State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report Steve Myers Manager of System Operations.

Similar presentations


Presentation on theme: "State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report Steve Myers Manager of System Operations."— Presentation transcript:

1 State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report Steve Myers Manager of System Operations

2 State Estimator  Progress Total difference between generation & load reduced from 10’s of 1000’s at first to <500 MW Approximately 25 buses >50 MW mismatch 90% observability (75% with measurements)

3 Uses of the State Estimator  Identifying data problems  Identifying model problems  Monitoring of locations w/o SCADA (by System Operators)  Creating a case for Contingency Analysis Normally successful at least once per day

4 SE Plan  Continue to incrementally improve  Continue to reduce mismatches  With Engineer’s attention, use in Day-Ahead analysis  Train System Operators  Ultimately – SE will run CA in RT sequence

5 SE Plan  Needs Data Response from QSE’s and Private Networks Unit Status – QSE Private Network Issues to Correct Net Gen sent as one unit Loads not modeled Data required by ERCOT Operating Guides Section 8

6 Simultaneous Feasibility Test (SFT)  Calculates “Shift Factors” used in Congestion Management  Progress Attempted use in December '02 Bugs that had not shown up in test mode Waiting on fixes from vendor Once offline testing complete, will test again in production

7 SFT Plan  Use in Day-Ahead Initially peak hour Limited contingencies  Use in Hours Ahead Initially test mode Limited contingencies Limited iterations with SPD

8 Next Steps  Contingency Analysis will run in the Real- Time sequence and upon demand  SE and SFT will run for each BES deployment  ERCOT expects its systems to be ready By April 1

9 What Do We Gain?  More accurate analyses – closer to RT  Greatly improved pro-active CM  Much more accurate “Shift Factors”  Potentially less OOM deployments