1 SUPPLY CHAIN EVENT GLENOUTHER RENEWABLE ENERGY PARK FENWICK HOTEL, 10 TH SEPT 2015

2 2 Supply Chain Event – September 2015 Introduction oReason for Today oGamesa Brief Overview oProject Overview oProject Timescales oMain Opportunities oKey Skills Required oNext Steps

3 3 Reason for Today’s Event Supply Chain Event – September 2015 o Should Glenouther Renewable Energy Park be consented by East Ayrshire Council, Gamesa will require a range of suppliers to take it through construction to operation. o Gamesa would like to maximise opportunities for local businesses to bid for contracts. o This event provides an early opportunity for us to explain the opportunities that may arise should we get planning permission, and what requirements we may be looking for. o It also provides you with the opportunity to register your interest and ask any questions you may have at this stage.

4 4 Supply Chain Event – September 2015 Gamesa Brief Overview o With 21 years' experience and more than 31,200 MW installed in 51 countries, Gamesa is a global technological leader in the wind industry. Its comprehensive response includes also the wind turbine's operation and maintenance services, that manages for more than 550MW in the UK and in excess of 20,700 MW throughout the world. o Gamesa is also a world leader in the development, construction and sale of wind farms, having installed 6,400 MW in Europe, America and Asia. o The annual equivalent of its 31,200 MW installed amounts to more than 7 million tons of petroleum (TEP) per year and prevents the emission into the atmosphere of more than 47 million tonnes of CO2 per year. A global technological leader in the wind industry

5 5 Wind Farm Production Cycle Título presentación / Presentation Title Gamesa will remain involved throughout the lifecycle of a wind farm development from development, through construction and throughout the operational period. Gamesa is the only wind turbine manufacturer who can bring expertise throughout the entire life of a wind farm.

6 6 Supply Chain Event – September 2015 Project Overview Site Location LOCATED ON GLENOUTHER MOOR o 4.5 km northeast of Stewarton o 4 km north of Fenwick o 5.5 km east of Dunlop

7 7 Supply Chain Event – September 2015 Project Overview Key Aspects of Design o 12 wind turbines (hub height up to 78m, tip height up to 126.5m) o 7.5 km access tracks (4.2 km excavated tracks; 3.3 floating tracks) o 3 water-crossings o 1 meteorological mast o 1 substation compound o 2 borrow pits o 2 temporary construction compounds o Underground electrical and communication cabling o Felling of 149.5 ha of forestry; restocking of 118.99 ha forestry

8 8 Supply Chain Event – September 2015 Project Overview Site Layout

9 9 Supply Chain Event – September 2015 Project Timescales Best case scenario Feb 2016 Planning permission granted Mar 2016 Tender process opens for GI, Topo Survey, Discharge of Conditions Sept 2016 Tender process opens for main construction activities Oct 2016 Planning conditions discharged GI complete Mar 2017 Commencement of wind farm construction Oct 2018 Wind farm becomes operational

10 10 Supply Chain Event – September 2015 Project Timescales Indicative Construction Timetable

11 11 Supply Chain Event – September 2015 Main Opportunities Construction Phase Gamesa are looking to procure a range of suppliers, primarily for the construction of the wind farm. The key areas in which there are opportunities are: o Civil Engineering o Consultancy Services o Electrical Engineering o Project Management o Mechanical Engineering o Construction Services o Plant and Equipment Hire o Haulage o Landscaping o Security o Catering

12 12 Supply Chain Event – September 2015 Key Skills Required EXPERIENCE: We are looking for companies with experience in the opportunity areas just discussed. It is not a requirement that you have direct experience of working on a wind farm, but do demonstrate how your experience can transfer into the main opportunity areas, VALUE FOR MONEY: We are looking for the best value from our suppliers, so do be competitive when it comes to pricing. SOLUTION ORIENTATED: We require that our suppliers take an active approach in solving dilemmas faced during the construction of the wind farm, of which there will be many! COLLABORATIVE: There will be many technical disciplines involved in the construction of the wind farm – it is imperative that our suppliers all work together.

13 13 Supply Chain Event – September 2015 oRegister your interest via the Supplier Registration Form oPresent your company information clearly and in an easy to read format oKeep us updated if you acquire a new relevant skill / certification We will get in touch when we are ready to commence the tendering process. Next Steps

14 14 Título presentación / Presentation Title Thank you for your time. Any questions?