Construction Report November 17, 2009
3
Projects Site Improvements –In close out Track replacement and turf –Last phase (track) Generators –In close out
4
Projects Walking tracks: Redesign Water wells On hold Bleachers Ordered Stadium seatsJanuary 2010
5
District Projects Fence / gatesOngoing Science Classrooms / lab Auditorium lighting Sports Fields Generators Marquees Scoreboard Playgrounds Athletic Director Office
6
Projects Sheldon ECA In close out Early Learning CenterIn close out M. R. Null Middle SchoolPunch list
7
Maintenance, Operations & Transportation Complex (Support Services) Property purchased Programming resumed/completed Surveys Design development – final phase Utility Service Environmental Geotechnical
8
Maintenance, Operations & Transportation Complex (Support Services) Corps of Engineers Wetlands TIA DOT Texas Parks & Wildlife Utilities Harris County (permits) Harris County Flood Control
9
Maintenance, Operations & Transportation Complex (Support Services) Storm water Detention Historical Endangered species
10
Network Operations Center Architect Land Programming – final phase Survey Geotechnical
11
Developments Update Projections Enrollment projections Future projects Attendance zones
12
Elementary #5 Architect identified Engineer identified Programming Initial design review Plan reuse Enrollment projection