STUBBLEFIELD LAKE ROAD Head Wall Failure. THE HEAD WALLS ARE GIVING AWAY AND THE ROAD IS SINKING.

Similar presentations


Presentation on theme: "STUBBLEFIELD LAKE ROAD Head Wall Failure. THE HEAD WALLS ARE GIVING AWAY AND THE ROAD IS SINKING."— Presentation transcript:

1 STUBBLEFIELD LAKE ROAD Head Wall Failure

2 THE HEAD WALLS ARE GIVING AWAY AND THE ROAD IS SINKING

3 PILING TIMBERS HAVE GIVEN AWAY

4 EXACT DAMAGE IS NOT ACCESSIBLE UNTIL EXCAVATION BEGINS

5 This one is over four feet deep!!

6 LABOR COSTS Just recently Precinct 4 built bulkheads on Hostetter Rd. That project cost the county roughly $120 per foot. Stubblefield Lake Rd needs 180 feet of bulkheads constructed. $120/ft x 180’ = $21,600 *** This is just a rough estimate. ***

7 MATERIAL COSTS (STEEL) 38-7 5/8”Pilings, 8- 30’ x 5/16”sheet plate, 180’- 7”channel, 180’- 8”Angle, 40’-4” Angle, 40’-4” Flat Bar, 500’-3/4”Galvanized Cable, 50-3/4” Galvanized Cable Clamps $23,000.00 *** This is just a rough estimate. ***

8 ROAD MATERIAL COSTS Stabilized Sand 200tns * 30.14/tn = $6,028.00 Limestone Base 150tns * 24.59/tn = $3,688.50 Hot Mix 100tns * 67.69/tn = $6,769.00 $16,485.50 *** This is just a rough estimate. ***

9 APPROVAL REQUESTED Total Estimated Cost $61,085.50 Please approve purchasing to bid out this project.