1 Cosmic Origins Spectrograph
Charles D. (Tony) Keyes Last MSR: 22 April 2002 16 July 2002

2 The project is on track (green)
Project Summary A M J Remarks Budget G G G Schedule G G G Technical G G Y G Y FUV QE grid The project is on track (green) most recent report: 22 April 2002 LEGEND: G NOMINAL MODERATE PROBLEM SOLUTION EXISTENT Y R MAJOR PROBLEM NO SOLUTION YET

3 Schedule

4 Health Chart Subproject Staffing Schedule Technical
Instrument Development OK (g) ongoing (g) IDT/STScI MOU (g) FUV I & T CU/UCB (y) Commanding and RPS2  OP-01 (g) calib exposure development (g) Pipeline and Calibration  keyword development (g) pipeline development (g) SM4 initial planning (g)

5 Instrument Development (FSW)
DATE Y PROBLEMS/ISSUES PROGRAMMATIC IMPACT ACTION ESTAB. COMPL. Delay of FSW implementation for target acquisition (Build 4.0) Delays timeframe for testing our acq commanding and delays availability of subset of test image data Revised FSW development schedule implemented at Ball CURRENT STATUS Open Tool is not mature enough for use in Cycle 11 Phase II Cycle 11 Phase II to be released Spring ‘02 (originally January ‘02) Evaluation underway (internal & external evaluators) look and feel GUI process model STScI front-end development completed; one-month Ball schedule slip this period (Sep 02 delivery); no impact on beta OPUS/HDA Delivery nor Thermal-Vac MOU schedule; now one month of float

6 Instrument Development
DATE Y PROBLEMS/ISSUES PROGRAMMATIC IMPACT ACTION ESTAB. COMPL. None to STScI short-term; delays integration of FUV flight detector; IDT delay in MOU deliverables, T-V and SI delivery; additional long-term impacts possible IDT investigation: review of qualification procedures and test data; secure new grid; revise test procedures; utilize ETU for optical bench fitting activities; implemented repair and testing FUV detector QE enhancement grid breakage CURRENT STATUS Open Tool is not mature enough for use in Cycle 11 Phase II Cycle 11 Phase II to be released Spring ‘02 (originally January ‘02) Evaluation underway (internal & external evaluators) look and feel GUI process model Investigation complete; fix identified, implemented, and integrated; detector scrubbed and testing proceeding; 4-week delay to SI schedule and MOU deliverables (STScI T-V support development); FUV install in optical bench expected late July.

7 Highlights - Accomplishments
SI News: FUV flight detector QE grid breakage in detector T-V testing Detailed investigation conducted; full review of qualification and inspection procedures; modeling of material and test properties; design fix fabricated, installed, tested, and verified; re-scrub detector. Final vibration and thermal-vac testing of flight unit FUV01 to be performed in July; cumulative 4-week schedule impact. (continues yellow ) MEB functional tests completed successfully FUV and NUV gratings all installed on Optic Select Mechanisms (OSM) OSMs installed in COS optical bench OSM repeatability and stability accuracies require wavecal with each new central wavelength including FP-POS positions Completed and delivered COS Mini-Handbook Initiated SM4 SMOV requirements planning Joint effort with COS IDT

8 Highlights - Accomplishments (cont.)
STScI scheduling system Phase 5 Scheduling System components FLATFIELD exposures and SAA contours completed on schedule AUTO “WAVECAL” exposures in code development; revision of FP-POS (formerly called FP-SPLIT) exposure capability Ops bench testing at Ball for all components per Ball FSW availability timeline (Aug 02) Phase 6 integrated schedule established Continued keyword review; established COS Association requirements Commenced Bright Object Protection requirements review Evaluated FASTEX Standards for use with COS 2 are acceptable; FUSE DD observations submitted and approved Established STScI COS public WWW pages

9 Additional Information
Appendix Additional Information

10 APPENDIX: Planned Activities and Future Milestones
Commence Phase 6 Special Commanding requirements definition Commence Phase 6 Anomalous Recovery, Initial Turn-on developmnet Complete Phase 5 AUTO-WAVECAL exposure development Continue STScI FSW macro-timing tests on ops bench Complete review and issue OSM thermal issues report Continue keyword review; add TV-specific keywords to ICD-19 Commence Bright Object Screening scheduling system development Commence APT/ETC development Milepost Dates: {+ ==> later than last report} COS integrated SI test data to STScI: 1 Sep 2002 (no change) [Ball timeline] SI delivery to GSFC: 20 Mar (+1 month) [Ball timeline/QE grid impact] Launch: February 2004 (no change) [SM3B + 2 yr]

11 APPENDIX: COS Phase Development Plan (rev 6, 10/26/01)
Macro Development Reconfigurations Phase 2 (7/1/00 – 12/31/00) NUV Timetag Mode + Darks FUV Timetag Mode + Darks Phase 3 (1/1/01 – 6/30/01) FUV & NUV Accumulation Science Exposures FUV & NUV Target Acquisition Exposures FUV & NUV Target Peakup Exposures Phase 4 (7/1/01 – 12/31/01) Aperture Alignment Exposures OSM1 Focus Alignment Exposures OSM1 Rotation Alignment Exposures OSM2 Rotation Alignment Exposures FUV & NUV FP-Split Exposures Phase 5 (1/1/02 – 6/30/02) FUV & NUV GO Wavelength Calibration Exposures FUV & NUV Flat Field Lamp Calibration Exposures FUV & NUV Automatic Wavelength Calibration Exposures SAA Contours Phase 6 (7/1/02 – 12/31/02) SMGT Preparations SMOV Special Commanding FUV & NUV Anomalous Recovery FUV & NUV Initial Turn-on FUV & NUV BOP Target Screening Phase 7 (1/1/03 – 6/30/03) FUV & NUV Lifetime Adjustments

12 APPENDIX: Project Synopsis
Role: STScI supports COS science operations by leading development of “front-end” (operations) and “back-end” (OPUS/MAST/calibration) ground system and user support functions. COS project is led by NISD, and presently consists of 12 people (7.65 FTE) drawn from NISD, SISD, and ESS. The project is on track (green) most recent report: 22 April 2002

13 APPENDIX: Resource Summary
Current COS Resources (FY 02) NISD 3 Scientists (3.0 FTE) SISD 1 Data Analyst (0.5 FTE) ESS 1 System Engineer (0.5 FTE) 1 Command Development System Engineer (1.0 FTE) 1 Instrument Engineer (0.4 FTE) 2 Developers (1.25 FTE) Pipeline Development (1.0 FTE)

14 Progress versus Planned Milestones and Requirements:
APPENDIX: Metrics Progress versus Planned Milestones and Requirements: 5 of 7 planned activities completed within reporting period COS Operations Working Group Action Items: 0 opened, 0 closed; 2 revised during review period 4 presently open (1 High, 2 Medium, 1 Low) COS Calibration Working Group Action Items: 0 opened, 0 closed during review period 0 presently open

15 APPENDIX: COS FUV QE Grid
old broken new

16 APPENDIX: COS STScI WWW Page


Download ppt "Cosmic Origins Spectrograph"