Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 1 Xolani Lembede 2010 ESI Forum Meeting 08 April 2010.

Similar presentations


Presentation on theme: "1 1 Xolani Lembede 2010 ESI Forum Meeting 08 April 2010."— Presentation transcript:

1 1 1 Xolani Lembede 2010 ESI Forum Meeting 08 April 2010

2 2 Stadium power supply requirements and status of provision  Soccer City Crown SS and Soccer City Chamber commissioned MV reticulation is 80% complete Gen sets and UPS system commissioned and chop over tested  Ellis Park Delays with Siemert Rd SS – Commissioning 15 May Precinct reticulation complete Gen sets and UPS system commissioned and chop over tested

3 3 status of 2010 preparedness in terms of:  Telecoms: key infrastructure, risk profiles and resourcing Network communication channels Fibre optics – vulnerable to damages Pilot cables – possible thefts Telkom lines – Tetra network – no major risks The team will be focusing on critical networks

4 4 Operational Readiness – Information Technology  IT support: key operational IT system risk profiles, e-mail and internet support over the period - IT plans over the period Risk mitigation Backup servers installed on all critical services i.e. SAP, E/mail, IT personnel on standby on all critical installations

5 5 Operational Readiness – Communication  Communications: alignment of communication processes between roles players during normal and emergency conditions Tetra system will be used among these stakeholders City Power Eskom Security JMPD SAPS Transportation Other Joint Command Centre Venue Operating Centre

6 6 Operational Readiness – Security  Security preparations: pro-active and reactive security measure being put in place and level of integration between technical and security staff Security personnel in all major substations Random patrol on critical networks

7 7 Operational Readiness – Disaster Management  Disaster management: alignment between regional electricity preparations and city and provincial disaster management structures Draft document in discussion stage Deal with the local situation, escalations to city level and to the provincial level

8 8 Operational Readiness – Personnel  Mitigation plans on how personnel will be sourced and scheduled for the duration of the 2010 tournament Staff roster is now complete Staff will be stationed on all major sites supplying the affected venues Precinct - Staff will be on site 3 hrs before the game Outside precinct – staff on site 1 hr before the game


Download ppt "1 1 Xolani Lembede 2010 ESI Forum Meeting 08 April 2010."

Similar presentations


Ads by Google