T-76.4115 Sprint Demo Team Tarantino Iteration 1 / Sprint 2 12.12.2006.

Similar presentations


Presentation on theme: "T-76.4115 Sprint Demo Team Tarantino Iteration 1 / Sprint 2 12.12.2006."— Presentation transcript:

1 T-76.4115 Sprint Demo Team Tarantino Iteration 1 / Sprint 2 12.12.2006

2 T-76.4115 Iteration demo 2 Agenda  Project status (10 min)  Achieving the goals of the sprint  Project metrics  Realized risks  Work results (15 min)  MUPE status  Wiki status  Used work practices (5 min)

3 Introduction

4 T-76.4115 Iteration demo 4 Introduction to the project  Quentin primary goal is to agilize movie’s production stages.  It is a modern tools for collaboration.  Amount of information that is gathered during pre-production is huge  During production coherent information is vital since shots can be filmed in middle of nowhere. A simple misunderstanding can become very expensive!  Crew can get more tailored information

5 T-76.4115 Iteration demo 5 Project plan: Development process  Iterative process  Two development iterations, each divided into two sprints  Sprint contents  Planning phase, overlaps with the previous sprint  Development phase, features for this sprint are frozen  Integration phase, the implemented features are verified  Sprint planning  Features to be included are agreed with the customer at the start of the sprint  Kick-off meetings with the whole team at the beginning of each sprint  Reflection workshop at the end of each sprint, process improvement Project Planning Iteration 1Iteration 2 Holiday Sprint 1Sprint 2 Sprint 4Sprint 3 Colors: Planning Defeloping features Integrating features S1 S2 S3 S4 S3 S2

6 Project status

7 T-76.4115 Iteration demo 7 Status of the S1s deliverables  The first version of the MUPE reader  OK, still some problems when using with real device  The first version of the modified Wiki  OK, some minor bugs to be fixed  Updated version of project plan and requirement document  Not OK, formal versions of project plan and requirement document will be produced only at the end of S2  QA Plan  OK  Progress report  OK  Test reports  OK

8 T-76.4115 Iteration demo 8 Status of the S2’s deliverables  The first version of the MUPE-io  OK  The second version of the modified Wiki  Quite OK: Bold goals for S2 not fully realized, but technically challenging core functionality in place.  Updated version of project plan and requirement document  OK  QA Plan  OK  Progress report  OK  SEPA diaries  OK?  Test reports  OK

9 T-76.4115 Iteration demo 9 Realization of tasks (S1)

10 T-76.4115 Iteration demo 10 Realization of tasks (S2)

11 T-76.4115 Iteration demo 11 Resource usage  Project is on its track but under its budget  Lower than expected resource usage in the S1 & S2 will give us more slack for the rest of the project  The challenge is to use this slack: => Holidays can be utilized. Original plan (in the beginning of the iteration) Realization and updated plan (realized hours and updates) 631112106,581779885,571 I2 21433473545,51516,521,5 S2 1330190 Total 202,5211634 36,527 S1 3702420,539,533,54351,571 PP SUMRBTPLKJHTHTNJM 5609699,573,581,57773,559 I2 285485443413629,533 S2 1330190 Total 202,5211634 36,527 S1 3702420,539,533,54351,571 PP SUMRBTPLKJHTHTNJM

12 T-76.4115 Iteration demo 12 Quality dashboard  Documentation extensively reviewed and updated  Wiki: Use cases selected for implementation have been tested, some minor defects open  MUPE: Explorative testing performed, usability not yet sufficient  Code reviews behind schedule, customer comments needed Legend Confidence: 3 = tested well 2 = tested 1 = looked at, but uncertain 0 = not tested at all Quality: 3 = quality is good 2 = quality is mediocre 1 = quality is bad

13 T-76.4115 Iteration demo 13 Quality Metrics 1/2  Defect status:  Most defects logged are minor cosmetic defects or usability notes  No critical defects logged, testing during development sufficient  High severity TR029_MUPE: Old MUPE login does not work after server restart, almost showstopper, but has a workaround

14 T-76.4115 Iteration demo 14 Quality Metrics 2/2  Codebase size in LOCC (revision 304):  Other metrics and practices:  Statistical metrics for the Generic Wikireader for MUPE: http://b123.myrootshell.com/~tinurmin/s2_complexity/ http://b123.myrootshell.com/~tinurmin/s2_complexity/  Heuristic evaluation of usability for Wiki and MUPE brought many improvement suggestions  Explorative testing and extensive testing during development

15 T-76.4115 Iteration demo 15 Realized Risks  RI003: A team member may lack the skills needed in the project.  Effect: A developer had challenges in getting started with his work. (S1, severity: High)  Effect: A bottleneck task was almoust complete for several days during. (S2, severity: High)  RI004: Communication between group members might be insufficient.  Effect: PM was unaware of problems that one developer had. (S1, severity: Medium)  RI007: Project servers might be down for a while.  Effect: Wiki was not in use for a while. (S1, severity: Low)  RI009: There might be problems with communication channels.  Effect: See above.  RI013: Sprint time schedule might be unrealistic.  Effect: Some tasks were clearly late and the development had to be continued parallel during the testing. (S2, severity: High  RI014: Bottlenect tasks might hinder the project progress.  Effect: See RI003  RI019: Making modifications to Wiki might be unexpectedly challenging  S1 & S2 came a bit short of what was planned.

16 Work results

17 T-76.4115 Iteration demo 17 Wiki status  Implemented:  Data structure has been designed  The most technically challenging functionality has been implemented  Many kinds of special pages  Commenting functionality  Shot scheduler  Drag-drop sorting  Basic call-sheet functionality  To be implemented:  Call sheet to be finalized  Version history  GUI and navigational structure to be finalized based on customer comments  Lots of work in here!

18 T-76.4115 Iteration demo 18 MUPE status  Implemented:  Transfer WikiText to MUPE  Working links  Dividing article to subpages  Upload: Commenting functionality & photo sending  To be implemented:  MUPE-parser: Usability & Heuristics  Authentication?

19 Used work practices

20 T-76.4115 Iteration demo 20 Most important work practices  Time reporting (Excel-sheets)  Status reporting:  Backlog used as a part of status reporting => wasn’t of much use, since S1 there was no budget pressure  Communication  Few face-to-face meetings used in S1, Many Skype meetings in S2  Challenges in communication during S1 => Regular Skype meetings solved this problem in S2.  Documenting  All the documents in team Wiki, has functioned well  Document version control in Wiki  Early victory  "Easy thing first, the most business critical second" turned more into "Easy thing first, the hardest second”, but was nevertheless a useful approach  Process improvement  What did we learn?  Which methods were worth using and which were not?  What problems did we have?  Whas the problem caused by us or some other stakeholder?  What can we do better?  Which methods should be try using in the next sprint?

21 S3 Goals

22 T-76.4115 Iteration demo 22 S3 Goals (to be discussed with the customer)  Finalizing the functionality currently under work in Wiki + new requirements received from the customer  Enhance the usability of both MUPE and Wiki GUI so that the first ”production” version of the software would be ready at the end on S3  Continue SEPA work

23 Thanks for your interest! Questions?


Download ppt "T-76.4115 Sprint Demo Team Tarantino Iteration 1 / Sprint 2 12.12.2006."