Download presentation
Presentation is loading. Please wait.
Published byScot Todd Modified over 9 years ago
1
TDC2-TCC2 consolidation status report to RSSO EDMS 1422345 October 14 th, 2014 E. Harrouch, Q. Bouirek, EN-MEF, on behalf of the TDC2/TCC2 WG
2
Outline Objectives and schedule Completed activities Dosimetry analysis Conclusions RSSO meeting
3
Objectives Reduce corrosion of vacuum equipment Replace PVC-insulated cables Re-route cable trays and cables Eradicate water leaks Upgrade ventilation Reduce machine downtime Replace damaged equipment (TCSC, ion pumps, beam instrumentation) Replace obsolete low voltage equipment Install radiation resistant equipment Apply ALARA principle Reduce maintenance time Increase Mean Time Between Failures RSSO meeting
4
2014 Schedule RSSO meeting L3 ALARA Committee agreement in October 2013. EDMS 1317027 L3 ALARA Committee agreement on May 20th for EN/EL activities. EDMS1377072
5
Outline Objectives and schedule Completed activities Dosimetry analysis Conclusions RSSO meeting
6
Removal of hot equipment TCSC removed first and brought to B.955 3 splitter2 magnets and 2 MDLV removed and stored in TDC2 Various beam monitors, BLM and vacuum beam pipes RSSO Meeting
7
Cooling and ventilation upgrades RSSO meeting New chilled water pipes (200 m DN 200) New cooling coils in all AHU’s AHU cabinet (40 years old) quite in good shape Demineralized water circuit: 20 new valves Challenge: asbestos removal
8
Civil Engineering RSSO meeting Repair of the TDC2 roof joints: 3 joints have been fitted with a metallic gutter driving water and bitumen to 3 retention boxes. Repair of the mezzanine floor: Resin flooring
9
Civil Engineering: drain network maintenance RSSO meeting Contractor Vallier checked all the manholes and inspection chambers High pressure cleaning Cleaning water collected and RP checked before disposal Sludge treated as radioactive waste
10
Civil Engineering: various repairs RSSO meeting New, extension of, repair to water collecting gutters Exchange of all remaining PVC pipes by PE pipes New drain connection
11
Heavy handling equipment RSSO meeting PR544 maintenance and test Power supply rail (feeding TT20 for transport vehicles) has been removed from TDC2
12
Magnet upgrade RSSO meeting One manifold dismounted in order to estimate time needed for future exchange Cooling flexible replacement completed in TDC2 (joints replaced) About 120 seals exchanged
13
Magnet upgrade Splitter rails and vacuum tank RSSO Meeting
14
Cabling activities Re-routing of 5 Cable trays (5x40m) Replacement of 70 DC and 42 control cables Installation of 10 new cables (new requests) Gangway Average 100µSv/h. Max: 500µSv/h Courtesy of I. Moya RSSO meeting
15
Cabling activities Control Power General services New situation RSSO meeting
16
Replacement of emergency and conventional light fittings Total 66 emergency light fittings (Not compliant with current standards) Total 338 conventional light fittings Replacement of AUG buttons Replacement of power distribution outlets Installation of cable distribution for vacuum pump heaters Emergency radiation resistant LED light fitting High Power LEDs hung from walkway TCC2 TDC2 Conventional light fittings Low voltage activities Courtesy of J. Devine RSSO meeting
17
Target refurbishment Preparation in EHN1 cleanroom: Production of new monitors and target boxes for target stations T2, T4, T6 & T10 + spare survey and vacuum & motorisation tests Courtesy of D.Grenier RSSO Meeting
18
T2, T4 and T6 target refurbishment In TCC2: Proximity cabling has been renovated Old monitors and target boxes remotely removed Dedicated shielded container for long term storage in B. 954 and 955. Re-installation of new monitors and target boxes currently in progress Courtesy of D.Grenier RSSO Meeting
19
Upgrade of 12 XTAX tables: Removal of spiral springs (screw protection) Jacks greasing Functional test of each tables Cleaning and maintenance of the base plates Realignment of XTAX4 XTAX table upgrade RSSO Meeting
20
Vacuum consolidation New beam pipes (100m) New ion pumps (10 units) Heated collars Vacuum consolidation RSSO Meeting
21
New TCSC collimator New beam instrumentation A few new units Maintenance of 40 beam instruments Collimator & beam instrumentation RSSO Meeting
22
Outline Objectives and schedule Completed activities Dosimetry analysis Conclusions RSSO meeting
23
Dosimetry analysis Dose breakdown by activity Accuracy of the estimate dose Dose breakdown by week Wish for the temporal breakdown Dose cost for free time Dose sharing between workers RSSO meeting
24
Estimate / Integrate dose RSSO meeting
25
Estimate / Integrate dose RSSO meeting
26
Estimate / Integrate dose Over estimate time and/or dose rate MSSB 460, 450 and 441 Removal In this case, incorrect estimate of dose rate RSSO meeting EstimateReal MagnetsTimeDoseTimeDose MSSB 220460803037284 MSSB 220450803035592 MSSB 2204418030367167 Total240909194343 Ratio 81%38%
27
Temporal dose distribution Radioactive decay : more waiting = less dose Handle highly activated equipment as late as possible (targets, XTAX,…) RSSO meeting
28
Temporal dose distribution RSSO meeting Cumulative dose TDC2 TCC2
29
Temporal dose distribution RSSO meeting ■ Real dose ■ Handle highly activated first The worst way to do … Dose is multiplied by 2
30
Keep a margin ? RSSO meeting Impact of two additional weeks before NA start up ?
31
Keep a margin ? What about the dose ? RSSO meeting 7% increase in dose for 15 days
32
Dose sharing RSSO meeting
33
Outline Objectives and schedule Completed activities Dosimetry analysis Conclusions RSSO meeting
34
Conclusions The TDC2/TCC2 consolidation activities have been successfully completed, within schedule, budget and without major problems. The corrective and preventive maintenance will reduce corrosion of the vacuum equipment and reduce machine downtime in the future operation of the beam lines. The strategy defined in the preparatory ALARA committees has proven to be very successful (decay time, planning optimization, staff training, remote control operation, 360° movie) However, individual dose management has been very challenging for some groups. Especially for experts (vacuum, targets, survey) resource management to improve (competition with other LS1 activities) Proposal: use a x-factor in future similar interventions. RSSO meeting
35
Pending issues RSSO meeting Chat de Schrödinger
36
Acknowledgements P. Catherine, M. Dumas, J. Bauche, P. Schwarz, M. Duraffourg, C. Vuitton, M. Hamani, R. Folch, D. Grenier, Z. Ajdid, M. Calviani J. Ferreira, T. Mongelluzzo, P. Chiggato, B. Rio, P. Debernard, R. Morton, A. Dodard, J-C Guillaume, D. Ricci, G. Gros, M. Da Costa, M. Dujardin, J-P. Billon-Grand, J. Pierlot, C. Crombez, S. Delarue, J. Devine, I. Moya, J-F Faure, A. Herve, Y. Pira, C. Theis, H. Vincke, L. Ulrici, Y. Algoet, M. Piccard, L. Gatignon, I. Efthymiopoulos, E. Harrouch, A. Bouvard, Y. Muttoni, C. Magnier, F. Galleazzi, A. Beynel, P. Bestmann, M. Troillet, S. Girod, A. Ebn Rhamoun, J. Etheridge, M. Bonnet, T. Wijnands, A. Pardons, J. Pedersen, Y. Seraphin, J-L. Grenard, C. Bertone, P. Brunero, P. Vallet, S. Deleval, A. Avian, B. Bannister, J. Lehtinen, F. Moro, R. Barrilliere, M. Baudin. RSSO meeting
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.