US ATLAS Tier 1 Facility Rich Baker Brookhaven National Laboratory DOE/NSF Review of U.S. ATLAS and CMS Computing Projects Brookhaven National Laboratory NOVEMBER 14-17, 2000
2
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 2 Tier 1 Facility Requirements (1) Based on NCB Review Numbers Focus on Analysis (200k of 209k SI95) Probably Insufficient for Simulation CPU: 209,000 SpecInt95 Commodity Pentium/Linux Estimated 640 Dual Processor Nodes Online Storage: 365 TB Disk High Performance Storage Area Network Baseline: Fibre Channel Raid Array
3
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 3 Tier 1 Facility Requirements (2) Tertiary Storage: 2 PB Tape Library Baseline: HPSS, STK Media & Tape Drives 75% Event Summary Data 25% Simulation, Analysis Objects, Local Data “Raw” I/O Rate: 400 MB/second, 12.5 PB/year Exploit Use Patterns to Maximize Efficiency Random Access to AOD - Always on Disk Managed Access to ESD - Grid SW? Custom SW?
4
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 4 Estimation Methods - Hardware (1) Use Recent RCF Purchases as Cost Baseline Moore’s Law Scaling for Commodity Components (CPU, Disk, Tape) STK Tape Drives: Constant Cost per Drive, Double I/O Capacity Every 2 Years Similar Constant Cost Projections for High Performance Data Mover Nodes $40K per HPSS Mover Node $30K per SAN Control Node
5
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 5 Estimation Methods - Hardware (2) Local Area Network: 8% of Disk+CPU Cost plus $20K per HPSS Mover Firewall/WAN Hardware: 25% of LAN Cost Interactive Nodes 2 Linux Nodes Purchased per Year Maintain One Sun/Solaris Node “General Purpose” Nodes 21 Currently for RCF - Estimate 25 for ATLAS
6
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 6 Estimation Methods - Software Share Site License Costs with RCF HPSS: 50% of $200K by 2005 LSF: 50% of $65K Starting 2002 Veritas: $5K per SAN Control Node Or Other SW Choice Most Other SW License Costs Can Only be Estimated - Total $97K in 2005 Good Estimate Based on Actual RCF Costs to Support Operational Facility & Development
7
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 7 Existing Facility
8
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 8
9
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 9 Timeline Overview Prototype – FY ‘01 & FY ‘02 Initial Development & Test, 1% to 2% scale Establish Facility Independent from RCF Lessons Learned from RCF Experience System Tests – FY ‘03 & FY ‘04 Large Scale System Tests, 5% to 10% scale Support Growing Tier 2 Network Operation – FY ‘05, FY ‘06 & beyond Full Scale System Operation, 20% (‘05) to 100% (‘06)
10
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 10 Tier 1 Facility Capacity
11
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 11 Tier 1 Facility Staffing
12
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 12 Tier 1 Budget By Year (FY’01 k$) Includes Tier 1 Staff Under WBS 2.3.2
13
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 13 Tier 1 Budget (FY’01 k$)
14
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 14 Tier 1 Material Costs (FY’01 k$) HPSS License Included in HPSS Volume Manager Software Included in Disk “Other” Includes Power, Special Purpose Nodes, Video Conferencing, Supplies
15
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 15 Tier 1 Materials Summary (FY’01 k$)
16
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 16 Tier 1 Facility Beyond 2006 (FY’01 k$) Staffing: Constant at 25.5 FTE Major HW Components Constant $ at 33% of 2006 Full Facility Cost Allows for Continual Upgrade All Other Costs Level at 2005/2006 Levels
17
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 17 Comments Scaleable Design - Recent 2.5X Expansion Very Late Bulk Procurement Working System Earlier - Minimize Design Risk Maximize Moore’s Law Advantage Retain Flexibility as Long as Possible Leverage RCF Knowledge Lessons Learned Improved Estimation
18
November 14-17, 2000 Rich Baker US ATLAS Tier 1 Facility 18 Summary Facility Already Running Near Term Prototype Planning in Progress Budget Exceeds Agency Guideline by 33% Despite Recent 2.5X Scale Expansion! Estimates Are Realistic Detailed Cost Basis From Recent Purchases Moore’s Law Uncertainty Build to Cost Contingency Feasible As Long as Tier 2 Facilities Are Funded