Presentation is loading. Please wait.

Presentation is loading. Please wait.

EE/CS 481 Spring 1 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Project Merlin WOC 60 :Wind Output Converter to 60Hz Team Tammy.

Similar presentations


Presentation on theme: "EE/CS 481 Spring 1 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Project Merlin WOC 60 :Wind Output Converter to 60Hz Team Tammy."— Presentation transcript:

1 EE/CS 481 Spring 1 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Project Merlin WOC 60 :Wind Output Converter to 60Hz Team Tammy Okubo Will Acorda Meghan Tisdell Advisor Dr. Wayne Lu Industry Representative Ms. Swetha Varadharajan Intel

2 EE/CS 481 Spring 2 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Overview Introduction Scorecard Additional Accomplishments Plans Issues/Concerns Conclusions

3 EE/CS 481 Spring 3 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Introduction zoom in

4 EE/CS 481 Spring 4 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Scorecard Tasks Completed: Completed Design Review Measured and recorded output information from UPS Ordered parts Shortcoming(s): Complete circuit design and simulation Team Merlin was not able to complete circuit design, but will be finalizing the circuit and its components this week. This was due to the fact that emphasis was placed on completing some sort of simulation using PSPICE, B2Spice, etc. However, they have been advised by there advisor to start building and not worry about simulation at this point.

5 EE/CS 481 Spring 5 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Additional Accomplishments Stand built for AIR-X

6 EE/CS 481 Spring 6 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Plans Complete Theory of Operations 0.9 Finalize circuit design Construct and test the design (circuit) Build battery bank Receive all the parts ordered

7 EE/CS 481 Spring 7 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Milestones NumberDescriptionOriginalPreviousPresent 1Put together wind turbine11/14/07 1/22/08 2Order Parts12/14/07 1/28/08 3Complete Circuit Design11/30/07 2/8/08 4Parts Received01/14/08 2/8/08 5Begin Constructing Circuit2/1/08 2/8/08 6 Build battery bank and interface with wind turbine 11/23/07 2/17/08 7Theory of Operations 1.02/22/08 8Complete PIC program01/14/08 3/3/08 9Interface PIC and Circuitry02/14/08 3/3/08 10Complete Building02/28/08 3/10/08 11Test, Debug03/22/08 12Collect Output Data, Package03/30/08 13Prototype Release04/04/08 14Founder’s Day04/08/08 04/07/04 15Final Report 1.004/25/08

8 EE/CS 481 Spring 8 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Concerns/Issues Behind schedule Solution: Keep focused and commit the team to the deadlines specified. No other choice! Building without having done a complete simulation - Could not simulate using software such as PSPICE last semester and during Christmas Break. Advised to stop simulating and start the building process as simulation will take too much time. Solution: Extra safety/careful verifications of numbers/values

9 EE/CS 481 Spring 9 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Conclusions Design Review Approved AIR-X put together (Stand and device interfaced) Ordered Parts Plans: –Theory of Operations 0.9 –Finalize circuit design –Build battery bank –Construct and test design (circuit) –Receive all the parts ordered Many changes have occurred with ‘Milestones’ and therefore, no choice but to keep to those deadlines Any Questions?


Download ppt "EE/CS 481 Spring 1 EE/CS 4 2008 January, 2008 University of Portland School of Engineering Project Merlin WOC 60 :Wind Output Converter to 60Hz Team Tammy."

Similar presentations


Ads by Google