Presentation is loading. Please wait.

Cobb County Department of Transportation

Similar presentations


Presentation on theme: "Cobb County Department of Transportation"— Presentation transcript:

1 Cobb County Department of Transportation
Regional Transportation Management Center

2 Genesis Joe Fletcher, Traffic Signal Systems Manager, identified a need to build a facility to serve the County’s current and future transportation management functions. This vision was pursued by combining different funding sources. Provide a dedicated resource to replace the existing one-room facility to serve the County’s transportation needs for the next 20 years

3 Existing Cobb TMC

4 Functions of TMC Signal Operations Management Camera Surveillance
Information Sharing Traffic Data Collection Incident Management Alternate Emergency Management Site

5 Facility Concept Modeled after TDOT Facility in Nashville
Site Visits and Discussion

6 TDOT Nashville

7 Design Consultant Selection
Good Proposals from Two Firms Gresham Smith and Partners URS

8 Early Coordination / Input
Met with Agency Reps Fire Public Safety 911 Cobb Emergency Management Center (EMC) Property Management GRTA GDOT FHWA Others

9 Concept Design On Site of Existing Outdated Building
24,000 S.F., 3 Story Facility Basement – Field Operations/Incident Management First Floor – Operations Room Including 9 Consoles and Support Staff Second Floor – Support Staff

10 Concept Development Visited Several TMC’s in the Metro Area:
Gwinnett County City of Atlanta GDOT TMC

11 Existing Facility

12 Proposed Facility

13 Leadership in Energy and Environmental Design (LEED)
Decision made by Chairman to Pursue LEED Certification Silver Certification Targeted Construction Waste Diversion Recycled Materials No Irrigation/Low Maintenance Landscaping Reduction in Water Use Waterless Urinals Low-Flow Fixtures ETC.

14 Design Process Design Contract Executed Dec., 2006
Design Finalized Feb., 2009

15 Cost Estimates Consultant Estimates - $6 Mill.+
Independent Contractor Cost Estimate – $6 Mill.+

16 Contractor Selection Process
Construction Management at Risk Desirable But Not Allowed Under Current Laws Governing GDOT Traditional Low Bid 8 Submitted Bids Low Bid - $4.4 Mil. – Hogan Construction

17 Schedule Demolition Started on June 15, 2009
Completion Slated for April of 2010 Building Occupation May 2010