1 River Research & Design, Inc.
LONGITUDINAL PEAKED STONE TOE PROTECTION {LPSTP} & LONGITUDINAL FILL STONE TOE PROTECTION {LFSTP} By Dave Derrick, Potomologist & VP, River Research & Design, Inc.

2 SELF-ADJUSTING, SELF-HEALING, BANK STABILIZATION METHODS ARE BEST!!

3 Derrick’s Reference PowerPoints
LECTURE: 04-BIG-RESISTIVE METHODS: FUNNEL TECHNIQUE CASE STUDY: CHENUNDA CREEK ROAD PROTECTION, NY; CASE STUDY: TOLEDO-MIAKONDA-BUILT FALL 2012 CASE STUDY: MISSOURI LEWIS & CLARK-VERMILLION SD {LFSTP} CASE STUDY: DUCK CREEK-DAVENPORT IA-LPSTP CASE STUDY: BELEWS CR-EPA 319-HILLSBORO MO VIDEO: DUCK CREEK

4 DESCRIPTIONS

5 Description of Longitudinal Peaked Stone Toe Protection {LPSTP}
LPSTP is a continuous stone dike placed longitudinally at, or slightly streamward of, the toe of the eroding bank. Cross-section is triangular. The LPSTP does not necessarily follow the toe exactly, but can be placed to form a "smoothed" alignment through the bend. Smoothed alignment might not be desirable from the environmental or energy dissipation points of view . Amount of stone used (1 ton/ lineal ft, 2 tons/ft, etc.) can depend on the height of LPSTP required, volume of stone required to mitigate toe scour, estimated stream forces (impinging flow) on the bank, & flood durations & stages. Bank grading is not always needed (existing vegetation not disturbed).

6 Description of Tie-Backs
Tie-backs are short stone dikes (at regular intervals) connecting the LPSTP to the stone key that is dug into the bank. Tie-backs are usually the same height as the LPSTP, or elevated slightly toward the bank end. If tie-backs are long they should be angled upstream to act as Bendway Weirs (if level-crested), or Bank Barbs (if crest is sloped).

7 Functions of No Mow Stones (NMS)
“No Mow Stones” are designed to effectively keep riparian, wetland, near stream, & other wild areas from getting accidently mowed. If mowed, many of these important & expensive areas never recover functionality. One study in Charlotte, NC. detailed that 26 agencies, governments, & companies mowed right-of-ways within city limits. No mow & no spray signs did not work. St. Louis District Corps of Engineers requires that Now Mow Stones be placed to protect vulnerable areas in stream mitigation banking projects.

8 FUNCTIONS

9 Functions of Longitudinal Peaked Stone Toe Protection
Resists the erosive flow of the stream, only stabilizes the toe, does not protect mid and upper bank areas. "Smoothed" longitudinal alignment results in improved flow alignment. Success depends on ability of stone to launch into scour holes formed on the river side of the LPSTP. Weight of stone in the LPSTP (loading of toe) might resist some shallow-fault geotechnical bank failures. Captures alluvium & upslope failed material on bank side of structure.

10 HISTORY

11 HISTORY OF LPSTP/LFSTP
One of the more universal bank protection methods. Very versatile, works well in a wide variety of situations. Pioneered by Vicksburg District Corps of Engineers in the late 1960’s. Probably 300 miles of LPSTP a rate of 1 to 2 tons/ft on Mississippi small to large sand-silt bed streams. Long history since early 1970’s of nearly maintenance free functionality. Very few failures recorded.

12 APPLICABILITY

13 APPLICABILITY OF LPSTP/LFSTP
Where the bank must be built back out into the stream (realignment of channel or a “false bankline” needed to gain space between stream & object requiring protection) Construction of & protection for a backfilled vegetative bench or terrace for habitat improvement and/or velocity attenuation) or to increase space between stream & object requiring protection

14 APPLICABILITY OF LPSTP/LFSTP
Where a minimal continuous bank protection is needed. Good where outer bank alignment makes abrupt changes Works well in combination with other methods (Hydraulic Cover Stones, Bendway Weirs, vanes, barbs, J-Hooks, and/or Locked Limbs/Locked Logs, and/or bioengineering within the stone {joint planting, Bent Willow Poles} or immediately behind stone {Live Siltation, Living Dikes}, & veg in mid/upper bank areas {brush layering, Slit Brush Layering, transplants, Living Dikes, Dead Dikes, rooted stock or container plants}.

15 DESIGN CONSIDERATIONS

16 DESIGN CONSIDERATIONS FOR LPSTP KEYS
LPSTP must be deeply keyed into the bank at both the upstream and downstream ends and at regular intervals along its entire length. Charlie Elliott’s spacing rules-of-thumb for keys in flat-sloped sand bed water bodies: 50 to 100 ft intervals on smaller streams, 1 to 2 bankfull widths on larger waterways. Keys at the upstream and downstream ends of LPSTP should not be at a 90 degree angle to the LPSTP structure, but at 20 to 30 degrees to HIGH FLOW. Keys should go far enough back into the river bank so river erosion & migration will not flank the key & the LPSTP. Keys should be vegetated if possible. Key length can be extended with vegetation alone in some cases. Volume of material per ft of key should equal or exceed the volume of material per ft in the LPSTP. Stone max. size & gradation should be the same as the stone used in the LPSTP & Tie-Backs Minimum key width should be three times the D-100 of the stone used

17 Key designs for continuous bank protection
20-30 degrees Longitudinal Peaked Stone Toe Protection Flow Inner bank Upstream key Outer bank 20-30 degrees LPSTP (black line) Both the upstream & downstream keys should be angled 20 to 30 degrees to high flow. All keys are vegetated & soil choked Downstream key Tie-backs (blue lines) connect the LPSTP to the key. The key, sometimes called the key root or keyway, is dug into the bank. Mid-project keys (red lines) are perpendicular to high flow & connect the tie-back to the bank Key designs for continuous bank protection

18 Longitudinal Peaked Stone Toe Protection (LPSTP)
As-built After a couple of high flow events stream has scoured at the toe & stone has self-adjusted Sediment can deposit landward of the LPSTP

19 Johnson Creek, MS. Pre-project, rapidly eroding near-vertical bank {rural, sand bed, slope < 1%, pool-riffle-pool, meandering, incised} Mini case study: 1 of 3

20 Johnson Creek, MS. As-built protection consists of Longitudinal Peaked Stone Toe protection (LPSTP) applied at 1 ton/ lineal ft (3 ft tall) Mini case study: 2 of 3

21 Johnson Creek-LPSTP one year later (note volunteer willow growth)
Mini case study: 3 of 3

22 Longitudinal Peaked Stone Toe Protection {installed 1977, picture taken Sept 2003} at Batapan Bogue, Grenada, MS. LPSTP has launched as intended (note steep angle of repose), armored the scour hole as expected, & mature vegetation is assisting with overall bank stability

23 CASE STUDY- Hickahala Creek Pipeline Protection Project at milepost Tate County, Senatobia, MS Constructed Sept Longitudinal Peaked Stone Toe Protection {LFSTP} with upper bank paving

24 LPSTP BUILT FROM SELF-ADJUSTING, SELF-FILTERING STONE, EXCESSIVE SCOUR SHOWN
As-built cross-section, note angle of repose 1:1.5 to 1:1.25 Reduced height of protection Undercut & launched, original height of protection is reduced Undercut angle of repose is steeper than original

25 Looking US at the entire stream trying to flow underneath the exposed pipeline, the first bend downstream of a long straight stretch is hard to repair, the water does not want to turn!!! This stream put sediment 1,000 ft in a straight line out into the farmer’s field & scoured the field.

26 Area of interest. Flow attack angle

27 LPSTP 5 ton/ft toe September-26-2003
LPSTP & bank paving totaled 8 tons/ft on this bank! Bank Paving September

28 Hickahalla Creek, Senatobia, MS. Constructed Sept 2003
Hickahalla Creek, Senatobia, MS. Constructed Sept Looking US at impinging flow impact zone. Note steep angle where LPSTP was undercut & launched (self-adjusted). Several years later this bank is still stable & vegetated April 2006

29 Note steep angle where LPSTP was undercut and launched (self-adjusted)
Original angle of repose Launched angle of repose

30 4 years after construction, very stable, veg growing well
LOOKING US, JULY 2004 4 years after construction, very stable, veg growing well March 2007

31 7 years later, bank steep near water but very stable, Veg growing well on 2 ft of deposition on stone, rock has not launched since high flows hit shortly after construction April 19, 2011

32 3 MINI LPSTP CASE STUDIES

33 Over-launching of LPSTP due to excessive scour, S
Over-launching of LPSTP due to excessive scour, S. Fork Tillatoba Creek, installed 1972, photographed 1998

34 Minimal LPSTP Pix by Wayne Kinney
Brushy Creek, IL. Looking DS. About 0.75 ton/ft of self-adjusting stone, which is about the minimum that can be used. Note that contractor worked from top bank & really beat up a lot of the good upper bank vegetation.

35 Transitioning from LPSTP to full bank paving
Looking DS on Harland Cr. Tchula, MS, very smooth transition in the downstream direction from one ton/ft LPSTP to full bank paving (tree area)

36 COMBINATIONS OF RESISTIVE & REDIRECTIVE METHODS: CASE STUDY- Duck Creek East of Eastern Avenue, Davenport, Iowa (View the construction video) Constructed June-July Longitudinal Peaked Stone Toe Protection {LFSTP} with interspaced Short Bendway Weirs & Locked Logs

37 LPSTP with Bendway Weirs & Locked Logs modified from: www.E-SenSS.com
20-30 degrees Inner bank Flow Upstream key Outer bank Locked Logs 20-30 degrees Downstream key Bendway Weirs at intervals, keyed into the LPSTP. Designed to act as a system to realign the thalweg & reduce velocities near the LPSTP LPSTP with Bendway Weirs & Locked Logs modified from:

38 FROM DOWNSTREAM LOOKING UPSTREAM AT THE THALWEG ALIGNMENT

39 Looking US @ thalweg realigned by Bendway Weirs & Locked Logs
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. CONSTRUCTION-DUCK CR. E. OF EASTERN AVE. PIX BY DERRICK

40 Same pix as previous, but with thalwegs delineated.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Old thalweg alignment new thalweg alignment CONSTRUCTION-DUCK CR. E. OF EASTERN AVE. PIX BY DERRICK

41 From DS looking US @ thalweg trace.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. CONSTRUCTION-DUCK CR. E. OF EASTERN AVE. PIX BY DERRICK

42 3 YEARS AFTER PROJECT COMPLETION Looking US to DS Photos: Brian Stineman SEPTEMBER 2011

43 3 YEARS LATER-DUCK CR-BRIAN STINEMAN 9-2011
3 YEARS LATER-From DS bend looking US. All stable & fully functional. Great diversity & complexity of vegetation. 3 YEARS LATER-DUCK CR-BRIAN STINEMAN

44 3 YEARS LATER-DUCK CR-BRIAN STINEMAN 9-2011
3 YEARS LATER-Looking US in the bite of the Bendway Weirs & Locked Logs providing hyd. roughness & habitat 3 YEARS LATER-DUCK CR-BRIAN STINEMAN

45 3 YEARS LATER-DUCK CR-BRIAN STINEMAN 9-2011
3 YEARS LATER-Looking a well vegetated bank & overbank riparian corridor. All stable. Bendway Weirs & Locked Logs providing complexity in the channel , 3 YEARS LATER-DUCK CR-BRIAN STINEMAN

46 COMBINATIONS OF RESISTIVE & BIOENGINEERING METHODS: CASE STUDY – Elton Creek DS of Freedom 6 Bridge, Cattaraugus County, New York Constructed in 3 days Oct Longitudinal Peaked Stone Toe Protection {LPSTP} with Joint Planting, Live Siltation & Living Dikes (Shrub Willow transplants)

47 Looking US at eroded bank. Bob is 6 ft 4” (for scale).
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. PRE-PROJECT-Elton Creek DS of Freedom 6 Bridge-derrick-May 17, 2007

48 Elton Creek near Freedom 6 Bridge, Freedom, NY
Road Install one-half of the Longitudinal Peaked Stone Toe Protection (LPSTP).

49 BOTTOM LAYER IS JOINT PLANTING & TOP LAYER IS LIVE SILTATION {Willow branches about 1-2 inches in diameter, 6 to 8 ft long, 2/3 in ground, 1/3 out, intermixed with Silky & Red Osier Dogwood that is 4 to 6 ft long} “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”.

50 Elton Creek near Freedom 6 Bridge, Freedom, NY
Road Install adventitious rooting Willow Poles

51 Elton Creek near Freedom 6 Bridge, Freedom, NY
Road Install remainder of LPSTP. Side slopes will be at the angle of repose

52 Looking DS. Vegetation integrated thru LPSTP.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

53 Elton Creek near Freedom 6 Bridge, Freedom, NY
Install top row of Live Siltation over top of LPSTP stone. Road

54 Looking US at installed Live Siltation (willow & dogwood).
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

55 TRANSPLANTING LARGE SHRUB WILLOWS AS LIVING DIKES Multi-stem (20 to 40 stems) bushes approx. 14 to 24 ft tall, transplanted as a single clump, with roots in trench directly behind the LPSTP. Tops of branches were trimmed & used as Live Poles (6 to 10 ft long). “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”.

56 THE PLAN – ELTON CREEK DS OF FREEDOM 6 BRIDGE
WILLOW BUSH TRANSPLANTATION FLOW “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Drawing by Robert Shenk, Catt County Soil & Water

57 Elton Creek near Freedom 6 Bridge, Freedom, NY
Road Dig trenches to receive willow bushes

58 Looking DS at LPSTP, backfilled bank, & dug trench.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

59 Another good-sized willow bush transplant.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

60 Elton Creek near Freedom 6 Bridge, Freedom, NY
Transplant large multi-stem Willow Bushes Road

61 Gently placing willow bush in trench.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

62 Close-up of willow bush & cuttings.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

63 Elton Creek near Freedom 6 Bridge, Freedom, NY
Road Water in & backfill

64 Looking US at LPSTP, Live Siltation, & transplants.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

65 All veg in this pix was installed in 45 minutes.
“Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

66 Veg planted on a grid, Live Siltation in front & transplants
Willow shrub transplants & willow poles “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. Joint Planting Live Siltation Under construction-Elton Creek DS of Freedom 6 Bridge-derrick-Oct 2007

67 19 MONTHS LATER-Elton Cr. DS of Freedom 6 Br.-Derrick-June. 9, 2009
1 growing season & 2 more growing months after completion. From point bar right bank. This is the 50 ft of Live Siltation & two large willow bush transplants that took 45 minutes to install. “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. 19 MONTHS LATER-Elton Cr. DS of Freedom 6 Br.-Derrick-June. 9, 2009

68 32 MONTHS LATER-Elton Cr. DS of Freedom Br.-Derrick-June 15, 2010
2 years & 8 more growing months after completion. From point bar right bank. This is the 50 ft of Live Siltation & two large willow bush transplants that took 45 minutes to install. Veg is very robust. “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”. 32 MONTHS LATER-Elton Cr. DS of Freedom Br.-Derrick-June 15, 2010

69 Design Rules-of-Thumb for LPSTP (developed from experience in Mississippi on incised, relatively flat-sloped, sand bed streams) Dr. Dave Biedenharn recommends that if you have never used LPSTP in your area, get a designer with LPSTP experience to design your first project! If there is the opportunity to build a demonstration project do so. Either test different heights of LPSTP in a number of similar bends, or for testing in a single bend start at the upstream end with a reasonably tall 50 ft long section of LPSTP (take the amount of stone calculated from consideration #2 and add 4 ft to the height). Continue in the downstream direction reducing height in 1 ft increments until an unusually small amount of stone is used (3 ft below low-flow water surface elevation for example, or below the vegetation line if one exists). After a reasonable time and at least two flood or long-duration high-flow events the sections that failed will provide some guidance for the minimum effective crest height At this time, no specific design criteria exists that relates the crest elevation of LPSTP to the channel forming discharge, effective discharge, or dominant discharge. One ton of LPSTP/per lineal ft is approx. 3 ft tall (using ft) Two tons/per lineal ft is approx. 5 ft tall (height calculations from Vicksburg Dist.) Three tons of LPSTP/per lineal ft is approx. 6 ft tall 7.5 tons is 9.5 ft tall Four tons of LPSTP/per lineal ft is approx. 7 ft tall 10 tons is 11 ft tall Six tons of LPSTP/per lineal ft is approx. 8.5 ft tall 14 tons is 13 ft tall Pg 1 of 3

70 Design Rules-of-Thumb for LPSTP (continued)
Maximum stone size and correct gradation can be generated using any of many available riprap sizing design programs (“ChanlPro”, WEST Consultants “RIPRAP”, etc.) * Consideration #1: The minimum amount of stone that would have a launchable component to any degree, would be ½ to ¾ of a ton of stone per ft. The ½ ton/ft amount would provide a triangular section of stone approximately 2 ft tall. * Consideration #2: Maximum scour depth in the bend should be numerically calculated, or estimated from field investigations (depths might be underestimated due to in-filling of scour holes during the falling side of the high-water hydrograph). Typically 1 ton of stone will protect against every 3 ft of scour. Amount of stone required to amour the estimated maximum scour depth should be calculated, and a factor of safety added. ** If scour is greater than 3 ft (as calculated in Consideration #2) then a Longitudinal Fill Stone Toe Protection (LFSTP) should be considered. Pg 2 of 3

71 Design Rules-of-Thumb for LPSTP (continued)
* Consideration #3: If there is a vegetation line, the mature well-established section of the veg line should be analyzed, and if Considerations #1 and 2 are met, then the veg. line elevation would be the absolute minimum crest elevation. But, since plants immediately above the vegetation line are typically not very robust, and there is no factor of safety included, this minimum crest height should be increased at least 2 to 4 ft or more, dependant on situation. Consideration #4: The height of the bend’s opposite bank pointbar bench should be analyzed. If the point bar bench height is taller than the crest of the designed LPSTP, then consideration should be addressed as to whether the LPSTP height should be raised to a height equal to, or taller than, the pointbar bench elevation. Scour estimation and various methods of positioning launchable stone are discussed in CORPS Engineering Manual “EM-1601, Chapter 3” Pg 3 of 3

72 LONGITUDINAL FILL STONE TOE PROTECTION {LFSTP} Same as LPSTP but the crest has a width!!

73 Longitudinal Fill Stone Toe Protection {LFSTP} (also called a “Weighted Toe” or a “Reinforced Revetment”) Description -Longitudinal Fill Stone Toe Protection (LFSTP) is similar to LPSTP, except that instead of coming to a peak, the crest has a specified width. Therefore, LFSTP has a trapezoidal cross-section as compared to the triangular cross-section of LPSTP. Advantages - Same as LPSTP. In addition, in areas of deep scour LFSTP provides sufficient rock to self-adjust (launch) into the scour hole while still maintaining its original crest height. Design considerations - The maximum scour depth should be calculated. The volume of stone required to launch into and armor the scour hole (with an appropriate margin-of-safety incorporated into the design) should be calculated. Based on these calculations, the crest width (volume of launchable stone needed from the LFSTP) can then be back-calculated.

74 LFSTP is similar to LPSTP but it has a crest width!
Typical colluvium & alluvium deposition (note swale, good for wetland plants but can drown young planted willow) LFSTP is similar to LPSTP but it has a crest width! Longitudinal Fill Stone Toe Protection (LFSTP)

75 Longitudinal Fill Stone Toe Protection (LFSTP)
Original height of protection still maintained after stone has launched into deep scour hole

76 COMBINATIONS OF RESISTIVE, REDIRECTIVE, & BIOENGINEERING METHODS: CASE STUDY- Cattaraugus Savage Road, Sardinia, New York Constructed October A FALSE BANKLINE USING “DUG-IN” LFSTP WITH LIVE SILTATION, A VEGETATED FLOODPLAIN BENCH & BENDWAY WEIRS

77 LFSTP LFSTP False Bankline & Created Floodplain Bench
Living Dikes Slit-trench plantings Pole plantings Live Siltation Original bankline Backfill LFSTP On gravel-cobble streams the LFSTP can be dug below stream invert, hard to do in sand

78 LFSTP False Bankline Backfill
All stone streamward of the red line can self-adjust, & the original design height of the protection is still maintained Original bankline Backfill

79 LIVE SILTATION BEHIND & OVER THE TOP OF THE LONGITUDINAL FILL STONE TOE PROTECTION (LFSTP)

80 The secret to success with willows is to get the basal ends down into the water, or the vadose zone. Looking US. Live Siltation willows are behind & over the top of the LFSTP.

81 Looking US at Live Siltation behind LFSTP, placing fine-grained material from DS end of opposite bank point bar (growing medium for Live Siltation).

82 Looking US at completed project with all LPSTP with Live Siltation, Rock Vane, Bendway Weirs and the floodplain bench in place

83 Jumping a year ahead, looking US at the same floodplain bench, note good veg growth. Aug 29, 2005

84 Looking DS at Live Siltation, it will provide shade quickly over water and LFSTP.

85 Looking DS at Live Siltation behind LFSTP, Catt Creek at Savage Road.

86 Live Siltation Aug 29, 2005, end of first growing season after installation. Note 2 Bendway Weirs

87 This PowerPoint presentation was developed & built by Dave Derrick
This PowerPoint presentation was developed & built by Dave Derrick. Any questions or comments, call my personal , or Enjoy the information!! “Based on the interagency publication, Stream Corridor Restoration: Principles, Processes, and Practices, this introductory training covers: Stream corridor ecosystems and their components Ecological processes, structure & functions Characterization and analysis of stream corridors Development of a restoration plan Design, implementation, monitoring, and Integrated, iterative, adaptive, flexible approaches”.

88 REGARDING QUESTIONS, I AM ALL EARS !!!
Each ear is 10 inches long, front legs are 5 inches long Cleophus at 8 weeks

89 Live siltation (willow)
Constructed terraces with specific species vegetation (or combos) on each bench Live siltation (willow) Backfill Original bank LPSTP Longitudinal Peaked Stone Toe Protection (LPSTP) Constructed of a well-graded, self-adjusting, self-filtering stone (no filter fabric underlayment)

90 LIVE SILTATION landward of LPSTP
From: Produced by John McCullah’s firm Salix Applied Earthcare