1 GNSS PROJECT (PHASE-I)
SARVARAJA (3.059 TMC) SAGAR VAMIKONDA (3.249 TMC) SAGAR POTHIREDDYPADU HEAD REGULATOR Sill : +841’ BANAKACHERLA CROSS REGULATOR Tunnel 5.25 Km OWK RESERVOIR 4.31TMC GANDIKOTA RESERVOIR FRL M CAP: TMC(Live) TMC (Gross) KM 24.33 PKG 47 PKG 48 PKG 49 SRMC SRBC SRBC Bypass canal (5 M dia) KM 32.64 KM KM KM KM 16.50 KM 34.80 KM KM 0.00 PKG 1 PKG 2 GNSS Flood Flow Canal GNSS FFC PKG 89 GORAKALLU RESERVIOR Capacity: TMC FRL : +261 M Package: Open Category Completed Work in Progress Tender Stage LEGEND With the completion of the above packages, an Irrigation Potential 35,000 Ac will be created in Kadapa District in Phase-I.

2 GNSS PROJECT (PHASE-I)
1 PROJECT PROFILE Location of Head works : Pothireddypadu Head regulator, foreshore of Srisailam Reservoir 2 Admn. Sanction : G. O. Ms. No. 53, Dt: for Rs Crs. G. O. Ms. No. 5, Dt: for Rs Crs. G. O. Ms. No. 108, Dt: for Rs Crs. 3 No. of Packages (EPC) 6 4 Agreement value of packages Rs Crs. 5 Budget Provision Rs Crs. Expenditure Rs Crs. Rs Crs. Cum. Exp. Rs Crs. 7 Utilisation 38 TMC 8 Ayacut Ultimate 2.6 Lakh acres (Cuddapah: 1,55,000 Acres, Chittoor: 1,03,500 Acres, Nellore: 1500 Acres) Phase-I 35,000 Acres in Kadapa District

3 GNSS PROJECT (PHASE-I)
9 Land Acquisition (Ultimate) Required : 26,284 acres Requisitioned 22,223 acres Acquired 4,082 acres 10 Mob. Advance. Paid Recovered Rs Crs. -- Rs Crs. Rs Crs Total Rs Crs Rs Crs. 11 Target Date 3/2008

4 GNSS PROJECT (PHASE-I)
PKG No. Description Name of Contractor Bid /Agreement Amount Rs in Crs. Agreement concluded date Mobilisation Advanace Rs. in Crs. 1 Construction of Gandikota Reservoir across river Pennar and Head regulator. Excavation of Main canal from KM 0.00 to KM 24.33, including CM & CD works, distributories, field channels etc., M/s Mythas – NCC, Hyderabad 250.20 3 / 2005 12.51 2 Excavation of Main canal from KM to KM 32.64, formation of Vamikonda and Sarvaraja sagar reservoirs including CM & CD works, distributories, field channels complete M/s Gammon India Ltd. 294.45 3/2005 13.72 OC Gadikota LI Scheme (Gandikota Reservoir to Pulivendula Branch Canal) M/s KBLM – CCL (JV) 286.00 14.30 47 Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from KM to KM, including Head regulator, CM & CD works Engineers & Contractors, Hyd 72.997 3.65 48 Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from KM to KM including Head regulator, CM & CD works Coramandal Prestcerte (P) Ltd, Hyd. 78.559 3.927 49 Excavation of GNSS Flood flow canal from Owk Reservoir to Gandikota Reservoir from KM to KM including Head regulator, CM & CD works Coramandal Prestcerte(P)Ltd, Hyd 73.65 3.682

5 GALERU NAGARI SUJALA SRAVANTHI
Package No.1 [EPC System] Construction of Gandikota dam across Penna river. Earth work excavation of main canal from Km to Km , fabrication and erection of radial crest gates, stop log gates and its accessories, river sluice gates, gantry crane etc. Construction of Head Regulator. Name of the Contractor : M/s MAYTAS-NCC (JV), Hyd. Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 30 Months Target date of Completion : 4/2007 Investigation : Completed Design (Canal) : 12 Km length approved against Kms. Completed Execution (Canal) : 12 Km length completed against Kms. Execution (Dam) : Exploring drilling completed. Qty. of earth work done : 52,93,972 cum against 81,98,000 cum Qty. of concrete work done : 2,807 cum against 3,04,000 cum Expenditure : Rs Crs. (Inc. Mob. Adv. Rs Crs.) against Rs Crs. : Rs Crores (mob. Adv. Only) : Rs Crores. Land Acquisition : Required Ac. Acquired 3398 Ac. Requisitioned:16398 Acs R & R : Estimate under preparation

6 GALERU NAGARI SUJALA SRAVANTHI
Package No. 2 Excavation of main canal from Km to Km Formation of Vamikonda Sagar and Sarvaraya Sagar reservoir and leading channels to reservoirs and its distributaries etc. Name of the Contractor : M/s Gammon India Ltd., Mumbai Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 30 Months Target date of completion : 4/2007 Investigation : Completed Design : 5 Km length approved against 10 Km Structures : Under Approval Execution : 6.5 Km length in progress against 10 Km Qty. of earth work done : 6 T cum against 7.73 T cum Expenditure : Rs Crs. (inc. mob. adv. Rs Crs) against Rs Crs. : Rs Crs. (Mob. Adv.) : Rs Crs. Land Acquisition : Required – 5253 Ac. Requisitioned : 5053 Acres Acquired : 419 Acres. R & R : Estimate under preparation

7 GALERU NAGARI SUJALA SRAVANTHI
Package No.47 / Cat – II Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of Head Regulator from Km to Km Name of the Contractor : Engineers & Contractors, Hyd. Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months Target date of completion : 2/2007 Investigation : Length in KMs against KMs – Completed a) Designs approved length in KMS against KMS - Approved b) Structures approved 17 Nos. against total 17 Nos. of Structures – Approved a) Execution: Length in KM in progress against total length of KM b) Structures approved - Nil - Nos. against total Nos. of Structures a) Qty. of earth work done : 20,25,000 Cum against 49,36,500 Cum. b) Qty. of Concrete works done - Nil - Cum against 46,000 cum. No. of Machinery (Machinery wise) deployed.Excavaters - 11,Tippers-45,Dozers-3,Compressers-8,Wagon Drills -8, Water Tankers-3 Expenditure : Rs Crs. (including Mob. Adv. Rs Crs.) against Rs Crores : Rs Crs (Mob. Adv. Only) : Rs Crs. (Inc. Mob. Adv. Rs Crs.) Mob. Adv. Recovered : Rs Crores Land Acquisition : Required : 640 Acres; Acquired : Nil, Requisitioned 640 Acres.

8 GALERU NAGARI SUJALA SRAVANTHI
Package No.48 / Cat – II Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km to Km Name of the Contractor : Coramandal Prestcerte(P)Ltd, Hyd. Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months Target date of Completion: 2/2007 Investigation : Length in KMs against KMs – Completed a) Designs approved length in KMS against KMS – Approved b) Structures approved Nil. against total 19 Nos. of Structures a) Execution: Length in 7 KM in progress against total length of KM b) Structures approved - 9 Nos. against total 19 Nos. of Structures a)Qty. of earth work done 25,50,000 Cum Against 50,15,000 cum No of Machinery deployed. (Excavators – 5, Tippers – 15, Dozer – 3, Compressors – 13, Wagon drills -13) Expenditure: Rs Crs. (inc. mob. Adv. of Rs Crs. against Rs Crs. : Rs Crs (Mob. Adv.) : Rs Crs. (Inc. Mob. Adv. Rs Crs) Mob. Advance Recovered : Rs Crores Land Acquisition : Required : 576 Acres ; Acquired : Nil, Requisitioned – 576 Acres

9 GALERU NAGARI SUJALA SRAVANTHI
Package No.49 / Cat – II Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD works from Km to Km Name of Contractor : Coramandal Prestcerte (P)Ltd Agreement Amount : Rs Crs. Agreement Date : Period of Completion : 24 Months Target date of Completion: 2/2007 1 Investigation : Length in KMs against KMs - Completed 2 a) Designs approved length in KMS against KMS – Approved 3 a) Execution: Length in 13 KMs in progress against total length of KM 4 a) Qty. of earth work done 43.8 Lakhs Cum against Lakhs Cum. b) Qty. of Concrete works done - Nil - Cum against 13 Nos of Structure Concrete. 5 No. of Machinery (Machinery wise) deployed ; Excavators -8,Tippers-12, Dozers-6, Compressors-10, Wagon Drill-10. 6 Expenditure : Rs Crs. (including advances Rs Crs. against Rs Crs. : Rs Crs. (Mob. Adv) : Rs Crs. (Inc. Mob. Adv. Rs Crs) Mob. Advance Recovered : Rs Crores Land Acquisition : Required : 737 Acres ; Acquired : Nil, Acquired – 737 Acres