TDC2/TCC2 consolidation EATM 15/07/2014. EN/EL – DC and control cable identification and cut completed – Old light removal in TDC2 – New AUG installed.

Similar presentations


Presentation on theme: "TDC2/TCC2 consolidation EATM 15/07/2014. EN/EL – DC and control cable identification and cut completed – Old light removal in TDC2 – New AUG installed."— Presentation transcript:

1 TDC2/TCC2 consolidation EATM 15/07/2014

2 EN/EL – DC and control cable identification and cut completed – Old light removal in TDC2 – New AUG installed

3 Demin. circuit valve replacement Remplacement des vannes terminé

4 Unités de ventilation Travaux terminés.

5 XTAX upgrade 12/12 XTAX tables XTAX repaired Still alignment issue for XTAX T4 This week: survey & test on XTAX T6 + roof closure

6 Magnet Manifolds re-installed

7 OTND (Onet nucleaire) Nettoyage 3 eme chateau XTAX OK Démontage passerelle et chemins de câbles en cours

8 OTND (Onet nucleaire)

9 Oculus porte

10 Dose Most critical activitiesCollective dose in uSv 471594186 XTAX table upgrade4186 374052554 Removal, temporary storage and reinstall...2554 197361705 TDC2/TCC2 replace valves1705 438701630 Mesures topographiques TCC21630 447161526 Remplacement flexibles aimants TDC21526 483481104 démantèlement et nettoyage TDC21104 486641063 TDC2 Consolidation works EN/EL/CF - Phas...1063 TOTAL 25000

11 Planning