1
Restructured-APDRP An initiative of Ministry of Power Government of India Nodal Agency Power Finance Corporation Ltd. Restructured Accelerated Power Development and Reforms Programme R-APDRP Implementation in Karnataka
2
Go-Live Status of ESCOM’s of Karnataka Scheduled date for Go live / integration of all towns : Sep 2015 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP) ESCOMMBC live (100% implementation in Karnataka) Full Stack with Energy Audit BESCOM 25 16 CESC 12 6 GESCOM 21 11 HESCOM 29 26 MESCOM 11 1 TOTAL 98 60 Town Integration Energy Audit Schedule Mont h Up to Jan ’ 13 Up to Feb ’ 13 Up to Ma r’ 13 Up to Apr’ 13 Up to May ’ 13 Up to Jun’ 13 Up to Jul’ 13 Up to Aug ’ 13 Up to Sep’ 13 Up to Oct’ 13 Up to Nov ’ 13 Up to Dec ’ 13 Up to Jan’ 14 Up to Feb’ 14 Up to Mar ’ 14 Up to Apr’ 14 Up to May ’ 14 Up to Jun’ 14 Up to Jul’ 14 Up to Aug ’ 14 Up to Sep’ 14 Up to Oct’ 14 Up to Nov ’ 14 Up to Dec ’ 14 Up to Jan’ 15 Up to Feb’ 15 Up to Mar ’ 15 Up to Apr’ 15 Up to May ’ 15 Up to Jun’ 15 Targe t 101840 50 5355759198 Achie ved 61031 46 51 60 1
3
Restructured-APDRP Issues and Intervention required - Karnataka ActivityIssues /Status DC Data centre commissioning along with all hardware, OS, NMS, EMS & availability of network connectivity. DC Commissioned, in production phase since Dec 2011. Only state to successfully demonstrate DC/DR drill as on date. The same was done in in July 2013. DR is running as primary and DC as secondary from 15 th March 2015 as per the SRS requirement. GIS Updating delta changes of Assets LOI issued on NSG India by BESCOM for "Updating incremental data of Network Assets into GIS application under RAPDRP in 92 towns across all five ESCOMs of Karnataka. DWA issued by all ESCOMs on NSG. In BESCOM, incremental data given for 13 out of 25 towns and data validation at Field in progress for 3 out of 13 towns. In Bangalore, incremental data given for 9 out of 48 subdivisions to NSG for updation. Updating delta changes of Consumers The data of floating consumers to be tagged with assets in GIS is being shared by ESCOMs with ITIA for migrating the same from back end. So far 1,22,000 floating consumers of 24 towns in BESCOM are updated in GIS. Updating data on continuous basis Business flow ensures the assets and consumers are updated in GIS. Since GIS is a heavy application consuming lot of user time, the following changes are made for speedy disposal of new connections: Bypass GIS online for all cases where updating Assets is not required. Updating assets in GIS to be made One-time activity post-power sanction which will also improve performance. This change is yet to be deployed by ITIA. NA Deployment of GIS integrated Network Analysis Software Software is deployed and integrated with GIS User operations to begin which is planned by ITIA after implementing One-time GIS and user training is also pending from ITIA.
4
Restructured-APDRP ActivityIssues /Status MDAS Meter & Modems at all DTs, Feeders, HT consumers etc. Tender for Feeder meter replacement is under progress since it is joint work of KPTCL and ESCOMs For the Quantity Modems except HT & Boundary installations, tender work is under progress. M/s Infosys has requested ESCOMs to take up the procurement and installation of modems by ESCOMs. ESCOMs have agreed to take up the same and tender is called by BESCOM (all ESCOMs tender) for original BOQ along with 3 years incremental quantity. All the ERL modems fixed earlier will be replaced with new modems, Extra Cost of modems under Infosys scope will be deducted from amount to be paid to M/s Infosys. New(M/s Analogics) MDA software should be integrated with New MDM of M/s Infosys.ITIA requested to change their old MDM which is not user friendly. Since multiple modem vendors are selected, Infosys has to integrate both MDAS S/Ws CCCCustomer Care Centre Integrated with Data Centre in all 5 Discoms. Town Level Network connectivity Due to application slowness like GIS and WAMS,based on the recommendation, BESCOM has upgraded primary network to 4 mbps at all locations with last mile OFC connectivity. But quality of network connectivity is very poor with frequent fibre cuts and outages Secondary network provider has failed to deliver more than 109 links, out of 330 links in BESCOM. There are huge latency issues and present VSAT equipment is incompatible to increase the Bandwidth BESCOM has decided to call a Tender for the Alternate connectivity under RAPDRP Issues and Intervention required - Karnataka
5
Restructured-APDRP Implementation Status in Karnataka ITC:Reliance Infrastructure Ltd (May’09); Ernst & Young LLP(March 15) ITIA:Infosys (Dec’09) SDC:N/A SIA:N/A TPIEA-EA:CPRI (May’10) DC/DR:Bangalore/Chennai Pilot Towns:Bangalore, Mandya, Dharwad, Shikaripura and Gulbarga Ring Fencing:All 98 Towns completed & verified by TPIEA Baseline AT&C:All 98 Towns established Eligible towns Sanctioned Cost Rs. Cr Sanction dateGoI Loan Rs. Cr CP Fund Rs. Cr Disburse Rs.Cr. Part-A (IT) 98391.2Feb 09 & Sep 09 391.2 - Part-A (SCADA) Part-B 81 786.6Mar 10 196.6 590
6
Restructured-APDRP Consumer Indexing Asset Mapping * Initially it was proposed to migrate the legacy GIS data available with MESCOM for 6 towns. As the data was found to be not compatible by ITIA and MESCOM, a fresh tender is invited by MESCOM for DGPS survey, Validation, Asset mapping and Consumer indexing in respect of 6 towns with contract period of one year. DWA issued by MESCOM on successful bidder M/s. Northsouth GIS Pvt. ltd. Survey has started in all the 6 towns. DISCOMTotal TownsTotal Consumer as per RFP (Lakh) Work In Progress/ Taken upSurvey CompletedSubmitted by ITIAApproved by Utility TownsConsumers (Lakh) TownsConsumers (Lakh) TownsConsumers (Lakh) TownsConsumers (Lakh) % BESCOM2538.732543.272543.272543.272543.27112.00% HESCOM297.98298.87298.87298.87298.87110.00% GESCOM215.55215.55215.55215.55215.55108.00% MESCOM 11 * 4.1811*4.211*4.211*4.210*4.096.00% CESC124.98125.14125.14125.14125.14103.00% Total9861.339867.039867.039867.039766.83109.00% DISCOMTotal Towns Total Fdrs Total SS Work In Progress/ Taken upSurvey CompletedSubmitted by ITIA Approved by Utility TownsFdrsSSTownsFdrsSSTownsFdrsSSTownsFdrsSS% BESCOM251327124251327124251327124251327124251327124100% HESCOM29262652926265292626529262652926265100% GESCOM21154362115436211543621154362115436100% MESCOM 11 * 1855 55 55 55 5100% CESC12143291214329121432912143291214329100% Total 981904259921904259921904259921904259921904259100% Implementation Status in Karnataka
7
Restructured-APDRP ESCOMQuantity in Nos. meters Progress of meter installation ESCOMs committed date for metering Modem Pending quantity Progress In modem installation ITIA Committed to fix the New modems BESCOM(24) BMAZ 46 40 100% 40 pending Nil 20 th July-15 08 40 38 Nil Before next VC CESC21100%Nil 21Completed GESCOM10100%Nil10NILBatches will be deputed immediately HESCOM25100%Nil0223With in 12 days MESCOM26100%Nil1610Completed for 5Towns where GIS is already completed Boundary Meters & Modems : ESCOMQuantityPending quantitySchedule committed on 26/05/2015 Progress ESCOMs committed during the meeting ITIA Committed to fix the New modems BESCOM49877 2975Budget requested from divisions to complete the balance work which are not completed by RC work, since RC period is closed. 46902Budget is requested from the divisions to complete the balance work which is not completed by RC work, since RC period is closed. Committed to leave it for ESCOMs scope and old ERL modems in the field and at store are not used for DTCs and HTs in all ESCOMs CESC643076115 th July-15566915 th July-15--------do---------- GESCOM8303Nil 8303Nil--------do---------- HESCOM14943 681 15 th June-15 14262 15 th June-15--------do---------- MESCOM7350Nil.Nil7350Nil--------do---------- Schedule for Installation of DTC DLMS Compliant Meters Implementation Status in Karnataka
8
Restructured-APDRP Schedule for Installation of HT DLMS Compliant Meters &Modems ( responsibility of ITIA) ESCOMQuanti ty Pending quantit y Schedule committed on 26/05/15 Progress in metering ESCOMs committe d during the meeting Modem Pending quantity Progress In modem installation ITIA Committed to fix the New modems BESCOM(2 4) BMAZ 550 7439 Nil 480 Nil 20 July15 Completed 6959 Nil 20July15 28 3893 520 3455 Agreed to install before next VC End of July-15 CESC 801 Nil Completed Nil 145 656 30 th June-15 GESCOM 670 425 Before 15 th July-15 60 20 th April-15 670NIL Will Depute the batches immediately. HESCOM 1103 Nil Completed Nil 53 1050Will complete with in 12 days MESCOM 861 Nil. NilCompleted Nil 81249 Completed before 10 th April- 15 for 5Towns where GIS is already completed Implementation Status in Karnataka
9
Restructured-APDRP