1 Stormwater Overview Board of County Commissioners Planning Conference March 1, 2007

2 Stormwater Ordinance Required to meet Phase II Regulations Proposed to address secondary and cumulative impacts related to: 12 Mile WWTP expansion to 6 mgd 42-inch water transmission main 74 ByPass, Carolina Connector Expected to be required for future projects

3 Proposed Ordinance Section I – Stormwater Design Manual Section II – General Drainage Includes requirements in Land Use Ordinance Concentrated flow to adjacent properties Permanent drainage easement recordation Section III – Riparian Buffers Streamside Zone Undisturbed land along stream channel Exemptions include limited access and utility crossings, gravity sewer and stormwater bmp’s with no alternative, fences, dam maintenance, stream restoration

4 Proposed Ordinance Section III – Riparian Buffers (continued) Upland Zone Vegetative land along Streamside Zone Allowable uses include exemptions from Streamside Zone, storage buildings less than 150 sq ft, limited grading, greenways, recreational equipment

5 Proposed Ordinance Section IV – Stormwater Requirements Applicability: Cumulatively disturb > 1 acre Total impervious surface > 20,000 sq ft Exceed 6% impervious in protected watersheds Runoff Control Downstream hydrologic analysis High Density (exceeds 24% built-upon) control 1-inch rain, discharge equals pre-development rate, 85% TSS removal, post equals pre-development run-off rate for 1, 10, and 25-year storm Convey upstream drainage assuming build-out conditions 100-year storm elevations defined

6 Proposed Ordinance Section IV – Stormwater Requirements Final Plat Requirements Streams, ponds, wetlands, buffers, base flood boundary and elevations Permanent drainage easements Statement lot contains stormwater management facility As-Builts Annual Inspection Report Performance Security Plan Review Fee

7 Schedule May 2007 - Presentation to Planning Board June 2007 – Public Hearing and comment period August 2007 – Presentation to Board of County Commissioners


Download ppt "Stormwater Overview Board of County Commissioners Planning Conference March 1, 2007."