Reto M. Hummelshøj Project coordinator 1 22 OCT. 2012 ECO-CITY STATUS 2012 Coordinators meeting Brussels 22-24 Oct. 2012.

Similar presentations


Presentation on theme: "Reto M. Hummelshøj Project coordinator 1 22 OCT. 2012 ECO-CITY STATUS 2012 Coordinators meeting Brussels 22-24 Oct. 2012."— Presentation transcript:

1 Reto M. Hummelshøj Project coordinator 1 22 OCT. 2012 ECO-CITY STATUS 2012 Coordinators meeting Brussels 22-24 Oct. 2012

2 ECO-City project Main project figures: ›22 project partners from ›5 countries ›3 Communities ›Cost budget 28.7 mio. € ›EU support 11.4 mio. € ›Project application 2003 ›Project period 2005-2012 ECO-CITY STATUS 2012 22 OCT. 2012 2

3 Main Components ›ECO-Buildings ›ECO-dwellings: about 1500 dwellings in many forms of buildings ›Tertiary buildings: schools, offices, commercial, institution, cultural, sport ›55% refurbishment ›Renewable energy: ›Use of solar, biomass, biogas, heat pumps, waste, (wind) etc. ›Polygeneration ›Biogas from organic household / industrial waste for transport, CHP and fertiliser ›Integrated free cooling concepts using river water, ground source heat pumps and district heating driving absorption cooling ›Integration ›Whole building / community approach, monitoring & knowledge sharing, training, dissemination ›Innovations ›Intelligent metering. Use of waste / storage. Ground source simulation program. 3 22 OCT. 2012 ECO-CITY STATUS 2012

4 Target for main demonstration elements after latest contract amendment 4 22 OCT. 2012 ECO-CITY STATUS 2012

5 ECO-City Progress October 2012 5 22 OCT. 2012 ECO-CITY STATUS 2012

6 ›We are proud ! 6 22 OCT. 2012 ECO-CITY STATUS 2012 Community RES el.RES heat./cool.RES heat./cool. solar space foreseencompletedprogressforeseencompletedprogressforeseencompletedprogress [kW] [%][kW] [%][m 2 ] [%] Helsingborg/Helsingør20010251%5.500 100%227 100% Tudela58 100%2.518 100%555194% Trondheim00#DIV/0!1.433 100%151493% Community Buildings newBuildings refurbishedPolygeneration capacity foreseencompletedprogressforeseencompletedprogressforeseencompletedprogress [m 2 ] [%][m 2 ] [%][kW] [%] Helsingborg/Helsingør52.959 100%77.43770.34891%2.307 100% Tudela16.77017.144102%12.514 100%00#DIV/0! Trondheim31.40731.953102%33.39035.142105%3.000 100%

7 Peculiarities Actual U-values in ECO-City 22 OCT. 2012 ECO-CITY STATUS 2012 7 MeasureTrondheim (Ranheimveien, passive house) H+H (Björka Ödåkra passive house) Tudela (New ECO- buildings) Façade W/m ²K 0.090.120.26 Roof W/m ²K 0.0650.070.17 Ground floor W/m ²K 0.080.090.24 Windows W/m ²K 0.80.91.4 Ventilation rateh -1 1.040.70.5

8 A few glimpses from Helsingborg and Helsingør 8 22 OCT. 2012 ECO-CITY STATUS 2012

9 BEST table numberProjectAreaEnergy savingsCO2 savings Energy cost savingsInvestment Simple pay- back time m2kWh/yearTon/yearEUR/yearEUR H+H 1. NewMaria Park 23-246420 341.19426 35.388 330.1729 H+H 1. NewFronten4591 368.43136 49.615 465.9049 H+H 1. NewLaröd Östra, phase 11388 103.61710 14.734 -- H+H 1. NewLaröd Östra, phase 26544 488.52147 69.467 -- H+H 1. NewBjörka Ödåkra4003 288.10525 25.313 524.36421 H+H 1. NewPortalen11073 678.9396 108.774 581.3505 H+H 2. New ECO LightMaria Sofia 3-411842 1.055.87275 121.127 310.2104 H+H 2. New ECO LightMaria Sofia 1-27098 543.10949 63.500 331.4825 H+H 2. refurbishedParkkvarteret Norra Vallgatan 44-463800 71.381-6 21.722 414.35315 H+H 2. refurbishedParkkvarteret Norra vallgatan 483289 61.782-5 19.268 215.91311 H+H 2. refurbishedHamilton appartments17250 -- - -- H+H 2. refurbishedStattena5600 -- - -- H+H 2. refurbishedVattentårnet2525 -- - -- H+H 2. refurb. adm.Hamilton office4073 -- - -- H+H 5.Cultural Yard13000 335.708357 120.169 2.925.07124 H+H 4.Grydemose School11196 725.635124 92.824 443.7845 H+H 3.Prøvestenen9615 684.354102 80.307 744.7679 Total community123.307 5.746.647409822.2107.975.28111 Impact of ECO-City buildings in Helsingør/Helsingborg 22 OCT. 2012 ECO-CITY STATUS 2012 9

10 22 OCT. 2012 ECO-CITY STATUS 2012 10 Example of CO2 emission (Grydemoseskolen) 60% savings with 5-10 year pay-back

11 Environmental impact of ECO-City 18 SEPTEMBER 2012 COMMON ECO-CITY MEETING IN TUDELA 11 28%

12 Overall reduction of energy consumption 18 SEPTEMBER 2012 COMMON ECO-CITY MEETING IN TUDELA 12 Environmentao impact of ECO-City 35% (target: 25-35%)

13 18 SEPTEMBER 2012 COMMON ECO-CITY MEETING IN TUDELA 13 Environmental impact of ECO-City 775 households Extra investment demand side 7.9 mio € vs. investment supply side 7.8 mio €

14 First 62 og 300 passive house dwellings completed in Miljøbyen Granås in Trondheim 14 22 OCT. 2012 ECO-CITY STATUS 2012

15 100 ECO-dwellings in Tudela received 1st prize of best energy efficiency and sustainable city development in Spain 17 Oct 2012 15 22 OCT. 2012 ECO-CITY STATUS 2012

16 Overall Objectives in ECO-City project - achieved ›Energy savings 4000 households equivalent in project and further impact of same magnitude ›Influencing 17.000 inhabitants ›Electricity savings of 20.2 GWh/y (incl waste storage and planned wind) ›Heat savings of 75.4 GWh/y ›CO2 savings of 26,500 ton/y ›Affordable pay-back periods of 10-12 years ›Being a pilot demo project as a ambassador for sustainable town development in the 3 regions from north to south in Europe 16 22 OCT. 2012 ECO-CITY STATUS 2012