluation Matrix

11 Current Plan: Alternative 3