Presentation is loading. Please wait.

Presentation is loading. Please wait.

Oct 24 2011C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document

Similar presentations


Presentation on theme: "Oct 24 2011C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document"— Presentation transcript:

1 Oct 24 2011C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document http://clasweb.jlab.org/wiki/index.php/PCAL_navigation

2 Oct 24 2011C. Smith - PCAL/EC Commissioning 2 PCAL/EC Calibration and Commissioning  Final assembly and cosmic tests of six PCAL modules in EEL 125.  EC uncabling, refurbishment, recabling, integration into CLAS 12 trigger.  PCAL installation, checkout and joint commissioning/calibration with EC.

3 Oct 24 2011C. Smith - PCAL/EC Commissioning 3 PCAL/EC Calibration and Commissioning  Final assembly and cosmic tests of six PCAL modules in EEL 125.  Primary goals: PMT gains (HV settings), scint. fiber attenuation lengths, response uniformity, light yield.  Evaluate CLAS12 DAQ environment: (FADC, trigger-based cluster finding, offline reconstruction).  FADCs still being bench tested, will use LeCroy 1881 ADCs and delay cables.  Manpower: PMT installation, light leak checking, cable routing and connections, DAQ.  Software: HV slow controls, calibration database, legacy calibration code (C. Smith), reconstruction and calibration code in development (M. Wood, W. Brooks)  EC uncabling, refurbishment, recabling, integration into CLAS 12 trigger.  PCAL installation, checkout and joint commissioning/calibration with EC.

4 Oct 24 2011C. Smith - PCAL/EC Commissioning 4 PCAL cosmic tests in EEL 125 - Status First PCAL module waiting in corner of room for fiber cutting rig to be installed. Stacking of second module has begun.

5 Oct 24 2011C. Smith - PCAL/EC Commissioning 5 U fibers V,W fibers PCAL cosmic tests in EEL 125 - Status Goal: Fiber cutting and polishing complete by end of November

6 Oct 24 2011C. Smith - PCAL/EC Commissioning 6 PCAL cosmic tests in EEL 125 - Status JMU delivered enough photomultiplier assemblies for at least 2 modules. Photomultiplier installation and light leak checks should take 1-2 weeks -> Dec 14 Opaque RTV has already been applied to seams and mating surfaces of PCAL box. Cable installation and initial HV settings could take another week -> Dec 21 Would be desirable to conduct cosmic runs over holidays if DAQ is ready. PCAL PMT Assembly

7 Oct 24 2011C. Smith - PCAL/EC Commissioning 7 Previous experience – slow start, fast finish 1996 Test Lab checkout of EC modules

8 Oct 24 2011C. Smith - PCAL/EC Commissioning 8 PCAL/EC Calibration and Commissioning  Final assembly and cosmic tests of six PCAL modules in EEL 125.  Primary goals: PMT gains (HV settings), scint. fiber attenuation lengths, response uniformity, light yield.  Evaluate CLAS12 DAQ environment: (FADC, trigger-based cluster finding, offline reconstruction).  FADCs still being bench tested, will use LeCroy 1881 ADCs and delay cables.  Manpower: PMT installation, light leak checking, cable routing and connections, DAQ.  Software: HV slow controls, calibration database, legacy calibration code (C. Smith), reconstruction and calibration code in development (M. Wood, W. Brooks)  EC uncabling, refurbishment, recabling, integration into CLAS 12 trigger.  Goals: Replacement of weak, broken, inaccessible PMTs/bases, repair light leaks.  Still compiling list – possibly as many as 50 PMT/bases need to be accessed ~ 1 month work.  Repair work difficult unless all cables and some railings removed.  Schedule - CLAS 6 removal: 5/2012, DAQ /pre-cable installation: 10/2012, 1 st PCAL installation: 1/2014.  More time for PCAL cosmic testing, less time for integration into CLAS 12 DAQ prior to commissioning runs.  Earliest possible installation CLAS12 DAQ w/frontend/trigger electronics, cable up and test a single EC sector.  Possible to have ~1 year of EC / CLAS12 DAQ testing before arrival of PCAL.  PCAL installation, checkout and joint commissioning/calibration with EC.

9 Oct 24 2011C. Smith - PCAL/EC Commissioning 9 EC Refurbishment – PMT replacement EC uses a mixture of Phillips and EMI PMTs that run at different voltages and use non-interchangable socket/bases. PMTs running at or near their maximum HV ratings should be replaced.

10 Oct 24 2011C. Smith - PCAL/EC Commissioning 10 EC Refurbishment – PMT replacement Between 5-10 Phillips and EMI PMs are at or near max HV. SPARES - XP2262: ~6 JLAB, 113 available at UVA (D. Day) No ET9954B spares, still available at $650 ea @ 50 minimum.

11 Oct 24 2011C. Smith - PCAL/EC Commissioning 11 PCAL/EC Calibration and Commissioning  Final assembly and cosmic tests of six PCAL modules in EEL 125.  Primary goals: PMT gains (HV settings), scint. fiber attenuation lengths, response uniformity, light yield.  Evaluate CLAS12 DAQ environment: (FADC, trigger-based cluster finding, offline reconstruction).  FADCs still being bench tested, will use LeCroy 1881 ADCs and delay cables.  Manpower: PMT installation, light leak checking, cable routing and connections, DAQ.  Software: HV slow controls, calibration database, legacy calibration code (C. Smith), reconstruction and calibration code in development (M. Wood, W. Brooks)  EC uncabling, refurbishment, recabling, integration into CLAS 12 trigger.  Goals: Replacement of weak, broken, inaccessible PMTs/bases, repair light leaks.  Still compiling list – possibly as many as 50 PMT/bases need to be accessed ~ 1 month work.  Repair work difficult unless all cables and some railings removed.  Schedule - CLAS 6 removal: 5/2012, DAQ /pre-cable installation: 10/2012, 1 st PCAL installation: 1/2014.  More time for PCAL cosmic testing, less time for integration into CLAS 12 DAQ prior to commissioning runs.  Earliest possible installation CLAS12 DAQ w/frontend/trigger electronics, cable up and test a single EC sector.  Possible to have ~1 year of EC / CLAS12 DAQ testing before arrival of PCAL.  PCAL installation, checkout and joint commissioning/calibration with EC.  Cosmics: check EC calibration after PCAL installation, transverse alignment, recheck PCAL calibration (vertical vs. horizontal), spatial, energy uniformity and efficiency of (EC∙PCAL) trigger, debug cluster finding, evaluate trigger based software corrections (gain,attenuation,pedestal).  Beam: Luminosity studies (vs. thresholds, beam energy, target, torus, solenoid, polarity, sector).

12 Oct 24 2011C. Smith - PCAL/EC Commissioning 12 Flash ADC JLAB FADC250 16 Channel 250 MHz 12-bit Wave Form Digitizer Sector 3 inner U21 - U25 3:1 UVA splitter 2/3 1/3 Current Test Setup on Forward Carriage Sergey P. Sergey B.

13 Oct 24 2011C. Smith - PCAL/EC Commissioning 13 FADC250 Tests U21-U25 V22-V26 W22-W26 Time (1 ch=4 ns) Charge Trigger studies: Capture windows (red) will be set to optimize S/N. Luminosity studies: Effect of multiple hits on energy and cluster reconstruction. Improved calorimetry: Event-by-event baseline subtraction possible.

14 Oct 24 2011C. Smith - PCAL/EC Commissioning 14 FADC250 Tests  Current MIP based energy calibration fixes only a single point at 10 MeV (~ch. 100).  Extrapolating this calibration to 10 GeV e- may not be adequate.  More accurate calibration requires knowledge of conversion gain of each ADC channel and gain stability of PMTs at high rates or linearity over full dynamic range.

15 Oct 24 2011C. Smith - PCAL/EC Commissioning 15 PCAL summed energy may require software corrections in trigger EC: Dalitz u+v+w readout cancels scintillator attenuation x,y dependence to first order. PCAL: u+v-w readout creates worst case scenario.

16 Oct 24 2011C. Smith - PCAL/EC Commissioning 16 The End Thank you

17 Oct 24 2011C. Smith - PCAL/EC Commissioning 17 CLAS 12 Installation Timeline (old)

18 Oct 24 2011C. Smith - PCAL/EC Commissioning 18 CLAS12 Forward Carriage Rack Layout


Download ppt "Oct 24 2011C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document"

Similar presentations


Ads by Google