concerns related to water supply of wards 24 – 27 and 34
BRIEFING TO THE PORTFOLIO COMMITTEE ON WATER AND SANITATION on NOVEMBER 2015, PARLIAMENT, Room S12A concerns related to water supply of wards 24 – 27 and 34 Greater Tzaneen LM, Mopani District
2
Presentation outline Water Services – District Overview MOPANI
Provision of water supply to wards 24 – 27 and 34
3
Water Services – District Overview
MOPANI
4
Background The five wards falls under Ritavi II / Tours and Thabina Regional Water Schemes They get their water from 3 Water Treatment Works with a total capacity of 40Ml/day and currently producing 38Ml/day as well as 108 boreholes.
5
Water Resource Thabina Dam which is 41.2% full Tours Dam which is 53% full Groot Letaba River Ground Water augmentation
6
Current supply status Ward no. Population Names of Villages Water supply Current Intervention 24 14 752 Muhlava/ Sasekani/ Zangoma/ Petanenge Supplied from Nkowa Nkowa Water treatment works. The plant has the capacity to produce enough water for is area of supply Bulk water no longer reaches reservoirs due to illegal connections Areas with water interruptions are currently serviced by 9 water tankers 25 9 473 Mafarana Bourdeux Ntsako / Bonn Sedan Mulati 26 11 767 Tours / Masona Hoveni Rhulani Solani Nyanyukani Hweetsi / Sebela Supplied from Tours Water Treatment Works which has enough capacity for all the villages. Huge no of illegal connection
7
Current supply status Ward no. Population Names of Villages
Current status Current Intervention 27 22 472 Makhubidung Mokgapeng Shoromoni Ezekhaya / Shilubane Matshilapata Serotutung Hospitalview Mineview Senkwana Malekeke Supplied from Tours Water Treatment Works which has enough capacity for all the villages. Huge number of illegal connection Areas with water interruptions are currently serviced by 9 water tankers 34 18 900 Khopo Lephepane Thabina (Mogoboya) Rasebalane Topanama Supplied from Thabina Water Treatment Works Huge number of illegal connections
8
District profile Municipality Population Wards Current No. Villages
Current No. Urban Areas GGM 30 93 1 GLM 29 80 3 GTM 34 125 5 BPM 18 23 4 MLM 94 857 14 33 MDM TOTAL 354 16
9
Mopani District Municipality depends largely on the Letaba, and the Olifant River systems as well as ground water augmentation The Letaba catchment is over stressed. There are five large dams, namely, Ebenezer, Tzaneen, Magoebaskloof, Nsami, Middle letaba which supply water across municipalities in Mopani.
10
Mopani DM has nine Regional Water Schemes with 24 Water Treatment Works (WTW) with a total design of Ml/d and currently producing 202, 08 Ml/d. Out of 24 WTW, 23 are operational and 1 not operational namely Metz Package Plant – Alternative supply from mountain spring
11
BULK WATER PROVISION # PLANT Municipality MEGALIT ER CLASS
Population Supplied Capacity 1 GIYANI WATER WORKS Greater Giyani 36.7 B Adequate 2 MIDDLE LETABA WATER WORKS 36 39 638 Insufficient 3 MUYEXE WATER WORKS 1.08 D 3 228 4 ZAVA WATER WORKS 0.3 4 821 5 MAPUVE WATER WORKS C 15 196 6 TZANEEN WATER WORKS Greater Tzaneen 14 571 7 LETSITELE WATER WORKS 1.8 406 8 NKAMBAKO WATER WORKS 12 99 152 9 SEMARELA WATER WORKS E Part of Thapane 10 THABINA WATER WORKS 75 384 Reached the capacity of both the plant and the dam 11 GEORGE VALLEY WATER WORKS 423
12
BULK WATER PROVISION # PLANT Municipality MEGALIT ER CLA SS Population
Deficit 12 THAPANE WATER WORKS Greater Tzaneen 4.5 C Insufficient 13 TOURS WATER WORKS 4 52 216 Being upgraded 14 NKOWANKOWA WATER WORKS 24 99 676 15 MODJADJI WATER WORKS Greater Letaba 71 519 16 POLITSI WATER WORKS 5.5 11 994 To be upgraded in the current financial year 17 KURATA WATER WORKS - 1 664 18 PHALABORWA WATER WORKS Ba- Phalaborwa 76 B Adequate 19 NONDWENI WATER WORKS 4.7 D 21 581 20 THE OAKS WATER WORKS Maruleng 1 19 304 21 Mametja/Sekororo Water Works 15 C 94 857 Under construction
13
HOT SPOTS Municipality Community Challenge Intervention Required
Progress to date Greater Tzaneen Relela Insufficient water from Thapane Water Works Upgrading of the water treatment plant; TR submitted to DWS for additional abstraction Illegal connections along the bulk pipelines Replacement of the existing PVC pipe with steel pipe; Lack of reticulation infrastructure at village extensions Provision of internal water reticulation Awaiting the approval of the MWIG BP Petanenge, Muhlava, Sasekani, Co-Op Insufficient water from Nkowankowa Water Works Review allocated quota and upgrade Uprooting of the illegal connection along the bulk pipeline Municipality team is on site for the uprooting of the illegal connections Vandalised booster pump station Repair of booster pump stations Contractor appointed Awaiting the approval of the MWIG BP (Sasekani &Zangoma)
14
HOT SPOTS Municipality Community Challenge Intervention Required
Progress to date Greater Tzaneen Tickyline Insufficient internal water reticulation infrastructure Extend reticulation to cover extension Technical report finalised and is being assessed. Greater Letaba Hlohlokwe, Taulome and Mamanyowa Insufficient bulk water supply Extension of the Nkambako bulk pipeline Designs are complete. This is part of DWS Phase 2 Intervention project Four boreholes have been drilled, tested and equipped and there is supply of water Kgapane Extension of Politsi WTW by LNW Licence for additional water has been granted to LNW. Designs for extension for the plant are complete. Contract advertised. Utilization of ground water LNW is exploring a possibility of augmenting the system with ground water
15
Major projects under implementation
MAMETJA SEKORORO RWS – CONSTRUCTION OF 15ML WATER TREATMENT WORKS AT THE OAKS UPGRADING OF WATER RETICULATION IN MARULENG HOEDSPRUIT BULK WATER SUPPLY KAMPERSRUS BULK WATER SUPPLY KAMPERSRUS SEWAGE PLANT THABINA WATER PROJECT LEPHEPANE WATER PROJECT TOURS WTW UPGRADING OF WATER RETICULATION IN BPM
16
Provision of water supply to wards 24 – 27 and 34
Greater Tzaneen Local Municipality
17
STATUS OF WATER SUPPLY: BULK WATER: WARD 24
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Muhlava Headkraal 1 768 Nkowankowa Damaged pipeline during road construction Contractor to reinstate the pipeline 30 November 2015 No progress Sasekani 5 616 Partially receiving water due to illegal connection and the reticulation is vandalized Removal of illegal connections along the bulk pipeline Booster pump station repaired. Contractor busy reinstating the rising main. Petanenge 5 228 No bulk supply. Eskom to replace the stolen cable Power supply cable stolen on Thursday, 29 October 2015 immediately after replaced. Zangoma 2 202 No bulk supply as it is dependent on Petanenge booster pump station
18
STATUS OF WATER SUPPLY: BOREHOLES: WARD 24
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Muhlava Headkraal 5 2 Transformer, motor and cables stolen and power supply Refurbishment of the borehole and application for electricity connection Application has been made with Eskom and replacement of stolen equipment has been reported 1 Outlet pipe broken Replacement of the pipe 6 Nov Maintenance team is on site Sasekani Vandalized immediately after completion Refurbishment of the borehole Reported to Eskom for the replacement of the stolen cables. Petanenge 9 Motor stolen Replacement of the motor 15 Nov Procurement for a contractor is underway Collapsed Re-drilling 30 Nov
19
STATUS OF WATER SUPPLY: BOREHOLES: WARD 24
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Petanenge 5 2 Motor stolen Replacement of the motor 15 Nov Procurement for a contractor is underway 1 Collapsed Re-drilling 30 Nov Mechanical fault Loose drive shafts/rods 7 Nov Receiving attention from internal maintenance team Zangoma 4 Diesel engine stolen Replacement of engine 14 Nov
20
STATUS OF WATER SUPPLY: BULK WATER: WARD 25
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Bonn 3 542 Nkowankowa Booster pump station at Coop is totally vandalized. Illegal between Co-op and Gabaza Refurbishment of the booster pump station Dependent on the availability of water at Co-op reservoir Removal of illegal connections between Dan and Sasekani Mafarana 2 808 AC Pipeline via Mafarana to Bonn damaged during road construction Contractor to be appointed to reinstate the pipeline as part of disruption of existing services December 2015 Procurement of a service provider is underway Mulati 2 830 Booster pump station at Sedan vandalized
21
STATUS OF WATER SUPPLY: BULK WATER: WARD 25
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Ntsako 1 166 Nkowankowa Booster pump station at Coop is totally vandalized. Illegal between Co-op and Gabaza Refurbishment of the booster pump station Dependent on the availability of water at Co-op reservoir Removal of illegal connections between Dan and Sasekani Sedan 2 041
22
STATUS OF WATER SUPPLY: BOREHOLES: WARD 25
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Bonn 13 2 4 Motor, panel and/or cables stolen Replacement of stolen equipment 14 Nov Procurement for a contractor is underway 3 Dry and or collapsed Drilling of new borehole Included in the 2015/16 approved MWIG BP 1 Mechanical fault Repairing of diesel engine and reconstruction of concrete slab Contractor on site as it is still under Defects Liability Period Repairing and/or replacement of broken equipment Procurement of spares is underway. Mafarana 8 Replacement of engine Contractor on site as it they are still under Defects Liability Period Vandalized or dry Refurbishment
23
STATUS OF WATER SUPPLY: BOREHOLES: WARD 25
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Mafarana 1 Mechanical fault Repairing or replacement of broken equipment 7 Nov Receiving attention from the maintenance team Mulati 11 4 Replacement of engine 14 Nov Contractor on site as it is still under Defects Liability Period 2 Vandalized Refurbishment Receiving attention from the internal maintenance team No power supply Application for electricity connection Awaiting for a quotation from Eskom Ntsako Motor and cables stolen Replacement of stolen equipment Procurement underway Collapsed Re-drilling of borehole 18 Dec Procurement of a contractor is underway
24
STATUS OF WATER SUPPLY: BOREHOLES: WARD 25
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Sedan 3 1 Diesel engine stolen Replacement of engine 18 Dec Procurement of a contractor is underway Collapsed Re-drilling of borehole
25
STATUS OF WATER SUPPLY: BULK WATER: WARD 26
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Bourdeaux 217 Tours The stand pipes are vandalised and the existing infrastructure has not been working for some time Refurbishment of the infrastructure an extension of the reticulation network.. Implementation is dependent on the approval of the technical report Technical reports completed and being assessed by DWS to access MIG funds and the plant is being upgraded Hoveni 1 564 As above Hweetji 1 716
26
STATUS OF WATER SUPPLY: BULK WATER: WARD 26
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Masoma 4 192 Tours The stand pipes are vandalised and the existing infrastructure has not been working for some time Refurbishment of the infrastructure an extension of the reticulation network. Implementation is dependent on the approval of the technical report Technical reports completed and being assessed by DWS to access MIG funds. The plant is being upgraded Nyanyukani 885 Part of the village is getting water from the illegal connection on the rising main Refurbishment of the infrastructure an extension of the reticulation network.. As above Rhulani 3 052
27
STATUS OF WATER SUPPLY: BULK WATER: WARD 26
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Solani 510 Tours The stand pipes are vandalised and the existing infrastructure has not been working for some time Refurbishment of the infrastructure an extension of the reticulation network. Implementation is dependent on the approval of the technical report Technical reports completed and being assessed by DWS to access MIG funds. The plant is being upgraded
28
STATUS OF WATER SUPPLY: BOREHOLES: WARD 26
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Bourdeaux 4 Not applicable N/A Hoveni 3 2 1 Broken pipes Replacement and or repairing of the pipes 14 Nov Receiving attention from the internal maintenance team Hweetji Sabela Nyanyukani Vandalized Replacement of stolen transformer and refurbishment of borehole 18 Dec Reported to Eskom for the replacement of the transformer and that procurement are underway for the re-equipping of the borehole Rhulani Refurbishment of the borehole Procurement is underway for the appointment of a contractor
29
STATUS OF WATER SUPPLY: BOREHOLES: WARD 26
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Solani 3 1 2 Vandalized and diesel engine stolen Replacement of diesel engine and refurbishment of boreholes N/A Procurement is underway for the appointment of a contractor Tours Not applicable
30
STATUS OF WATER SUPPLY: BULK WATER: WARD 27
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Makhubidung 6 020 Tours Part of the village is getting water from the illegal connection on the rising main Refurbishment of the infrastructure an extension of the reticulation network. Implementation is dependent on the approval of the technical report Technical reports completed and being assessed by DWS to access MIG funds. The plant is being upgraded Mogapeng 10 278 They get water daily from the illegal connections that are made on the rising main As above
31
STATUS OF WATER SUPPLY: BULK WATER: WARD 27
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Pharare 7 978 Tours Part of the village is getting water from the illegal connection on the rising main Refurbishment of the infrastructure and extension of the reticulation network Implementation is dependent on the approval of the technical report Technical reports completed and being assessed by DWS to access MIG funds. The plant is being upgraded Shiluvane 15 861 As above
32
STATUS OF WATER SUPPLY: BULK WATER: WARD 27
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Lephephane 1 226 Thabina The booster pump station has been discontinued and there is no bulk water in those villages they depend on mountain water stream which was community driven and upgraded by CSIR Completion of the booster pump station and the damaged bulk pipeline March 2016 Assessment report concluded.
33
STATUS OF WATER SUPPLY: BOREHOLES: WARD 27
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Makhubidung 4 2 1 Vandalized Refurbishment of borehole 18 Dec Procurement is underway for the re-equipping of the borehole Collapsed Fishing of pipes and rods 30 Nov Mineview Not applicable N/A Mogapeng 3 No power source Application for electricity connection Application done. Awaiting for quotation from Eskom Pharare Vandalized and or motor and cable stolen Refurbishment of boreholes
34
STATUS OF WATER SUPPLY: BOREHOLES: WARD 27
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Shiluvane 7 2 3 Collapsed Re-drilling 18 Dec Procurement is underway for the re-equipping of the borehole
35
STATUS OF WATER SUPPLY: BULK WATER: WARD 34
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Maake 3 371 Thabina Loss of water along the bulk pipeline through illegal Replacement and upgrading of the bulk pipe End of Feb 2016 A diversion pipeline is being constructed Bokgaga 5 236 Mphame 3 269 Mogoboya 4 398 Rasebalane 1 226
36
STATUS OF WATER SUPPLY: BULK WATER: WARD 34
Community Name Population Water Supply Scheme Challenge Planned Intervention Timeframe Progress Serare 1 489 Thabina Loss of water along the bulk pipeline through illegal Replacement and upgrading of the bulk pipe End of February 2016 Rehabilitation of the bulk pipeline is underway Topanama 846
37
STATUS OF WATER SUPPLY: BOREHOLES: WARD 34
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Lephephane Co-op 3 1 Vandalized Refurbishment 14 Nov Contractor on site No Power source Application for electricity connection 30 Nov Application done. Awaiting for quotation from Eskom Bokgaga 2 Mechanical fault Replacement of a pumping unit (element) 15 Nov Procurement is underway for supply and delivery of the required element. Maake Headkraal No power source Transformer and cable stolen Replacement of transformer and cable Reported to Eskom Mogoboya Refurbishment of boreholes Procurement is underway for the re-equipping of the borehole
38
STATUS OF WATER SUPPLY: BOREHOLES: WARD 34
Community Name No. of Boreholes Operational Non Operational Challenge Planned Intervention Timeframe Progress Rasebalane 2 1 Damaged electrical cable Replacement of the damaged cable 7 Nov Receiving attention from the internal maintenance team Serare 3 Not applicable N/A
39
CHALLENGES Illegal Connections;
The Bulk pipe lines, on the entire Bulk Water Schemes, have a lot of leakages caused by illegal connections. The connections are done by communities on pipe lines from water treatment works to various reservoirs. The extent of the illegal connections has resulted in high water losses on bulk pipelines and thus water does not reach existing reservoirs and the sections of distribution network.
40
CHALLENGES Supply System Below Standard
Most villages within the scheme have water supply systems which are below the minimum standard, There is no proper reticulation. Some people walk for long distances to fetch water Thabina Water Treatment works is drawing more water than the dam can supply Poor state of repair of the water system; The existing Bulk pipe lines are currently perforated with illegal connections. Most pipelines were built pre 1994 using Asbestos Cement (AC) pipes. This type of pipes contributes to water losses since they are prone to cracks and (Solid) settlements.
41
CHALLENGES Increase in water demand
The design of most of infrastructures within the scheme was based on the demand of 25l/c/d, which has been beyond doubt proven to be an unrealistic figure. The consumption pattern has significantly changed since most of the communities have illegally connected water into their yards. This automatically rises to yard connection category with consumption between l/c/d. Furthermore, the villages within the scheme have grown in population resulting in increased water demand.
42
Challenges and interventions
Vandalism and theft of water services infrastructure. Public awareness on By-Laws and enforcement Water allocations The review of the allocated quota to allow upgrades Illegal connections that renders water supply schemes inefficient. Extension of water reticulation network and uproot/remove illegal connections Ageing water infrastructure Source more funds to replace it, e.g asbestos pipes Demand higher than the supply capacity Upgrading of the water infrastructure Ageing infrastructure resulting into high frequency in services interruption Develop replacement program and source funding Physical condition of the water services infrastructure (WWTP) Refurbish and rehabilitate both water and waste water plants
43
Thank You