Presentation is loading. Please wait.

Presentation is loading. Please wait.

Lecture 19 GIS Project Design and Management + Case Studies

Similar presentations


Presentation on theme: "Lecture 19 GIS Project Design and Management + Case Studies"— Presentation transcript:

1 Lecture 19 GIS Project Design and Management + Case Studies

2 Management Responsibilities
Planning Design Strategy Staffing Standardize Interoperability Reuse Document Assume personnel loss and turnover Write formal documents

3 Ten step GIS Planning Methodology Tomlinson, Thinking About GIS
Consider the strategic purpose Plan for the planning Conduct a technology seminar Describe the information products Define the system scope Create a data design Choose a logical model Determine system requirements Benefit-cost, migration and risk analysis Make an implementation plan Needs Assessment Concept. Design Physical Design Implementation

4 Implementation Process!
Analysis of Requirements Specification of Requirements Evaluation of Alternatives Implementation of System 1.Definition of Objectives 2. User Requirements 3. Preliminary Design 4. Cost-Benefit Analysis 5. Pilot Study 6. Final Design 8. Shortlisting 9. Benchmark Testing 10. Cost- Effectiveness Evaluation 11. Implementation Plan 12. Contract 13. Acceptance Testing 7. Request for Proposal (RFP) 14. Implementation A Fourteen Step Implementation Process! (assumes external acquisition) Source: Longley, et. al. p. 391

5 Project Management Tools
WBS (Work Breakdown Structure) chart GANNT Charts PERT (Program Evaluation and Review Technique) SWOT analysis RISK Management Plan Gantt Charts (Gant Charts) are useful tools for analyzing and planning more complex projects. They: Help you to plan out the tasks that need to be completed Give you a basis for scheduling when these tasks will be carried out Allow you to plan the allocation of resources needed to complete the project, and Help you to work out the critical path for a project where you must complete it by a particular date. When a project is under way, Gantt Charts help you to monitor whether the project is on schedule. If it is not, it allows you to pinpoint the remedial action necessary to put it back on schedule.

6 WBS Chart

7 GANNT Chart Step 1. List all activities in the plan
Step 2. Set up your Gantt Chart Step 3. Plot the tasks onto the graph paper

8 Program Evaluation and Review Technique
PERT Chart Program Evaluation and Review Technique

9 SWOT Analysis

10 Risk Management Plan Identify the risks Rate the risks
Establish triggers for problems Identify mitigating actions Identify the owner of the risk

11 Which level of GIS? Project
Single department application (Departmental GIS) Multi departmental application Enterprise system (Enterprise GIS) Multi Organizational endeavor (Community GIS)

12 Level I: Project Organizational Environment
Expected result is a product, e.g a map or report Project has an end date and finite project No long-term support expected & no commitment to ongoing GIS Little organizational impact GIS Implementation Approach One-time effort Need best tool for the job Consultant or contractor may do entire thing

13 Level II: Single Department
Organizational Environment Small Organization or Single Department Well-defined, existing business function to be supported Ongoing support is required but no commitment to GIS Little or no reorganization e.g. manual drafters shift to GIS workstation Managed by departmental responsible for business activity GIS Implementation Approach PC or standalone workstation maybe CAD focused Little or no integration with attribute databases Little sharing of information within or beyond department

14 Level III: Multi-Department
Organizational Environment Mid-size to large organization, more than one department More significant commitment of staff and budget to GIS Ongoing support and update strategies Some organizational implications (“Champion”) Managed by cooperating departments GIS Implementation Multiple, networked PCs/workstations Topological GIS Object/Relational database Some information sharing between departments

15 Level IV: Enterprise System
Organizational Environment Usually medium to large organization, multiple departments High level long-term commitment to GIS Organization-level strategic planning, distributed implementation and maintenance Incorporation of GIS as part of organizational infrastructure Corporate management support and involvement is essential GIS Implementation Distributed client-server network(s) Integration of multiple GIS, database, and related technologies Multi-department data sharing, standards and metadata

16 Level V: Multi-Organizational
Organizational Environment Public organizations or industry alliance Multi-participant organizational structure for planning and policy Distributed maintenance responsibilities across organizations Long-term, high level commitments among participating organizations Significant reorganization of functions across organizations GIS Implementation Distributed maintenance of shared elements Data exchange facility and standards and metadata, Internet or other WAN Data integration from multiple technologies

17 GIS Development Cycle First decides what the GIS should do, second decide how the GIS will accomplish each task. Needs Assessment Conceptual Design Database Planning and Design Database Construction Available Data Survey GIS Use and Database Maintenance GIS System Integration Application Development Pilot / Benchmark Acquisition of GIS HW and SW HW and SW Survey

18 1. Needs Assessment Interviews, focus groups can capture the needs of a dept (managers, users, customers) Compiling the results of the needs assessment Master data list Master function list Budget constraints Assess available systems Select the system

19 2. Design and Choose a Data Model
The conceptual data model is a high level view, independent of the computer system. Identify the elements of the data model and their relationship to one another (flowchart) Create a list of actions the system must perform. Identify system inputs and outputs. Group actions, inputs and outputs into a logical order,

20

21 2. Design and Choose a Data Model
The physical data model describes the organization of the data in the computer. Choose a physical model that is closest to the aspects of the real world which you wish to model. May be straight forward – vector for road network. Not so straight forward – TIN or DEM for terrain analysis

22 3. Designing the Analysis
Cartographic Modeling Identify the map layers or spatial data required. Use natural language to explain the processes involved. Draw a flow chart of step 2. Annotate the flow chart with commands necessary to perform the operations within the GIS.

23 Cartographic modeling
23

24 Cartographic models Often represented with flowcharts; graphically representing the spatial data, operations and their sequence 24

25 Stages in Developing an Application
The waterfall approach – a linear approach to the management , development and implementation of a system. The prototyping approach Pilot project

26 Waterfall Approach Methodology Problems with the approach.
Feasibility study System investigation and system analysis System design Implementation review and maintenance Problems with the approach. Often misses the problem context for the group for whom it is being developed. Limits flexibility for change in the scope and timeline of the project. Does not put the user at the center of the design. Considered to be technocratic view of system development. It provides a structured framework for the management of a GIS project.

27 Prototyping Figure The prototyping approach

28 Advantages of Prototyping
Users have more direct involvement in the design of the system. It is easier to adapt the system in the face of changing circumstances. It can be easily abandoned if it fails to meet users needs. If time and money are available a number of prototypes can be built.

29 Problems of Prototyping
Can be difficult to manage Large number of users Differing opinions Resource implications may change after development of the prototype. Knowing when to stop development can be a problem. It is never finished

30 Pilot Projects As a demonstration, to show potential users the possible utility of GIS As an experiment to test a particular technical aspect of implementation As a temporary operation or production environment to assess operational feasibility or to determine organizational impact As a trail run to test adequacy of project planing and design As a benchmark test to compare hardware, software, network configurations being considered

31 GIS Implementation issues
GIS Paradigm Use of spatial location as integrating framework for information Power of spatial analysis Geographic Data Management Principles Extend data management principles to include geography Builds on standard IT practice Technology Select appropriate GIS-enabling technology and plan to evolve Follow and exploit new technologies Organizational Setting Organizational setting a crucial ingredient to success/failure Level and nature of enterprise

32 Implementation Problems
Data in the wrong format for the software. A lack of GIS knowledge imposing technical and conceptual constraints on the project. Users frequently changing their mind about what they want.

33 4. Project Evaluation Test and evaluate the output
Difficult if the output is being used to make predictions, Tests to see if the GIS meets its goals Are people using the application for which it was designed? Check the output against reality. Evaluate the changes that had to be made through the development stages from rich picture to implementation.

34 Case Study 1 Exploring Response Times
Which areas are within a four-minute drive time of a fire station in a particular city.

35 A Street Map with City Boundary

36 Step 1 Find areas within a four-minute drive time of a fire station during both light and heavy traffic conditions. In ArcGIS for Desktop you use the Network Analyst service area solver to create drive-time areas. You will need to have the Network Analyst extension installed, and a street network dataset that contains traffic information. First, add the Network analyst toolbar and create a New Service Area.

37

38 Right-click Service Area in the table of contents and select Properties.
On the Analysis Settings tab, set the drive time (Default Breaks) to 4 minutes and specify the day of week (Tuesday) and time of day (2:00 am).

39

40 Click Solve on the Network Analyst toolbar to calculate and display the drive-time areas.

41 To save the drive-time polygons, export them and add them to your map when prompted.

42 Area within a four-minute drive time from a fire station during light traffic conditions (2:00 a.m. on a Tuesday morning)

43 Step 2 To find areas within four minutes of a fire station on a typical Friday afternoon at 5:00 p.m., open the Service Area layer properties dialog box again, and on the Analysis Settings tab, change the Time of Day and Day of Week settings to 5 PM on Friday. Then click the Solve button on the Network Analyst toolbar, and export the resulting drive-time polygons, as before.

44

45 Area within a four-minute drive time from a fire station during heavy traffic conditions (5:00 p.m. on a Friday afternoon)

46 Step 3 Find out how many minutes from a fire station the farthest parts of the city are. To find areas within 6, 8, 10, and 12 minutes of a fire station on a typical Friday afternoon at 5:00 p.m., open the Service Area layer properties dialog box, and on the Analysis Settings tab, change the Default Breaks to 6, 8, 10, and 12 minutes. Once again click the Solve button on the Network Analyst toolbar, and export the resulting drive-time polygons.

47

48 Areas within 6, 8, 10, or 12 minutes of a fire station
Areas within 6, 8, 10, or 12 minutes of a fire station. Most of the populated part of the city is within 6 or 8 minutes.

49 Case 2 Are there any places in the city to build a mixed-use development?

50 Introduction With the success of several medium-sized mixed-use developments that have been built in the city over the past decade, a real estate analyst for a local development company has been keeping an eye on the market. The company wants to build several small mixed-use developments with a restaurant or shops at street level and three or four floors of housing or office space above. The analyst is particularly interested in locations of existing gas stations as potential sites. With fewer people driving, especially in urban centers, and improved fuel mileage in cars, profit margins for station owners are getting thinner and thinner. Many are realizing they can make more money by selling the land to developers.

51 Using information on the location of light rail stops, selected businesses, and the regional plan, theanalyst will attempt to identify areas that might be good candidates for small mixed-use development projects.

52 Find areas within a quarter-mile of a store or restaurant, light rail stop, or planned commercial district.

53 Step 1 Use the Buffer tool to create a quarter-mile buffer around the light rail stops.

54 Step 2 Use Select By Attributes with businesses to select restaurants and bars, clothing stores, and home furnishings stores. These correspond to Department of Labor SIC2 codes 56, 57, and 58.

55

56 Step 3 Use the Buffer tool to create a quarter-mile buffer around the selected businesses.

57 Steps 4 & 5 Use Select By Attributes with the regional plan layer to select neighborhood commercial districts. These correspond to the CC and CN regional plan codes. Use the Buffer tool to create a quarter-mile buffer around the commercial districts.

58

59 The buffer layers for light rail stops, shops and restaurants, and planned commercial districts are displayed together.

60 Potential development areas are displayed with the locations of gas stations.

61 Step 6 Use the Union tool to combine the light rail stop buffer layer and the shop and restaurant buffer layer. Union allows you to combine several layers at one time.

62

63 Step 7 Then use Dissolve to erase the residual buffer boundaries.

64 Step 8 Display the layer of potential development areas with locations of gas stations.

65 The three buffer layers have been combined using Union to create the layer of potential development areas.

66 Display the layer of potential development areas with locations of gas stations.

67 Steps 1, 2 & 3 Use Select By Attributes with the businesses to select gas stations. These correspond to SIC code 5541. To display the gas stations and the layer of potential development areas, create a layer from the selected set (the gas stations). Change the symbol used to draw gas stations to Gas.

68 Display the layer of potential development areas with existing mixed-use zone areas.

69 Step 1 Use Select By Attributes with the zoning layer to select the mixed-use zones. These correspond to regional zoning codes MUC1 and MUC2. Create a layer from the selected features (as with gas stations, above) and display the mixed-use zones layer with the layer of potential development areas.

70 Summarize the amount of land currently and potentially zoned for mixed use.

71 Step 1 For the zoning layer, calculate the area of each zone—in square miles—by adding a field to the attribute table.

72 Step 2 Then use the Calculate Geometry option to calculate the area for each zone.

73 Step 3 Right-click the new field and click Statistics to get the sum of the area currently zoned for mixed use.

74 Step 4 Clip the potential development areas using the city boundary to get only the development areas inside the city.

75 Step 5 Clip creates a single output feature representing the areas of the potential mixed-use development. Calculate the area in square miles by adding a field to the attribute table and using the Calculate Geometry option (as shown above for the existing mixed-use zones).

76 You can then enter the area values for the mixed-use zoning and potential development areas into a spreadsheet to create the bar chart.

77

78 Potential development areas are displayed with current mixed-use zoning.

79 A chart showing the amount of land currently zoned for mixed-use development compared to the amount of land in the development area layer While not all of that area can be rezoned, the map and chart show that there is potentially much more land that could be used for mixed-use developments.


Download ppt "Lecture 19 GIS Project Design and Management + Case Studies"

Similar presentations


Ads by Google